An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Vertical Test Stand Update C.M. Ginsburg (Fermilab) For the VTS group: C.Sylvester, Y.Huang, R.Nehring, J.Ozelis, T.Peterson, V.Poloubotko, R.Rabehl, I.Rakhno, C.Reid, M.Wong 02.November.2006

  2. VTS Cryostat • Preparations for fabrication underway at PHPK (Columbus, OH) • Biweekly phone conferences • 3 change orders by end of this week (2nd top plate, holes in top plate, attaching ring segments) • Fermilab supplied instrumentation on its way • Valves from Cryolab (Leslie Controls, Inc.) are 2 months late; so far not affecting schedule • We are impressed by PHPK’s commitment to keeping schedule, and working with us to fulfill requirements • Magnetic shielding purchase requisition by the end of this week C.M.Ginsburg ILC/SRF 05.Nov.06

  3. More VTS progress • Radiation Shielding (Igor, Valeri) • Shielding design update by Igor for updated (realistic) geometry; technical memo update soon • Shielding lid layout and movement by Valeri well advanced; beginning costing • RF System (Joe, Roger) • Assembly and in-house fabrication underway and on schedule • All components including racks have arrived except vector modulator (ok) • 500W CW amplifier specs to be measured by John Reid • MFR Ophir: performs better than specs • Cryo system tie-in has begun (Yuenian, Charlie Hess) • Variable coupler design (Andrei Lunin) and thermometry system design (Aseet Mukherjee) underway for beyond-the-baseline C.M.Ginsburg ILC/SRF 05.Nov.06

  4. Planning for operation (ORC) • Electrical Safety (Jim Garvey) • General Safety (Rich Ruthe) • Cryo-mechanical Safety (Bill Soyars (AD)) • Engineering documentation to be available one month before desired operation • FMEA, What-if analysis underway (Mayling) • Radiation Safety (Kamran Vaziri (ES&H)) • Kamran is up to speed on expected radiation and shielding design - so far so good • RF personnel safety interlocks design by Chuck Worel (AD) and Joe submitted to Kamran Oct. 27 • Plan for location of area radiation monitors and operational procedures with Sue McGimpsey (ES&H, Acting Radiation Safety Officer for VTS) underway C.M.Ginsburg ILC/SRF 05.Nov.06