Vertical Test Stand for ILC Cavities

Vertical Test Stand for ILC Cavities. Ruben H. Carcagno (for the VTS Team) ILC R&D Meeting Wednesday 11, 2006. Outline. Need for an ILC Vertical Test Stand (VTS) ILCTA_IB1_VTS Project Status Plan to increase VTS throughput. 26.5”. ILC Vertical Test Stand Function.

landis
Download Presentation

Vertical Test Stand for ILC Cavities

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Vertical Test Stand for ILC Cavities Ruben H. Carcagno (for the VTS Team) ILC R&D Meeting Wednesday 11, 2006

  2. Outline • Need for an ILC Vertical Test Stand (VTS) • ILCTA_IB1_VTS Project Status • Plan to increase VTS throughput ILC R&D Mtg 10-11-06

  3. 26.5” ILC Vertical Test Stand Function Low-power test of “bare” Cavities Measure Q vs. T (Tmin~1.5 K) Measure Q vs. Eacc at 2 K Only way to verify that an ILC cavity meets Q, Eacc specifications! ILC R&D Mtg 10-11-06

  4. Cavity Preparation Processes not Reproducible More than one vertical test/processing cycle is now needed per cavity to reach maximum performance Avoiding field emission is an ongoing struggle ! Graph from Lutz Lilje, KEK Mtg Sep. 06 ILC R&D Mtg 10-11-06

  5. ILC Cavity Baseline Yield too low around ILC performance baseline ILC R&D Mtg 10-11-06

  6. Main Sources of Reproducibility Problems • Imperfections in final surface treatment, • e.g. electropolishing (EP) • final rinsing • Field Emission from particle contamination • e.g. assembly processes • sulphur from EP acid • Thermal breakdown of superconductivity from material or manufacturing defects • Weld Problems at new industry • Deviation from specification • Insufficient quality control From Lutz Lilje, KEK Mtg Sep. 06 ILC R&D Mtg 10-11-06

  7. Vertical Test Stand Need • The need of making gradients more reproducible is a top priority • “S0” Goal: Achieve 35 MV/m at Q0=1010 in 9-cell cavity in vertical dewar tests (low-power) with a sufficient yield (> 90% for more than 100 preparation and test cycles). Two parts: • S0.1: Tight loop to improve “final preparation” yield • S0.2: Production-like activities to determine overall yield for cavity materials, fabrication and full cavity processing • S0/S1 Task Force • Hitoshi Hayano (KEK), Toshiyasu Higo (KEK),John Mammosser (JLab) Hasan Padamsee (Cornell), Marc Ross (FNAL), Kenji Saito (KEK), Lutz Lilje (DESY) • Wiki Site: http://www.linearcollider.org/wiki/doku.php?id=rdb:rdb_external:rdb_s1_home • Eventually a dedicated facility with sufficient redundancy and flexibility is desirable to have fast turn-around of cavity tests. From Lutz Lilje, KEK Mtg Sep. 06 ILC R&D Mtg 10-11-06

  8. Projected Total Number of Cavity Processes(from S. Mishra, ART FY08-09 Planning Meeting at SLAC 9/13/06) http://ilcagenda.cern.ch/materialDisplay.py?contribId=7&materialId=slides&confId=1114 Each process requires a Cavity Vertical Test ILC R&D Mtg 10-11-06

  9. 26.5” Vertical Test Stand at Fermilab • One VTS under construction in ILCTA_IB1 • Initial operation with single, bare, 1.3 GHz ILC 9-cell cavities but designed to accommodate up to two cavities (only one RF-powered at a time) • Maintain “Controlled Area” status in IB1 • < 5 mrem/hr immediately outside the shielding • <0.25 mrem/hr in normal working areas • VTS Team: Camille Ginsburg (Project Physicist), Cosmore Sylvester (Project Engineer), Y.Huang, R.Nehring, J.Ozelis, T.Peterson, V.Poloubotko, R.Rabehl, I.Rakhno, C.Reid, M.Wong • Expected to start operation in mid-2007 ILC R&D Mtg 10-11-06

  10. Radiation Shielding Designed • X-rays estimated from DESY data • Design from MARS15 simulation (I. Rakhno) has been approved by ES&H and is available as Fermilab-TM-2350-AD • Kamran Vaziri (ES&H) is our point-of-contact for radiation safety and permissions • Tritium production negligible • “Controlled area” satisfied ILC R&D Mtg 10-11-06

  11. IB1 Civil Construction Complete(August 2006) ILC R&D Mtg 10-11-06

  12. VTS Layout LLRF Cryo & Rad Inst. HPA & SW PC/PXI & RF Instr. ILC R&D Mtg 10-11-06

  13. Cryostat Order Placed • Design and procurement readiness review took place on May 16 (Review team: J. Theilacker (Chair), T. Nicol, P. Pfund) • Two bids received: Meyer Tool and PHPK • After technical & price bid evaluation, PHPK selected • Purchase order placed Sept. 20 • Magnetic Shielding design complete and ready for procurement • Cryostat installation in VTS pit scheduled for March 2007 ILC R&D Mtg 10-11-06

