1 / 87

ELTON CREEK, DS OF FREEDOM 7 BRIDGE, FREEDOM, NY.

A project to protect a farm road from bank erosion along Elton Creek, a high-quality trout stream, using a self-adjusting and self-filtering stone toe protection method.

Download Presentation

ELTON CREEK, DS OF FREEDOM 7 BRIDGE, FREEDOM, NY.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ELTON CREEK, DS OF FREEDOM 7 BRIDGE, FREEDOM, NY. • Bank erosion is threatening a farm road • NRCS –Environmental Quality Incentives Program {EQIP} cost share with landowner • Rural (farmland) • Bed material: gravel-cobble-sand, incised • Pool-riffle-pool regime, slope around 1% • Average width 20-30 ft, 10-14 ft tall banks • Partially spring fed. • High-quality trout stream, not stocked, natural reproduction of Rainbow, Brown, & upstream, Brook Trout

  2. ENTITIES INVOLVED • NRCS – Area Office, Batavia, NY • Cattaraugus County Soil & Water Conservation District, Ellicottville, NY • U S Army Corps of Engineers, Engineering Research & Development Center, Vicksburg, MS. • NRCS Cattaraugus County Office, Ellicottville, NY

  3. THE FIRST SITE VISIT. JANUARY 10, 2007PANNING US TO DS

  4. Looking DS at right eroding bank & exit conditions. PRE-PROJECT-Elton Creek DS of Freedom 7 Bridge-derrick-Jan 10, 2007

  5. THE SECOND SITE VISIT. MAY 17, 2007PANNING US TO DS

  6. Looking US at attack angle into eroding bank. PRE-PROJECT-Elton Creek DS of Freedom 7 Bridge-derrick-May 17, 2007

  7. Looking US at eroded bank. Bob is 6 ft 4” (for scale). PRE-PROJECT-Elton Creek DS of Freedom 7 Bridge-derrick-May 17, 2007

  8. Looking US at eroding bank. Truck on road we are protecting. PRE-PROJECT-Elton Creek DS of Freedom 7 Bridge-derrick-May 17, 2007

  9. Looking US at eroding bank & large block failure. PRE-PROJECT-Elton Creek DS of Freedom 7 Bridge-derrick-May 17, 2007

  10. Bank is 14 ft tall-toe is clay, gravel-cobble-sand above PRE-PROJECT-Elton Creek DS of Freedom 7 Bridge-derrick-May 17, 2007

  11. THE PLAN

  12. Project Limits THE PLAN – ELTON CREEK DS OF FREEDOM 7 BRIDGE FLOW Project Limits THE FARM ROAD WE ARE PROTECTING Drawing by Robert Shenk, Catt County Soil & Water

  13. THE PLAN – ELTON CREEK DS OF FREEDOM 7 BRIDGE THE PLAN FLOW Drawing by Robert Shenk, Catt County Soil & Water

  14. CONSTRUCTION OCT. 9-12, 2007CONSTRUCTION CONTRACT & STONE COSTS - APPROX. $16,000. TOTAL

  15. Looking US at the constructed bypass channel. We plugged the channel, put all flow in the bypass channel, & worked in the dry during construction. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007

  16. METHODS EMPLOYED • 225 ft of self-adjusting & self-filtering Longitudinal Peaked Stone Toe Protection {LPSTP}. Mix of DOT heavy & medium graded stone. All protection is on right bank • Curved & vegetated keys on US & DS ends, 1 vegged tieback & key in middle of project • A stone check dam at DS end {not enuf stone for an Engineered Rocked Riffle} • Boil-Up Pool with curved kicker (Smile) • Five Single-Stone Bendway Weirs • Many transplanted Streamco Willow shrubs • Live Siltation,Pole Plantings, & Live Staking using Streamco & Black Willows, Red Osier & Silky Dogwoods • 6 rooted-stock Red Osier Dogwood

  17. WE WILL START DOWNSTREAM & WORK UPSTREAM, THEN DO THE GRADE CONTROL @ THE DS END LAST.

  18. LONGITUDINAL PEAKED STONE TOE PROTECTION {LPSTP}{Self-adjusting & self-filtering, Longitudinal Peaked Stone Toe Protection. Consists of a mix of DOT “heavy” & “medium” graded stone}

