260 likes | 372 Views
ADMINISTRATIVE SYSTEMS Information Session April 23, 2013. PRESENTATION OVERVIEW. Project Status Overview UCPath Kronos Financial System Comments & Questions. MASTER TIMELINE. UCPath. UCPATH: GOAL. A UC system-wide project to streamline and standardize
E N D
PRESENTATIONOVERVIEW • Project Status • Overview • UCPath • Kronos • Financial System • Comments & Questions
UCPATH: GOAL A UC system-wide project to streamline and standardize payrolland human resources processes across all UC locations.
UCPATH: STATUS Biweekly Pay & Factor Leave Accrual Transition Resources at pmo.ucsb.edu Project Schedule Wave 1: July 1, 2014 – Los Angeles, Merced, Santa Cruz Wave 2: January 1, 2015 – Davis, Riverside, San Diego Wave 3: July 1, 2015 – Santa Barbara, Berkeley, Irvine & San Francisco
UCPATH: FOUNDATIONAL BLOCKS Governance & decision making process Wide representation while keeping groups small System configuration Ongoing dialog with UCPath PMO & other UCs Implementation plan System-wide vs. local work
UCPATH: NEXT STEPS Analysis & redesign of current business processes • Alignment with UCPath Center • Work smarter Implementation plan • Work sequence, timeline, and staffing needs • Begin Waves 2 & 3 implementation on May 13, 2013
KRONOS: GOAL Implement Kronos as the official campus timekeeping system
KRONOS: STATUS Advisory Committee Resources Variable Multiple Funding Sources Functionality Campus Deployment Next Steps
KRONOS: ADVISORY COMMITTEE Jeanie Cornet, NRI Laurie Eusey, ICB Maureen Evans, MRL Sandra Hammonds, Physics Mike Moore, ECE Kathy Murray, Film & Media Juli Pippin, Engineering Lynne Pritchard, Psychology Dorothy Satomi, EVC’s Office Donna Trimble, Chemistry Joyce Wolever, MSI
KRONOS: RESOURCES Project Manager We are hiring someone to coordinate resources. Kronos Support We have contracted for more support services from Kronos.
KRONOS: FUNCTIONALITY Testing Fixed allocation rules are a potential enhancement for the existing Kronos Workforce Central installation that will allow: • tracking variable multiple funding sources on timecards • processing timesheets for employees with multiple distribution numbers
KRONOS: DEPLOYMENT Active Users 5,100 UCSB employees are now using Kronos Student Affairs Almost all SA employees are now using Kronos University Center Scheduled to complete deployment in August
KRONOS: NEXT STEPS • Finish Project Manager recruitment • Standardize timekeeping practices • Finalize technical requirements • Develop deployment timeline
FINANCIAL SYSTEM: GOAL Implement PeopleSoft Financials Get off the current mainframe Business process review
PHASE 1 DELIVERABLES After go-live, you will not notice major changes. The risk associated with the mainframe will be mitigated.
PHASE 1 SCOPE General Ledger (G/L) Chart Of Accounts (COA) Purchasing Interface from Gateway Accounts Payable (A/P) Budget Ledger (Commitment Control – KK) Asset Management (AM) Project Costing (PC)
PHASE 2 SCOPE Accounts Receivable Grants Contracts Billing
WHAT ARE WE DOING? Data Conversion & Validation Complete data mapping from old system to new system. Hired a 3rd party company to extract data from the mainframe using the new data mapping format. Validate data against the existing mainframe reports. This processes helps us validate the data mapping and the data conversion programs.
WHAT ARE WE DOING? Developing Interfaces Real-time application programs (TOE, TOF, WEBTV, BARC, FORM-5, etc…) Middleware (SHIM) PeopleSoft to Data Warehouse