1 / 22

The MRP Heuristic

The MRP Heuristic. MRP stands for Materials Requirement Planning It is a widely used approach for production planning and scheduling in industry It is the approach embedded in many commercially available software applications. MRP Assumptions. No capacity constraints

lila-ford
Download Presentation

The MRP Heuristic

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The MRP Heuristic • MRP stands for Materials Requirement Planning • It is a widely used approach for production planning and scheduling in industry • It is the approach embedded in many commercially available software applications

  2. MRP Assumptions • No capacity constraints • A task initiated in period t completes in period t+ai • Product structure is typically assumed to be of the assembly type

  3. Formulation

  4. The MRP Solution Approach • Solve the lot sizing problem for each item independently starting with the end-items (finished products) and working your way down the bill-of-material (BOM) • The selected production quantities for an item, determine the demand for the items that are its immediate predecessors (its input items)

  5. Solving the Lot Sizing Problem • Solve the problem for each item optimally (e.g., using the Wagner-Whittin algorithm) • Solve the problem approximately using a heuristic (e.g., using a fixed order quantity, a fixed order period, or a lot for lot heuristic)

  6. Example

  7. Example (Continued…)

  8. MRP Terminology • Netting: determining net requirements against projected inventory for each period • Lot Sizing: determining order quantities • Time Phasing: determining when production orders should be initiated, given the production lead time • BOM Explosion: determining gross requirements for components

  9. MRP Terminology (Continued…) • Master Production Schedule (MPS): due dates and quantities for all top level items (finished products) • Bill of Material (BOM): the items that goes into each sub-assembly and into the finished product • Projected Inventory: (on hand plus scheduled receipts) for all items • Planned Lead times: production lead times • Level code: a number assigned to an item depending on the lowest position in the BOM where it can be found

  10. The Netting Procedure • Dt: Gross requirements in period t for some item • St: Quantity currently scheduled to complete in period t (i.e., a scheduled receipt) • It: projected on-hand inventory for the end of period t • Nt: Net requirement for period t • Qt: Planned orders in period t (production quantity initiated in period t)

  11. The Basic Steps • Step 1: Let t = 1 • Step 2:It = It-1 - Dt • Step 3: If It 0, then let t = t + 1 and go back to step 2, otherwise, let Nt = - It and set Nt’ = Dt’ for all t’ > t • Step 4: Use a lot sizing method to determine Qt for t=1,…, T, taking into account the production leadtime • Step 5:Use the production quantities Qtin determining the gross requirements for all items that are used by the item under current consideration

  12. Example - The Bill of Materials A B 100 (2) 200 500 300 300 400 100 600 300 400

  13. Example – The Input Data

  14. Example – Part A

  15. Example – Part B

  16. Example – Part B

  17. Example – Part 500

  18. Example – Part 500

  19. Example – Part 100

  20. Limitations of MRP • Capacity-insensitive • Assumes fixed lead times • Incentive to inflate lead times

  21. The MRP Planning Loop 1. Fixed lead times lead to poor due date performance 2. Management decides to increase lead time 3. Longer lead time requires longer forecasting horizon 4. Longer forecasting horizon creates errors in estimating demand 5. Errors in estimating demand lead to poor due date performance. 6. Management decides to increase lead time

  22. Enhancements to MRP • MRP II: The functionality of materials requirement planning (MRP) + capacity requirement planning (CRP) • APS: Advanced Planning Systems (software applications with the ability to solve the underlying optimization problem) • ERP: Enterprise Requirement Planning (MRP or APS capabilities integrated into an enterprise-wide information system)

More Related