1 / 7

Endcap Module Status

Endcap Module Status. Agreed Responsibilities Overall Production UK Situation Global Schedule Issues General Production Issues. Agreed Module Distribution. Overall Production. Proceeds smoothly ~816 module starts (35% of total) 70% tested of which

leroy
Download Presentation

Endcap Module Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Endcap Module Status Agreed Responsibilities Overall Production UK Situation Global Schedule Issues General Production Issues

  2. Agreed Module Distribution

  3. Overall Production • Proceeds smoothly • ~816 module starts (35% of total) • 70% tested of which • Yield: 88% (good), 92%(good+pass) Still OK but seems to be dropping slightly • Components: • No stocks building up for spines or hybrids • Very vulnerable to component delays http://ific.uv.es/~lacasta/ECproduction/

  4. Site Starts Bonded Unbonded Good Tested Total Incomplete Failing Tested OK Fail Total UK Outers in Database as of 31/8/04 UK Middles in Database as of 31/8/04 Thanks to Joe Foster for summary

  5. Overall Schedule UK Modules • Still some delay • Foreseen to finish last module by end June 2005 • GVA and MPI have increased their production rates • Could be earlier (during May) if sites soon approaching their agreed number of modules, keep their production lines running. • VLC helps MPI with middles • NIKHEF helps Freiburg with Inners • Melbourne has to start very soon. • Already pre-qualified.

  6. Production Issues • Disk measurements showed redundancy link operation increases noise: • Trials have led to new (screened) links and requirement to change module 5.1kΩ resistor on redundancy line • All UK modules at Liverpool now have shorted out resistor with 0Ω resistor following procedure proposed by Freiburg • 20% sample test show identical normal electrical performance after change • All new hybrids have 0Ω resistor • Disk results with these changes greatly improved, disc9C mounting to begin • Repeat of contamination/erosion of tracks on fan-in after thermal cycling. • Seen in one early Liverpool Module • Now seen on two MPI modules in the same place as at Liverpool • Chemical analysis soon at CERN • Spine QA and delivery still critical • Prague CTU and Melbourne still to qualify • Most other sites producing at or above original envisaged rates and UK is nearing half-way

More Related