  19. THE PLAN – ELTON CREEK DS OF FREEDOM 7 BRIDGE THE LONGITUDINAL PEAKED STONE TOE PROTECTION {LPSTP} DS key FLOW Drawing by Robert Shenk, Catt County Soil & Water

  20. Elton Creek near Freedom 7 Bridge, Freedom, NY Farm road Typical bank cross-section Left bank Right bank

  21. Looking DS. Laying out the alignment for the LPSTP Construction-Elton Creek DS of Freedom 7-Steve Perschke-NRCS-Oct 07

  22. Elton Creek near Freedom 7 Bridge, Freedom, NY Then place clay dug from thalweg channel at toe of eroding bank First pre-dig a thalweg channel

  23. Looking DS. Laying out the DS key (red flags). Dug clay placed as substrate fill. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007

  24. Elton Creek near Freedom 7 Bridge, Freedom, NY Install one-half of the Longitudinal Peaked Stone Toe Protection (LPSTP).

  25. Elton Creek near Freedom 7 Bridge, Freedom, NY Install adventitious rooting Willow Poles

  26. Elton Creek near Freedom 7 Bridge, Freedom, NY Install remainder of LPSTP. Side slopes will be at the angle of repose

  27. Elton Creek near Freedom 7 Bridge, Freedom, NY The stream will adjust to the LPSTP, & the LPSTP will self-adjust to armor the resulting scour hole Toe scour

  28. Elton Creek near Freedom 7 Bridge, Freedom, NY The LPSTP has self-adjusted

  29. Elton Creek near Freedom 7 Bridge, Freedom, NY Install gravel-cobble from stream

  30. Looking DS. Vegetation integrated thru LPSTP. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007

  31. LIVE SILTATION{Willow branches about 1-2 inches in diameter, 6 to 8 ft long, 2/3 in ground, 1/3 out, intermixed with Silky & Red osier Dogwood that is 4 to 6 ft long}

  32. Looking US. Dug trench landward of LPSTP. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007

  33. Looking US at installed Live Siltation (willow & dogwood). Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007

  34. Looking US at Single Stone Bendway Weirs & veg 8 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-derrick-JUNE 13, 2008

  35. TRANSPLANTING A LARGE CLUMP OF WILLOW Multi-stem (20 to 40 stems) bushes approx. 14 to 24 ft tall, transplanted as a single clump, with roots in trench directly behind the LPSTP. Tops of branches were trimmed & used as Live Poles (6 to 10 ft long).

  36. Looking down bank at a dug trench in backfilled bank. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007

  37. Elton Creek near Freedom 7 Bridge, Freedom, NY Dig trenches to receive willow bushes

  38. Looking DS at LPSTP, backfilled bank, & dug trench. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007

  39. Elton Creek near Freedom 7 Bridge, Freedom, NY Transplant large multi-stem Willow Bushes

  40. Looking DS. Transplanting willow bush in trench Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007

  41. Elton Creek near Freedom 7 Bridge, Freedom, NY Then trim long branches from bush & plant as Willow Poles

  42. Looking DS. Trim willow & plant poles in trench. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007

  43. Elton Creek near Freedom 7 Bridge, Freedom, NY Water in & backfill

  44. Looking DS. Covering willow bush & poles with soil Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007

  45. Looking DS. Transplant complete. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007

  46. THE PLAN – ELTON CREEK DS OF FREEDOM 7 BRIDGE WILLOW BUSH TRANSPLANTATION FLOW Drawing by Robert Shenk, Catt County Soil & Water

  47. Veg planted on a grid, Live Siltation in front & transplants Willow shrub transplants & willow poles Live Siltation Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007

  48. 1 full growing season and 2 more growing months after completion. From point bar looking @ right bank. This is the 50 ft of Live Siltation & two large willow bush transplants that took 45 minutes to install. 19 MONTHS LATER-Elton Cr. DS of Freedom 7 Br.-Derrick-June. 9, 2009

  49. PLACING LPSTP IN THE US SECTION OF THE BEND{Self-adjusting & self-filtering, Longitudinal Peaked Stone Toe Protection {LPSTP}. Consists of a mix of DOT “heavy” & “medium” graded stone. }

  50. Looking US @ smooth curve in impact area. Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007

More Related