1 / 21

Generation Technology Options in a Carbon-Constrained World

Generation Technology Options in a Carbon-Constrained World. October 2007 Prepared by the Energy Technology Assessment Center. Objectives of the Levelized Cost of Electricity Analysis. Provide a useful generic basis for comparison of technologies for base load generation.

liz
Download Presentation

Generation Technology Options in a Carbon-Constrained World

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Generation Technology Options in a Carbon-Constrained World October 2007 Prepared by theEnergy Technology Assessment Center

  2. Objectives of the Levelized Cost of Electricity Analysis • Provide a useful generic basis for comparison of technologies for base load generation. • Provide strategic comparisons of technologies over plant lifetimes. • Evaluate sensitivities of levelized cost of electricity (LCOEs) to potential CO2 costs and other parameters

  3. Overall Analytical Approach for LCOE Studies • Utilize EPRI Technology Assessment Guide (TAG) capital cost data and methodologies to calculate levelized costs of electricity (LCOEs) in constant 2006 $. • Survey available plant performance and cost estimates based on most recent data. • Choose representative values for each technology. • Incorporate key assumptions needed for calculations – capital cost, fuel cost, annual and fixed O&M, plant life, fuel type and energy content, cost of money. • No production or investment tax credits assumed for any technologies. • Assume that current technology parameters and costs are representative of 2010–2015. • Estimate LCOEs for 2020–2025 based on expected technology-driven improvements in performance and reductions in capital cost.

  4. Capital Cost Estimating Approach • Costs are to be reported in reference year dollars: • No cost escalation to startup date included. • Plant site is assumed to be clear and level. • Cost estimate assumes mature technology: • Plant is assumed to operate as designed (no allowance for field modifications) • Extra costs for 1st-of-a-kind demonstration not included

  5. Cost Basis for LCOE Estimates • Total Plant Cost (TPC): • All process and support facilities; fuel handling and storage; water intake structure and wastewater treatment; offices, maintenance shops, and warehouses; step-up transformer • Sometimes referred to as Engineering, Procurement, and Construction Cost (EPC), or Overnight Capital Cost • Owners Costs: • Pre-production costs, working capital, land, license fees, interest during construction • Project-specific Costs: • Project development, utility interconnections, legal/financial consulting, owner’s project management

  6. Capital Cost Estimate Summary • Total Capital Requirement (TCR) = TPC + Owner’s Costs • Total Capital Requirement (TCR) is typically 16–19% higher than Total Plant Cost (TPC): • Typical EPRI Owner’s Costs add about 5–7% to TPC • Interest during construction adds another 11–12% to TPC • The adder for project-specific costs varies widely: • Depends on project and site-specific requirements • Equivalent to 10–15% of TPC • “All-in” capital cost = TCR + estimated project specific costs When comparing capital cost estimates: • It is important to know if values are in constant year dollars vs. future year dollars • It is important to know which components of cost are included/excluded.

  7. Technology Assumptions for this Analysis • Near Term – 2010 to 2015 • Modest extrapolation of today’s technology. • Based on foreseeable technology development. • Longer term – 2020 to 2025 • Assume that established R&D objectives are achieved, and technology development is successful. • Estimated reductions in costs are based on assessment of potential technology improvements. Examples: new materials and designs, new gas turbines, chemical processes, and membrane contactors, and a wide range of other technologies.

  8. Near-Term: 2010–2015

  9. 0.86 Metric Tons CO2/MWh X $50/Ton = +$43/MWh Pulverized Coal Combustion2010–2015 Levelized Cost of Electricity, $/MWh All figures in 2006 $ PC ($2290/kW) Rev. Oct 2007 Cost of CO2, $/Metric Ton

  10. Comparison of PC and IGCC2010–2015 Levelized Cost of Electricity, $/MWh All figures in 2006 $ IGCC ($2730/kW) PC ($2290/kW) Rev. Oct 2007 Cost of CO2, $/Metric Ton