  14. RF Design Complete • Based on proven Jlab VTS RF system with improvements • Collaboration with Jlab established (added to Jlab MOU scope) • Reviewed on August 24. Review Team: R. Pasquinelli (Chair), J. Steimel, B. Chase, C. Worel, J. Reid, W-D. Moeller) 24.August • Most procurements have been placed • RF personnel safety interlocks in progress, with Chuck Worel (AD/ES&H) ILC R&D Mtg 10-11-06

  15. Tie-in Design to IB1 Cryo System Complete • Most procurements have been placed • Process Control Logic Description Document available Detailed P&ID ILC R&D Mtg 10-11-06

  16. Radiation Shield Lid Cover under Mechanical Design Example: Cornell VTS Cover ILC R&D Mtg 10-11-06

  17. Top plate insert under design Example: Jlab VTS Top Plate Example: Cornell VTS Top Plate ILC R&D Mtg 10-11-06

  18. Project Schedule Detailed MS Project Schedule Available ILC R&D Mtg 10-11-06

  19. FY07 Activities • Receive cryostat, install magnetic shielding, and install into prepared pit • Procure and assemble top-plate assembly • Fabricate and install radiation shield lid • Install Cryogenics • Install RF, controls, instrumentation, etc. • Install radiation safety interlock system • Commission test stand • Begin cavity tests ILC R&D Mtg 10-11-06

  20. IB1 VTS Capacity • Given the increased need for VTS throughput to satisfy S0 R&D goals, a team was put together to analyze the IB1 VTS peak capacity, feasibility of additional VTS stands, and IB1 infrastructure upgrades requirements • Analysis Team: Ruben Carcagno, Camille Ginsburg, Yuenian Huang, Arkadiy Klebaner, Joe Ozelis, Tom Peterson, Clark Reid, Cosmore Sylvester • This work is in progress, and following is a status of preliminary findings and recommendations ILC R&D Mtg 10-11-06

  21. Single VTS Throughput • Throughput Assumptions: • Single shift operation • Cavity arrives hermetically sealed • 120 °C bakeout done prior to IB1 delivery • “Production” Q vs. E test only (e.g., no 8-hr pause at 100K during cooldown to determine degree of H contamination (Q-disease)) • Two cavities in a VTS cryostat • Only one RF ON cavity test at any given time ILC R&D Mtg 10-11-06

  22. Unconstrained Test Cycle Schedule (Nearly) Unattended Operation ~ 28 hours Attended Operation ~ 11 hours TOTAL (unconstrained) ~ 39 hours ILC R&D Mtg 10-11-06

  23. Adding Constraints • Shift Operations • 11 hours of attended operations require a minimum of 23 hours because of 12-hour pause between 8-hour shifts • Inefficiencies (idle time due to shared resources, equipment availability, troubleshooting) • Add ~ 24 hours • Total Test Cycle ~ 75 hours or ~ 3.12 work days for two cavities. • Assuming 8 work weeks of maintenance and other facility down time per year: Single VTS throughput ~ 70 double-cavity test cycles per year (140 test processes) ILC R&D Mtg 10-11-06

  24. How to (quickly) increase throughput? • Two additional VTS stands can be added to the IB1 facility by relocating the ILCTA_IB1 Horizontal Test Stand (HTS) planned for FY07 to ILCTA_MDB. • Throughput can increase to ~ 3x140 = 420 test processes per year • Some throughput increase might be possible by adding shifts and removing inefficiencies • Substantial additional throughput increase only possible by building modifications and/or a building addition. Cryogenic capacity becomes a limiting factor (tie-in to CHL after Tevatron shutdown?) ILC R&D Mtg 10-11-06

  25. Phased Approach for a Vertical Cavity Test Facility (VCTF) • Phase I • Complete VTS under construction by mid-2007 • Phase II • Add two more (nearly) identical VTS stands by mid-2008 • Phase III • Add one or more high-throughput VTS stands in a modified or new building addition plus additional cryogenics capacity ILC R&D Mtg 10-11-06

  26. IB1 SRF Test Area Layout Vertical Test Area (FY06) (Bare Cavities) Existing Cryo Piping ILC R&D Mtg 10-11-06

  27. IB1 Layout for Phase II Trench for cryo piping Door Radiation Lid “park” area Stairs Additional VTS Vertical Magnet Test Facility (VMTF) Staging Area VTS under construction Tie-in to test stands cryo distribution box ILC R&D Mtg 10-11-06

