HV & LV status. DELIVERED AT BLG 904 40/60 67% of the A3009 ( LV ) 6/40 15% A3512N ( HV ) 10/10 100% A3018 ( T sens ) 30/34 88% EASY crates 5/7 71% branch controllers 6 boards land to ALICE + 2 to the DT group. BLG 904 test setup. Hardware and Software Test
E N D
HV & LV status DELIVERED AT BLG 904 • 40/60 67% of the A3009 (LV) • 6/40 15%A3512N (HV) • 10/10 100%A3018 (T sens) • 30/34 88%EASY crates • 5/7 71%branch controllers • 6 boards land to ALICE + 2 to the DT group P. Paolucci - I.N.F.N. di Napoli
BLG 904 test setup Hardware and Software Test • 3 LV EASY Crate running 15 boards 180 channels • 1 HV EASY Crate running 2 boards 12 channels • 20 LV boards tested = 240 channels 2 broken (< 1%) • 2 HV boards tested = 12 channels OK • Board Temperature went up to 60 °C due to a bad air circulation. Now fixed and temperature around 40 °C • DCS is always running (see Giovanni Talk) • LabVIEW (D. Lomidze) test program is under installation for more than 900 hours P. Paolucci - I.N.F.N. di Napoli
MAO Rpc-dt MAO rpc-dt LV LV trigger trigger PP PP 24 ch – HV - Barrel 24 ch – HV - Endcap HV HV HV HV HV HV HV HV HV-LV schema for MTCC W+1 LV RPC SY1527 Control cable BC LV BC HV BC LV BC LV HV multicond. 10 ch. service control 380 3-phase W+2 LV RPC LV MAJISTE HV service 48 V - service service 380 3-phase control Balcony Barack Detector
Rack LV 4 pairs LV distrib. board chip chip From LV power supply with floating output ALV1 AGND1 DLV1 ALV DGND1 shielded cable AGND ALV2 AGND2 DLV DLV2 DGND2 DGND shield IRON – MAGNET safety ground AGND FEB 1 chip chip AGND FEB strip copper chip kapton AGND Double Gap 2 Double Gap 1 DGND Chamber metallic structure AGND FEB 6 HVReturn Copper 2 Copper 1 chamber GND RPC ground schema
MAO Rpc-dt MAO rpc-dt trigger LV PP 24 ch – HV - Barrel 24 ch – HV - Endcap HV HV HV HV HV HV HV HV EARTH rack Ground schema for MTCC GND reference on the chamber W+1 LV EASY LV EARTH rack SY1527 GND Iron Control shielded cable BC LV BC HV BC LV BC LV Link Box HV multicond. shielded 10 ch. PP service control 380 3-phase W+2 LV RPC LV MAJISTE HV service 48 V - service service 380 3-phase control Balcony Barack Detector
MTCC status • LV hardware is ready for Barrel and Endcap • HV hardware ready for May the 22th • LV LB hardware now at blg 904 • LV EASY crates installation on the balconies started on May the 9th. • Crate insertion in the rack is difficult • No space around the racks • Balcony barrack 3-phase installation is underway P. Paolucci - I.N.F.N. di Napoli
MTCC status HV multicond. cables • 3 barrel cables are ready and have been tested by myself at CPE • 2 endcap cables are in construction at CPE • They will be sent at CERN on May 12th to be installed on May 22th • Local EASY cables will be ready for May 22th • Service and Control long cables ready on May 22th P. Paolucci - I.N.F.N. di Napoli
To be done • LV hardware is ready for Barrel and Endcap • HV hardware ready for May the 22th • LV EASY crates installation on the balconies started on May the 9th. • Crate insertion in the rack is difficult • No space around the racks • Balcony barrack 3-phase installation is underway We need 1 MAO channel per wheel (RPC-trigger). Ready ?? P. Paolucci - I.N.F.N. di Napoli
RPC DCS for MTCC P. Paolucci - I.N.F.N. di Napoli
To be done for MTCC • Move to RPC condition db on SX5 and test the performance. • Release the CMS_RPCfwHardware Component • Help our Warsaw friends, creating a control and monitoring system of the LB low voltage, and integrate it into the RPC DCS. • Do we want to integrate it in the FSM ?? It will be also discussed tomorrow in the DCS working group. • Test all the system when the hardware will be ready at SX5 (June 06). • Write documentation and organize training in order to have more people ready to take data. P. Paolucci - I.N.F.N. di Napoli