CONVENTIONAL FACILITIESLCLS Office Space Jess Albino – Associate Project Director for Civil Construction May 14, 2009
Agenda • Overview • Status • Turner Contract • SLAC Managed Contracts • CF Remaining Work • Turner Contract Closeout • Office Space Procurement
LCLS Office Space Building 028 Conversion to Office Space Baseline13,250 SF Optional6750 SF
LCLS Office Space Building 751 Conversion to Office Space (1st Floor)4,800 SF Cubicles Hard-wall Offices
Office Space Schedule Construction CompleteMarch 26, 2010 A/E Design CompleteJune 1, 2009 Award/NTP ConstructionJuly 29, 2009
Office Space Procurement • Baseline Office Space Plan • Title II design for B028 and B751 underway. • RFP in June and Notice to Proceed in July. • Construction complete March, 2010 • Preliminary Estimate: $6.4M • Construction Contract • B028: $3.8M Duration: 170 wd • B071: $1.4M Duration: 120 wd • Engineering Design & Indirects: $1.2M • Alternative (not in baseline) • New building at Near Experimental Hall • Guaranteed Maximum Price Contract • Construction to complete end of April, 2010 • Contract completion 1 Quarter prior to CD-4
Experience at LLNL • “$5M buildings” at LLNL • Similarly Spartan office buildings for project teams • Minimum risk to bidders • Price is fixed, bidders propose square footage
Alternate building site (near CEH) Near Experimental Hall Loop Road Potential Building Site Central Laboratory Office Complex