  11. 0.38 Metric Tons CO2/MWh X $50/Ton = +$19/MWh Natural Gas Combined Cycle Costs2010–2015 Levelized Cost of Electricity, $/MWh All figures in 2006 $ NGCC ($8/MMBtu, $730/kW) NGCC ($6/MMBtu, $730/kW) Rev. Oct 2007 Cost of CO2, $/Metric Ton

  12. Comparison of PC, IGCC, NGCC2010–2015 Levelized Cost of Electricity, $/MWh All figures in 2006 $ IGCC NGCC ($8/MMBtu) PC NGCC ($6/MMBtu) Rev. Oct 2007 Cost of CO2, $/Metric Ton

  13. Nuclear Data Range Levelized Cost of Electricity, $/MWh All figures in 2006 $ $3720/kW(Upper end – EPRI TAG data) $3500/kW(Average – EPRI TAG data) $3260/kW(Lower end – EPRI TAG data) All calculations for 1400 MW, 90% CF Rev. Oct 2007 Cost of CO2, $/Metric Ton

  14. Non-Emitting Generation Technologies Levelized Cost of Electricity, $/MWh All figures in 2006 $ Solar thermal power has LCOEs ranging between $120MW/h and $260/MWh. Biomass Wind (32.5% Capacity Factor) Nuclear Rev. Oct 2007 Cost of CO2, $/Metric Ton

  15. Solar Thermal Trough Design2010–2015 Levelized Cost of Electricity, $/MWh All figures in 2006 $ 280 260 240 TAG -- estimated LCOE range is $120/MWh to $260/MWh 220 200 Average LCOE ~ $190/kWh, Average All-in Capital Cost ~ $3150/kW 180 160 140 120 Rev. Oct 2007 100 0 10 20 30 40 50 Cost of CO2, $/Metric Ton

  16. Comparative Levelized Costs of Electricity 2010–2015 Levelized Cost of Electricity, $/MWh All figures in 2006 $ Biomass IGCC Wind (32.5% Capacity Factor) NGCC ($8/MMBtu) NGCC ($6/MMBtu) PC Nuclear Rev. Oct 2007 Cost of CO2, $/Metric Ton

  17. Longer-Term: 2020–2025

  18. Integrated Gasification Combined Cycle, Pulverized Coal with CO2 Capture Levelized Cost of Electricity, $/MWh All figures in 2006 $ IGCC ($2730/kW, no CO2 capture, 2010–2015) IGCC ($3100/kW, + CO2 capture, 2020–2025) PC ($3060/kW, + CO2 capture, 2020–2025) PC ($2290/kW, no CO2 capture, 2010–2015) Rev. Oct 2007 Cost of CO2, $/Metric Ton

  19. Impact of Anticipated Cost, Performance Improvements on PC, IGCC with CO2 Capture Levelized Cost of Electricity, $/MWh All figures in 2006 $ PC + CO2 Capture ($3820/kW); IGCC + CO2 capture ($3780/kW)(near term) PC + CO2 Capture ($3060/kW); IGCC + CO2 capture ($3100/kW) (with cost, performance improvements) Rev. Oct 2007 Cost of CO2, $/Metric Ton

  20. Comparative Levelized Costs of Electricity 2020–2025 Levelized Cost of Electricity, $/MWh All figures in 2006 $ Biomass IGCC PC Wind (42% Capacity Factor) Nuclear NGCC ($6/MMBtu) NGCC ($8/MMBtu) Rev. Oct 2007 Cost of CO2, $/Metric Ton

  21. Closing Thoughts • Several key uncertainties impact near-term and long-term project decisions and research priorities: • Stringency of future CO2 emissions reduction goals • Future cost of CO2 • Future price of natural gas (high sensitivity) • Financing costs and challenges • CO2 capture and storage technology development and costs • Impact of using lower rank coals • Siting requirements • Water availability • Renewable energy technology development • Technology-driven reductions in nuclear costs • Extraordinary opportunity to develop and demonstrate a very low emissions portfolio of generation technologies. Together…Shaping the Future of Electricity

More Related