1 / 24

Report to the Operations Sub-Committee July 7, 2006

This report provides an update on operations, including hiring progress, authorization and concurrent review updates, new processes for home-based services, outpatient services, and IVR/Web technology implementation.

Download Presentation

Report to the Operations Sub-Committee July 7, 2006

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Report to the Operations Sub-Committee July 7, 2006

  2. Operations Update • Hiring • 95% of Key Positions • UM Director position currently open • 98% Overall • 3 Peer Specialists • 1 ICM clinician

  3. Authorization and Concurrent Review Update *duplicates cleaned in June

  4. Operations Update, con’d • Inpatient Auth to Claims: 7/1/2006 • Care Coordination and Crisis Stabilization new auth process pended – need to finalize level of care criteria • Home based Services: 8/2006 • MST, IICAPs, MDFT, FFT for dates of service 8/1/06 and after will be auth’ed via clinician. Winfax process will capture members currently in care • FST will register via web registration in August and back date start date to capture individuals in care from August 1, 2006 and forward as a registered service vs auth’ed service

  5. Operations Update, con’d • Outpatient Services via web registration: • 9/2006 for services provided for dates of service 9/1/06 and forward • IVR/Web technology: 8/2006-9/2006 • Provider Trainings to be held in July and August • Web technology available August 2006, mandated to ensure payment effective September 1, 2006 • Providers will begin registering care in the system in August, will provide an additional 30 day window through September • Interim plan (possibly winfax) as alternative to web registration • Modified IVR/winfax technology October 2006

  6. Operations Update, con’d • Pre-Certification Call Duration • Reviewed Avaya phone system to test capability • More focused reporting has been programmed • Average call length: 16:53 min:sec • Maximum call length: 21:33 min:sec • ICM Activity • 186 total cases • 58 referred in June, 55 accepted • 19% of total referrals from inpatient psychiatric units • 34% of total referrals from internal source • Other referral sources include: MCO’s, DCF, self referral, Residential and EDs • Referrals from EDs decreased by approximately 65% since March

  7. Operations Update, con’d • ED Interface • Decrease in call volume from EDs. Instituting daily outreach calls effective July 1, 2006 • Delay in Discharge (Inpt., PRTF, Resi) • 6% of all clients in 24 hour LOC have discharge delays • 20% of the 6% represent delays from inpatient care • 20% of the 6% represent delays from PRTF • 60% of the 6% represent delays from residential • Majority indicate the family is requesting additional treatment

  8. Stuck ED Volume June 2006

  9. Call Management/Customer Service

  10. CT BHP Call ManagementJune, 2006*Please note: MCO and 211 totals are calculated in “member” total monthly calculation.

  11. Types of InquiriesJune, 2006 38% - Provider Referrals for Members 18% - Member Eligibility Verification 39% - Provider Related/Authorization/Enrollment/Billing 5% - General Information43% = Member Inquiries 0.01% = Inquiries initiated due to provider status change from IN to OON Type and percentage of calls remains relatively the same as May, 2006

  12. CT BHP CALL MANAGEMENTIncoming Calls Totals: June 2006 Total 4892 Increase of 215 calls over May, 2006

  13. Network Operations

  14. Network Operations/Status • Provider Handbook • Posted to the website June 14 2006 • Feedback appreciated • CMAP Network as of June 26, 2006 • 1,435 Total Providers • 519 Facilities • Individual Providers • MD and MD Groups: 381 • LCSW: 308 • LMFT: 122 • LPC: 82 • Add/Change report: 0-5 adds per week, 5-10 changes • DCF Network • 122 RTC and Group Home providers (Increase of 36 providers since 11/2005)

  15. Cycle date 051906 we have identified the following issues: 16 inpatient providers put data in auth line 7 IOP/PHP providers submitted claims without prior authorization Outreach calls were provided to the high level denial providers Cycle date 060906 we have identified the following issues: 343 Claims were submitted without authorization; 51 Claims were submitted outside the effective authorization dates; 43 Claims were submitted with the incorrect authorization number; 31 Claims were submitted with an invalid provider number; 17 Claims were submitted by Out-of-State providers without receiving prior authorization; 14 Claims were submitted after the effective authorization dates; Rapid Response Team Findings

  16. Rapid Response Team Process • The Rapid Response Team is composed of representatives from CTBHP, DSS and EDS: • The RRT meets bi-weekly to review any denial issues; • CTBHP produces a detailed report of provider claims that directly correlate with the reports forwarded by EDS; • CTBHP works in concert with EDS to resolve claims issues. • Providers are contacted and the denial(s) are reviewed for resolution; • CTBHP’s outreach contributes to building the relationship with the Network and providing cohesion across the departments;

  17. Rapid Response Team Process Cont’d • Reviewed claims issues for 26 providers, follow up included: • 16 Outreach Calls to providers; • Claim information was faxed and issues were resolved for 4 providers; • 3 Providers pending response from EDS Provider Assistance Center follow-up; • 1 Provider presently remains in review with RRT;

  18. Quality Management

  19. Quality Initiatives, con’d • Satisfaction Surveys • Member, Member with Complex Needs and Provider Surveys • Data collection will begin in June and July for the provider survey and conclude in late summer, early Fall – completed via phone interviews • Provider report complete Fall of 2006 • Member Survey presented to Quality Sub-Committee, feedback to be incorporated • Member Survey roll-out Fall of 2006

  20. Complaints and GrievancesJanuary – June 2006 • Complaints: 30 from January to June 23rd. 5 member complaints in June: 2 Quality of Service, 2 Quality of Care, 1 concerning member wanting to use an Out of Network provider • Grievances: 3 from January to June 23rd. None in June. All Complaints and Grievances were resolved within standard timeframes

  21. Community Outreach

  22. Community Outreach • June, 2006 • Systems Managers 91 DCF, Provider, Collaborative and MSS meetings in June 551 Meetings year to date • Peer/Family Meetings 49 Family forums, informational meetings, DCF and Collaborative meetings, 2 Staff attended NAMI conference in Washington DC • Peer/Family Outreach/Coordination: 41 Open family/peer consultations in June (68% increase from May) 19 Family/peer consults completed in June

  23. Local Area Development Plans • Preliminary plans submitted to the Departments on June 30, 2006 • Departments will review over the next 30 days • Final submission due September, 2006 • Statewide themes and regional variation • Sample of general issues: • Recognized commitment for continued change/reform • Determination to expand community-based services, while strengthening local service system development • System gridlock, lack of coordinated system infrastructure and accountability, lack of integration of resources, knowledge and strategies across advisory groups

  24. Questions?

More Related