1 / 48

State of water infrastructure

Presentation to the Portfolio Committee: Water & Environment. State of water infrastructure. Presentation by Dr C Ruiters Deputy Director-General: Water Resources Infrastructure 26 - 27 January 2011. Presentation overview. Background Macro Planning: Integrated Water Resources Planning

lbenavides
Download Presentation

State of water infrastructure

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Presentation to the Portfolio Committee: Water & Environment State of water infrastructure Presentation byDr C RuitersDeputy Director-General: Water Resources Infrastructure 26 - 27 January 2011

  2. Presentation overview • Background • Macro Planning: Integrated Water Resources Planning • Infrastructure Developments • Condition of existing infrastructure • Dam Safety Rehabilitation and Refurbishment Programme (DSRP) • Strategy on Access to Water for Basic use from Dams • Regional Bulk Infrastructure 2

  3. 3

  4. 2. Macro Planning: Integrated Water Resources Planning Policy and Regulation Branch (Chief Directorate: Integrated Water Resources Planning) custodian National Water Resource Strategy - 19 WMA Interventions and various options to address deficits are continuously assessed (Option Analysis) e.g. reconciliation strategies, all town and city studies, planning requirement documents. Infrastructure development informed by rigorous planning process 4

  5. 3. Infrastructure Development

  6. 1. Schemes completed since 2004 6

  7. Major water resource infrastructure development projects • MOKOLO AND CROCODILE RIVER (WEST) • AUGMENTATION PROJECT • 7 million m3 water for ESKOM (Medupi PS) • and 5 million m3 water for domestic use • - Direct Jobs: 250 • OLIFANTS RIVER WATER RESOURCES DEVELOPMENT PROJECT (de Hoop) • 40 million m3 of water for domestic use and 40 million m3 water for mining • - Direct Jobs: 800 VAAL RIVER EASTERN SUB SYSTEM AUGMENTATION PROJECT - 96 million m3 of water for ESKOM and 64 million m3 of water for SASOL 7 • KOMATI WATER SYSTEM • AUGMENTATION PROJECT • 54 million m3 of water for ESKOM • - Direct Jobs: 466 2 461 1 4 • MOOI MNGENI TRANSFER SCHEME (PHASE 2) • 60 million m3 of water for domestic use • - Direct Jobs: 450 3 5 • CLANWILLIAM DAM • 70 million m3 of water • for existing and new • irrigation farmers • - Direct Jobs: 678 Durban 6 • HAZELMERE DAM • 10 million m3 of water for domestic use Cape Town

  8. Augmentation projects (1) 8

  9. Augmentation projects (2) 9

  10. LEGEND SUPPLY AREAS EXISTING BULK WATER PIPELINES ORWRDP PIPELINES WATER SERVICES BULK PIPELINES ESKOM PSS INFRASTUCTURE ORWSDP: WATER SERVICES DEVELOPMENT Olifants-Sand RWS POLOKWANE MOKOPANE STRYDPOORT MOUNTAINS LEBOWAKGOMO Olifantspoort South RWS Lebalelo RWS Mphahele and Groothoek RWS BURGERSFORT MOOIHOEK Tubatse RWS JANE FURSE Flag Boshielo RWS STEELPOORT TOWN FLAG BOSHIELO DAM Nebo Plateau RWS DE HOOP DAM MOTOTOLO EPSS 10

  11. 5. Existing Infrastructure 11 11

  12. Summary of extent and value of immoveable assets controlled by the Department (Mar 2010 – R million) 12 12

  13. 5.1 Age Profile of Assets 13

  14. 5.2 Age profile of assets 14

  15. 5.3 Remaining Useful Life RUL profile with capital renewal values 15

  16. 5. DAM SAFETY REHABILITATION PROGRAMME (DSRP) • 359 dams on the asset register (218 listed in the ICOLD world register of large dams) • Rehabilitation work on 22 dams complete • 36 dams in various stages: feasibility study, detailed design or construction

  17. Rehabilitation done due to: • Insufficient spillway capacity: 80% • Slope stability problems: 10% • Inadequate maintenance eventually resulting in dam safety problems: 60% • Geological/foundation problems: 10% • Inadequate outlet systems: 80% 17

  18. 18 18

  19. Progress • Total Expenditure till Sept 2010: R1 200m • Dams on programme: 58 19

  20. 6. Strategy on Access to Water for Basic use from Dams 20

  21. Introduction 21 Communities in rural areas that live in close proximity to water sources and networks have been identified throughout South Africa that do not as yet have access to sufficient and safe water to fulfill their basic needs. This issue is of serious concern for DWA who has decided that urgent action be taken in order to ensure that the basic constitutional rights of these communities are fulfilled. This project is aimed at supporting the DWA to identify communities that live in close proximity to DWA dams that do not as yet have access to water for basic domestic use. It is envisaged that the final output of this project will be a report identifying these communities without access to basic water for domestic use and providing potential solutions to the identified service delivery problem.

  22. Scope of Work Envisaged by DWA 22 • Conduct a survey of communities in close proximity to the dams as by DWA in the list below in order to ascertain which communities do not have access to a basic domestic water supply • Assess what water is available from these dams. • Determine impact of allocating some of the water from the relevant dam to communities without a basic domestic water supply. The National Water Act states that the provision of water for basic human needs is a priority issue. • Determine the level of service to be provided.

  23. Scope of Work Envisaged by DWA 23 • Ascertain existing infrastructure in the area. • Determine the possible infrastructure requirements to supply potable water to the community. • Determine the estimated capital and operational costs of this supply. • Determine the estimated timeframe required to supply the infrastructure.

