430 likes | 523 Views
Board of Trustees Workshop. Update to 2007 Facilities Assessment and Current Proposal. Photos of students and a lab/classroom setting. June 21, 2012. Background Process Findings Proposal. Agenda. Parsons Team. National experts + local knowledge Parsons Planning & Assessment
E N D
Board of Trustees Workshop Update to 2007 Facilities Assessment and Current Proposal Photos of students and a lab/classroom setting June 21, 2012
Background • Process • Findings • Proposal Agenda
Parsons Team National experts + local knowledge • ParsonsPlanning & Assessment • MGT of AmericaEducational Suitability • Natex Architects *One-line Drawings • Bovay Engineers * Assessment • CBIC *Assessment • Marshall Engineering *Assessment • PGALAssessment • One World Strategy Group *Communications * M/WBE Firm
Background: Scope of Work Phase 1 of HISD Facility Master Plan • Update 2007 Facility Database • Gather Community Input • Identify Schools to Assess • Propose Facility Improvements • Develop Budget Proposal
Background: Overview of Previous Facilities Programs 1998: Rebuild 2002Designed to relieve overcrowding and address fire and life-safety issues 2002: Rebuild HISDFocused on replacement of obsolete facilities and technology upgrades 2007: HISD Bond Proposal 2007Proposed to enhance security at all schools, improve science labs, replace obsolete facilities, and improve schools not covered in past programs
Background: HISD Schools Built by Decade and Level Baby Boomers Rebuild Houston Significant Focus on Primary Schools Growth of the Suburbs
Background: Current Situation • Earlier facility improvement efforts focused on the ELEMENTARY LEVEL • Commitment to maintain and improve neighborhood schools at the SECONDARY SCHOOL LEVEL • Need to match facilities to PORTFOLIO of PROGRAMS
Background • Process • Solicit Community Input • Review and Align Standards • Review Capacity Data • Conduct Assessments • Findings • Proposal Agenda
Putting the Pieces Together Review and Align Educational Suitability and Technology Standards Solicit School Community Input Conduct Facility Assessments Review Enrollment Projections, Capacity and Utilization
Solicit School Community Input Community • GOAL: Broad-based participation at each site • PROCESS: • ALL schools invited to provide input • Principals sent “Packet” to facilitate school community input • Tool available for more than 6 weeks • Sign-in sheets • Group information • Ensure that every voice is recorded
Solicit School Community Input Community • Data Gathering Tool - Example • Q2. What is your level of satisfaction with the overall physical condition of the buildings at your school? • Satisfied • Somewhat satisfied • Dissatisfied • Q3. Please explain why you aresatisfied or dissatisfied
Solicit School Community Input Community • RESULTS: • 95% response rate • 237 schools and 3,302 participants • Q2: What is your level of satisfaction with the overall physical condition of the buildings at your school? • Satisfied 19% • Somewhat satisfied 32% • Dissatisfied 48%
Solicit School Community Input Community • RESULTS: • Q3. Please explain why you are: • Satisfied: “We have a brand new school that is beautiful.” • Somewhat satisfied : “The new building looks nice, but the old building needs a lot of renovations.” • Dissatisfied : “There are water leaks and there is constant repair on the same issues.”
Solicit School Community Input Community • RESULTS WILL BE USED FOR: • Developing priorities and Proposal: • HISD Maintenance Department Planning • Capital Improvement Planning • Long-Range Facility Master Planning
Review and Align Educational Suitability and Technology Standards Standards • GOAL: Understand current and future district goals • PROCESS: • Conduct focus groups and interviews with HISD experts • Apply national experience/TEA Standards • Align Assessment Tool to existing HISD Educational Specifications • Create Educational Suitability and Technology Assessment Tools
Review and Align Educational Suitability and Technology Standards Standards • Assessment Tool • Learning Environment • Room Size • Location • Storage and Equipment • Technology
Review Enrollment Projections, Capacity and Utilization Utilization • Gather HISD demographics and enrollment data • Evaluate current utilization rates: permanent spaces • Examine future utilization scenarios • Effect of Improved Facilities • Program Offerings • Community Changes • Enrollment Growth / Decline
Conduct Facility Assessments Assessment • GOAL: Use existing information and gather new data to identify current facility needs • PROCESS: • Conduct Desktop Modeling Activity • Update scores based on changes since 2007 • Develop Composite Score for each school • Conduct Field Assessments • Validate current conditions • Update data and drawings
Conduct Facility Assessments. Assessment • Desktop Composite Score - Examples
Conduct Field Assessments Assessment 3 Areas of Review: • Condition • Educational Suitability • Technology Readiness Site Visit Process • Interview Principal and Plant Operators • Walk the buildings and site
Background • Process • Findings • School Community Findings • Educational Suitability and Technology Findings • Facility Themes • Proposal Agenda
FINDINGS: Educational Suitability Review • General classrooms, Tech labs, and special education rooms do not meet current standards • Traffic and parking are a problem • Schools are not designed for easy supervision and control of entrances • Lack of storage
FINDINGS: Technology Readiness Review • Electrical service is insufficient in older schools • Schools lack video distribution systems • Communications / IT equipment is housed inappropriately • Equipment is not up to date • HOWEVER, with recent work, network connectivity and performance are greatly improved
Themes • High schools are “due” • Reinvest in neighborhoods • Match facility to program • “Build it and they will come” • Finish last phase of earlier projects • Maintain our heritage into the future • Provide technology upgrades • Revitalize appearance and capabilities
Background • Process • Findings • Proposal Agenda
Proposal • High School Focus: • Replace existing schools • Replace Inadequate Facilities • Replace Inadequate Facilities and Renovate • Build New Schools • Renovate
Proposal K-8: Facilities Match Program Middle School Needs Elementary School Needs District-wide Needs
High School Focus: Replace Inadequate Facilities: $353,696,000
High School Focus: Replace Inadequate Facilities and Renovate:$258,953,000
K-8: Facilities Match Program: $120,732,000 K-8: Completion K-8: Replacement
Middle Schools: Meeting Needs: $73,950,000 Middle School: Replacement Middle School: Addition
Elementary Schools: Meeting Needs: $67,347,000 Elementary School: Renovation and Addition Elementary School: Replace Inadequate Facilities and Renovate Elementary School: New Location: TBD
Questions Thank you