DSWG Update to WMS 4/12/2013. Future Meetings. ALR Subgroup 4/15/13 9:30 a.m. to 3:30 p.m . ERCOT Taylor , Building TCCI Room252 Demand Side Working Group 4/26/13 9:30 a.m. to 3:30 p.m. ERCOT Met 206. Another adjustment to NPRR522:.
E N D
Future Meetings • ALR Subgroup • 4/15/13 9:30 a.m. to 3:30 p.m. ERCOT Taylor, Building TCCI Room252 • Demand Side Working Group • 4/26/13 9:30 a.m. to 3:30 p.m. ERCOT Met 206 Demand Side Working Group 03-08-13
Another adjustment to NPRR522: • DSWG finalized on static values for LR • Thought to be simpler and easier for compliance • Caused issues with impact analysis and loss of accuracy • Suggest use of Forecasted TLF/DLFs for LRs • Seek WMS approval to submit comments
NPRR to Limit ERS10 Deployment: • Current language has limit of 8 hours* • *unless emergency conditions persist • A number of changes since Feb. 2011 including automatic renewals • Open ended commitment is a challenge • Recommend limit of 8 hours but last deployment could last up to 4 hours regardless • Seeking WMS approval for DSWG to submit NPRR
NPRR to Move ERS10 to Clearing Market: • Currently pay-as-bid • Many market participants expressed concern for years • ERS30 and WSL have clearing mechanism • More efficient behavior with clearing market • Recommend converting ERS10 to clearing market • Seeking WMS approval for DSWG to submit NPRR