  24. Dams Identified by DWA 24 24

  25. Overview of Approach Followed 25 25

  26. Approach 26 Phase 1 : Determine Location of Dams and Communities Phase 2 : Consultations with Relevant WSA’s Phase 3: Identify Possible Infrastructure Solutions Phase 4: Financial and Time Implications for Proposed Infrastructure per Dam Phase 5: Institutional Issues

  27. General Comments 27 • Currently the provinces that are focused on is: • Limpopo • North West • Eastern Cape • The full amount of funding indicated to conclude all activities was not available from inception • Therefore the aim is to conclude the full life cycle for them before commencing with the other regions to estimate what funding is remaining. • A time delay could occur if the All Town Study information is delayed due to some of the areas not yet concluded.

  28. Regional Bulk Infrastructure

  29. Is to develop an oversight and support function that will ensure the development and operational and maintenance of regional bulk infrastructure in the water sector. 1- Overview Strategic purpose 29

  30. Objectives of Programme 30 • Identify all regional bulk project requirements, through appropriate integrated planning processes. • Assist with the funding and implementation of regional bulk infrastructure projects through RBIG. • Facilitate the development of institutional arrangements and capacity to ensure the implementation and effective operations and maintenance of regional bulk infrastructure.

  31. 2 – Progress to date 31 31 109 projects were started since 07/08 financial year. 50 implementation projects have been initiated and are in construction, design or tender phase of which 36 are in construction and 14 are in design / tender phase 42 feasibility / implementation ready studies are ongoing. 17 projects have been completed.

  32. Projects completed 2007/08 Chris Hani Tsomo RDP2 BWS Delmas Phase 1 Emergency ThabaChweu BWS 2008/09 Delmas Phase 2 Maqwassi Hills RWS 2009/10 Mbhashe North BWS Mathulini BWS Greater Mthonjaneni BWS Phase 1 Van Wyksvlei Interim Solutions Van Der Kloof/Petrusville BWS Mjejane BWS 32 32

  33. Projects completed (continue) 33 33 2010/11 Mthatha Bulk Water Intervention Malangeni Waste Water Treatment Plant Greytown BWS Mbombela Water Supply Hoxani BWS Kenhardt BWS

  34. Budget allocated categories 34 • 85%-90% for project implementation • 10%-15% for feasibility studies and Implementation Ready studies • R 20 –R 30 million for project and programme management

  35. Budget allocation 35 35 Previous financial years 2007/08 and 2008/09 2007/08 R 300.0 million 2008/09 R 443.4 million 2009/10 R 618.2 million 2010/11 MTEF Allocation 2010/11 R 893.0 million 2011/12 R 1 675.3 million 2012/13 R 1 849.1 million

  36. 3: Allocations & needs 36 of benefiting municipalities to date Eastern Cape - 13 Free State - 4 Gauteng - 2 KwaZulu-Natal - 11 Limpopo - 7 Mpumalanga - 5 Northern Cape - 9 North West - 4 Western Cape - 6

  37. 2010 MTEF allocations (old) 37 37

  38. New MTEF 2011 38 2011/12 MTEF Allocation 11/12 R 1 775.3 m increase by R 100 m 12/13 R 2 233.1 m increase by R 384 m 13/14 R 2 418.8 m increase by R 468 m Total R 6 427.2 million There is an increase of approximately R 952 million

  39. Comparison: backlog and RBIG funding Urban –metro areas given less priority Housing and water scarcity sanitation and water scarcity 39

  40. 4 Alignment / Transparency 40 • CoGTA requires DWA to align RBIG with needs and all water related projects • Dep. of Human settlement is blaming other departments responsible for bulk of been responsible for constraints to service delivery Cape Time Nov 25 th 2010, p6 Problems with the provision of bulk infrastructure are stifling housing delivery across the country, says Human settlements Minister, Tokyo Sexwale….. Thus the need for a more integrated, planned and coordinated approach across various departments…

  41. Alignment 41 • Projects are motivated by WSA, therefore how can there be misalignment ? • The problem is that due to limited funds, RBIG • Has not initiated any new projects in the last 2 yrs (policy is to complete existing projects before new ones are initiated) • A significant gap exists between bulk infrastructure needs and budget available.

  42. Alignment with other programmes 42 The following alignment between RBIG and MIG are required and therefore proposed: • Scope of projects by each programme • Overlapping budgets and co-funding • Criteria / conditions for project approval • Integration of planning needs • Monitoring and evaluation procedures of project implementation

  43. Successes 43 • The programme was expanded from a 3 year term to a long term programme • The programme has expanded from R 300 million / annum in 2007/08 to R 2 418 million / annum in 2013/14 • A consolidated list of all bulk needs / projects has been developed and is been updated through 9 Regional bulk Master plans. • New innovative projects implemented (i.e desalination and Waste Water recycling) • Significant amount of new jobs created (6017 jobs). • Inter –governmental co-operation (particularly WC, & FS)

  44. Regional Bulk Expenditure 20 January 2011 44

  45. 6: Expenditure With invoices not yet processes R 490 m. 45

  46. New project management priorities 46 • DWA to take greater/direct control for implementing new RBIG projects in weak WSA utilising: • Project management capacity from DWA • Utilising the capacity of Water Boards • Utilising DWA construction • Private service providers (i.e BoTT) • Identify new institutional arrangements and models • Focus on sustainability of projects and O & M • Ensure conditions of IRS are followed through • Focus on improving agreements with WSA and DWA

  47. Conclusion 47 Most RBIG projects are large projects that require, appropriate water sector expertise for planning and implementation, they should not be entrusted to officials and institutions with limited expertise and capacity Although expenditure is slow , most funds will be utilised by the end of the financial year RBIG has been successful but not without problems

  48. THANK YOU 48

More Related