An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UK Project Alan Grant, STFC

  2. Finance • How savings are made • Update on stepIV position • Milestones • Critical Path - stepIV • Concerns

  3. MICE Finances – August (submitted in report) Income:- Common Fund:- £84k + £63k STFC TIARA - £45k EUCard:- Assumed same as last yr £45k Bring forward:- £100k Negative Variance £366k • Encumbrance line added & being monitored to avoid unexpected late payments • Staff OTL bookings being monitored

  4. MICE-UK allocation revised downwards in August in excess of £300k • Combined effect of: • Cost of University Staff larger than original estimate • Revision to laboratory staff over-head charging; and • Close out of old encumbrances (going back as far as 2010) and revised FC stage-payment plan • MICE has been allowed an advance of £100k from 2013/14 allocation. • Overspend recovery must come from MICE project not University Staff. • Project team is working towards re-profiling work and staffing levels to recover overspend.

  5. MICE Finances - September Negative Variance now ~ £87 after re-profiling

  6. Predicted overspend reduced from:- • ~ £366k August to £87k September • Recovery achieved by:- • Late delivery of 2nd AFC will only make 1st stage payment this yr. ~£200k saving • Staff re-profiling Project Management Office. ~£91k saving • Other Recovery Lines:- • Transfer of questionable staff bookings to MICE. ~ £10k saving - TBA • Transfer of R9 facility upgrade costs to STFC. ~ £20k saving – TBA • Close out of AFC module 1 encumbrance. ~ £10k saving • Further overhead costs to be met by PPD, TD • Still more work to be done!

  7. Finances • Additional costs to deliver step IV but not in this FY budget • Vacuum system ~ £150k (common fund ???) • Additional shielding for mitigating stray magnetic field ~ £80k • AFC transfer line ~ £18k • Floor plates (parked position) ~ £12k • Upgrade requirements • Decay solenoid power supply ~ £70k to be ordered this FY for delivery next FY

  8. Staffing • STFC: • Mike Courthold now only contracted to work 3days each week. • Project Management Office : • A Grant UK Project Manager reduced to 50% • UK Project Management duties transferred to Roy Preece • Retain integration of full (international) MICE schedule • V Francis released • S Watson Hydrogen system wp manager reduced to 50% • S Greenhall MICE Hall manager released, duties transferred to another?? • Hall contractor effort reduced by 50% CONCERNS:- • Essential to maintain international planning and enhanced Project Office functions • Need to recruit Hydrogen System operator & provide safety training. - RF work beginning to ramp up, need full commitment of ASTEC & RF systems engineers. Plan is to recruit a graduate engineer who eventually will be based at MICE.

  9. STEP IV Step IV readyQ2, 2014, courtesy Andy Nichols

  10. Milestone – [1]

  11. Milestone – [2] Magnet Deliveries MICE Steps:- Installation Completion

  12. Step IV - Critical Path Critical path driven by delivery of Spectrometer Solenoids Solenoid installation in series, due to mapping requirements & resources

  13. Concerns • Mitigation of Stray Magnet Field • Further analysis shows that problem is more severe than first thought. • Need to find alternative position for sensitive electrical components, racks & compressors etc. • Options being considered • Temporary solution - move racks behind North Wall were RF amplifiers will be installed. • Distribute compressors around west wall. • Install equipment in ISIS plant room – could be final solution for step VI also. • Provide return yolks around magnets ~ 130T of steel, needs to be engineered properly, supports, access etc. Could delay step IV. Collaboration decision to be made in January. • Solution’s 1,2 & 4 will be most expensive • labour • shielding

  14. Questions