  28. Conceptual 3-D Model of a 3-VTS Facility plus staging area ILC R&D Mtg 10-11-06

  29. VTS Staging Area Platform with 2 top plates per VTS needed for multiple VTS facility Example: Jlab VTS Platform Example: KEK VTS Platform ILC R&D Mtg 10-11-06

  30. IB1 FY07 Test Schedule and Civil Construction(Window during Feeder 47 and Cryo Maintenance Upgrade April-May 07) ILC R&D Mtg 10-11-06 : Magnet Dept. Support : SRF Dept. Support : IB1 Maintenance : New development needed for test

  31. IB1 Infrastructure Considerations • The IB1 Test Facility shares cryogenics and people with a very active Magnet Test Facility (MTF) • It is essential to decouple cryogenic operations between MTF and the Vertical Cavity Test Facility (VCTF) • There should be adequate cryogenic resources available to sustain both MTF and VCTF test programs. This includes both LHe inventory and pumping capacity for superfluid operation ILC R&D Mtg 10-11-06

  32. Infrastructure Requirements • Add a third vacuum pump to increase pumping capacity from 6 g/s at 20 Torr to at least 10 g/s • Add a compressor/purifier at the outlet of the vacuum pump system to mitigate contamination risk • Add more GHe storage capacity to store the majority LHe inventory as gas • These upgrades are needed to meet peak throughput of either one VTS or multiple VTS ILC R&D Mtg 10-11-06

  33. Current Plan for single VTS integration to IB1 ILC R&D Mtg 10-11-06

  34. Multiple VTS Integration to IB1 ILC R&D Mtg 10-11-06

  35. How much pumping? • For baseline E = 35 MV/m, Q0 = 1010 the power dissipation is: • Substantial margin is needed to continuously operate at higher gradients and/or lower Q. • Constraints: JT Heat Exchanger and Pumping Capacity (6 g/s at 2 K) ILC R&D Mtg 10-11-06

  36. JT Heat Exchanger Pumping Limit With the current VTS JT Heat Exchanger design, practical limit for continuous 2K operation is around 8 to 10 g/s (160 to 200 Watts) due to excessive shellside pressure drop To remove more than 200 Watts (10 g/s pumping) continuously, a redesigned JT Heat Exchanger must be used in future VTS. This may require an adjustment to the cryostat (and pit) diameters. ILC R&D Mtg 10-11-06

  37. IB1 Pumping Capacity • Installed: 6 g/s at 20 Torr • Kinney Pump I: 4 g/s • Kinney Pump II: 2 g/s • Need more pumping: • Margin for higher gradients and/or lower Q continuous operation • Simultaneous operation of superfluid magnet test and cavity test • Need a new, dedicated, large (13 g/s) vacuum pump for VTS stands, similar to the one installed at ILCTA_MDB for HTS testing. Use existing pumps for magnet testing. Kinney Pump Installed at ILCTA_MDB for the HTS ILC R&D Mtg 10-11-06

  38. Compressor/Purifier • Contamination is already one of the largest reason for IB1 cryo system unscheduled downtime and loss of efficiency • Addition of sub atmospheric test stands will make this problem worse • Need a high pressure compressor andpurifier skid to remove all contamination at the outlet of vacuum pumping system (like the one recently installed at ILCTA_MDB). • This is a high-priority item Compressor/Purifier installed at ILCTA_MDB at the outlet of Kinney Pump for HTS Testing ILC R&D Mtg 10-11-06

  39. LHe Availability • IB1 cryo system LHe make rate: ~ 250 l/hr (9 g/s) • VTS LHe consumption per test cycle: ~ 2,000 l (equivalent to 27 l/hr for a 75-hr test cycle) • For three VTS stands operating continuously: 3x27 = 81 l/hr • On average, there is still ~ 170 l/hr LHe make rate available to support magnet testing. Need adequate LHe and GHe buffer storage to satisfy peak demands for both Magnets and Cavity testing programs ILC R&D Mtg 10-11-06

  40. IB1 LHe and GHe storage • A 10,000 liter He dewar stores up to 7,000 liter of LHe • Three 30,000 Gallon GHe tanks store up to 3,900 LHe equivalent He gas (only 55% of LHe inventory capacity) • Need two more 30,000 Gallon tanks to store the majority of LHe inventory as gas ILC R&D Mtg 10-11-06

  41. Preliminary M&S Cost Estimate ILC R&D Mtg 10-11-06

  42. VTS Project Challenges • Aggressive schedule (Phase I ready by mid-2007, Phase II by mid-2008) • Must minimize disruption to the Magnet Test Program • Requires experienced resources outside of T&I department (e.g., AD-Cryo, FESS) • Must be a Laboratory High Priority Project • Requires adequate funding • Schedule-driven nature of project dictates need to procure turn-key skids from industry as much as possible (e.g., Compressor/Purifier, Kinney Pump) ILC R&D Mtg 10-11-06