1 / 8

Personnel Protection System Status

Update on the status of the personnel protection system for the Patrick Bong SLAC project, including engineering progress, certification procedures, procurement updates, installation status, and project team updates.

lenorah
Download Presentation

Personnel Protection System Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Personnel Protection System Status Patrick Bong SLAC Personnel Protection Systems Group

  2. Schedule • Engineering • Injector drawings are complete • Downstream engineering is beginning • Installation • In process • Scheduled to be complete by November 10 • Certification • Procedure due October 30 • In process • Using a standard template • Scheduled for December 18 • Turn On • Jan 2 - VVSs on for PEP • Jan 15 - start L0A and L0B RF processing

  3. Engineering • Injector Final Design Review • External reviewers • Minor changes were incorporated into the design • Radiation Safety Committee • Approval to proceed with PLC hardware • Approval came later than anticipated, but well within schedule parameters • Requested to see the certification procedure • BTH, Undulator, NEH, FEH • Cableplant design has just started • Design efforts will stop when certification begins in November and start again in January 2007 • Planning on using hardware and PLC software that is similar to Injector design to reduce engineering effort

  4. Procurement • Injector hardware is on site • Beam Shut Off Ion Chambers (BSOIC) • BSOICs are extremely long lead items • Five to Six month lead time from Apantec • Injector BSOICs are arriving too late to use • Plan B is to use SLAC Classic BSOICs • Downstream hardware count must be determined soon • Purchase should occur in November • Most hardware is 90-120 day lead • Cable and hardware will be purchased in January and February 2007

  5. Installation • Injector installation has fallen behind schedule • Racks arrived late • Moving an electrical disconnect held up work • Installation is starting to catch up with schedule • The modularity of the PLC hardware greatly simplified wiring • We expect to make our November 10 schedule • Two chassis are in fabrication due November 6 • Plan B • There are five weeks between November 10 and December 18 when a technician could complete the system

  6. PPS Rack with Operational LSS

  7. Project Status • Personnel • The PPS group added two engineers a designer and a technician • A requisition for another engineer has been posted • Design • Conventional Facilities • Drawings were checked and changes made to accommodate the PPS • BTH, Undulator, Dump, FEE • We have had several preliminary design talks and engineering efforts are beginning • NEH and FEH • The PPS specification in being written based on the LUSI experimental hutch layout

  8. Summary • RSC Approval for PLC based PPS • This is the first use of PLCs in the PPS at SLAC • This is the end of a five year development program targeted at using PLCs in the PPS • Laser Safety System • Laser Bay is already running using PLCs • Injector housing LSS will be completed with PPS • PPS appears to be on schedule • No major worries

More Related