An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Conventional Facilities Status Martin Fallier, Facilities Division Director NSLS-II Project Advisory Committee Meeting February 8-9, 2011

  2. Outline Baseline Scope, Cost, Schedule & Staffing Progress since last review Technical Progress Cost & Schedule Performance Risks & Lessons Learned Look Ahead FY11 Goals Issues Conclusions

  3. Baseline Scope

  4. NSLS-II Site Plan N NSLS-II With Full LOB Build-Out 100 0 200

  5. Ring Bldg Overall Floor Plan LOB 1 Storage Ring & Booster Tunnel Experimental Floor Access Corridor Service Buildings LOB’s 1, 2, & 3 Base Scope Future LOB’s Earth Berm Lobby RF Injection LOB 2 LOB 5 Process Cooling Water Bldg Vehicle Tunnel LOB 4 LOB 3

  6. LOB Exterior Perspectives LOB Roofline LOB Entry

  7. WBS 1.5 Cost Baseline ($K) • Major Increases or changes: • Revised CM staffing to address earlier LOB construction [$0.9M)]& safety incentive [$1.0M] • Redesigned & awarded larger LOBs [$10.9M] & added HXN Endstation Addition [$2.7M] • Ring Building changes due to ASD & XFD design maturity - $1.2M • Various field changes to Ring Building contractor – $2.1M • More robust data & communication infrastructure – $0.7M

  8. CF Schedule

  9. CF Organization

  10. Conventional Facilities Staffing

  11. Progress • Ring Bldg Construction • Excellent progress since Dec 09 – on/ahead of schedule • Concrete nearly complete @ 97% of 40,000 cy • Structural steel complete - 3,000 tons • Underground utilities – nearly complete, being commissioned • Building enclosure 45% complete and advancing • HVAC & electrical installation in progress throughout building • Sitework- restoration and landscaping remain for 2011 & 12 • Pentant 1 nearly ready for beneficial occupancy • Field changes running ~2% (not including requested scope additions) • Heavy snow and extended cold have slowed recent progress

  12. Technical Progress • Chilled Water Plant Expansion Contract Running on schedule • CCWF, Cooling Tower and Pump-house Buildings complete • Equipment & controls installation complete • Equipment start-up and commissioning in progress • Problem with Chiller motor starter to be resolved in Feb • Complete CCWF expansion several months earlier than needed • Electrical Substation Expansion Contract Running on/ahead of schedule • All ductbank, cable & switchgear installed and permanent power is available to the NSLS-II site • 20 MVA transformer installed and ready for start-up early Feb. • Contract close-out in February

  13. Technical Progress cont’d • Chilled Water Piping Tie-in at central main and NSLS-II site complete - CHW available • All work completed, contract close-out in progress • LOB Construction – ahead of original baseline by 1 year Contract awarded, contractor mobilized, construction underway • Construction of foundations in progress • Structural steel shop drawings in preparation • Detailed schedule nearly ready for approval • Other submittals in progress • Resolved work coordination and access needs of Ring and LOB contractors – now working well together on same site

  14. Progress Dec 2009 Photo From BGRR Stack 12-4-09 Column Footings SR Tunnel Slab SR Tunnel Wall Forms SR Tunnel Walls Vehicle Tunnel • Extensive earthwork nearing completion • Vehicle & Utility tunnels nearly complete • SR tunnel and “A” line foundation into P-2 & 3

  15. Current Progress Photo From BGRR Stack 01-03-11 Injection Bldg Steel Roof Insulation Clg Twr Bldg Roof Deck Finished SSM Roof Opening @ P5 Exterior Siding Lobby Curtain-wall LOB 1 Foundations • Pentant 1 nearly complete, being readied for February Beneficial Occupancy • Concrete complete except P5 opening & Injection Bldg 1st floor slab • Roof deck complete, Insulation to P5, Finished SSM Roof into P2 • P1, & 2, 3, 4, Cooling Twr, RF & Compressor Bldg Enclosure all underway • Utility installation complete in inner courtyard (some DI pipe backfill remains) • All major electrical gear in place and ready for power

  16. Technical Progress cont’d • Lobby Curtain Wall In Place Temporary Heating & Closure Wall • Pentant -1 – Interior Finish In Progress

  17. Technical Progress cont’d • Injection Bldg Equipment Area 2nd Floor RF Bldg HVAC In Progress • LOB 1 Foundation Wall

  18. Overall Cost and Schedule Assessment • Progress consistently ahead of schedule and below budget for CY 2010 • Stayed ahead of plan despite monthly BCWS going from ~$5M/mo to ~$10M/mo – significant ramp-up in activity Chart covers period 1/1/10 to 12/31/10

  19. Overall Cost and Schedule Assessment • CPI and SPI > 1 each month for 2010 • Recent dip in SPI due to December 2010 weather & holiday impacts combined with abnormally large BCWS ($15M vs typical $10-12M) Chart covers period 1/1/10 to 12/31/10

  20. Performance Outlook • Cost Variance - currently +$3.4M • Temporary positive cost variance due to differences in accrued vs monthly invoiced values – will go to ~$0 as contracts are completed • Schedule Variance - currently +$6.7 M • Work in P2 – P5 ahead of plan for concrete, steel, and mechanical, electrical & plumbing • May see temporary schedule (Jan – March 2011) drop due to abnormally cold/snowy winter weather • Remaining contracts on or close to plan • Ring Bldg contractor expects early completion of later sections of building

  21. Risks • Construction Safety - program must continue to be effective • Substantial performance improvement since 9/30/09 accident • Applying lessons learned to LOB contractor • Continually working with GC’s to improve program • Requires constant oversight, planning and encouragement • Potential for field changes, errors/omissions thru construction • Running @<2% of work complete and overall construction is 62%complete • Potential for design changes from ASD & XFD • Running @ <1.5% of work complete – mainly minor design maturity items • Risks of Ring Bldg GC and LOB GC conflicts • Overcame initial issues and now working well together

  22. Lessons Learned • Bid & award process for Ring Bldg was very successful & proved equally successful for LOB procurement • Well qualified contractors at competitive price • Contractor safety performance requires constant vigilance and intervention • Reworked safety incentive seems to have had positive impact • Initial experience in managing Ring Bldg contract made it clear that added CM staff were needed to manage accelerated LOB contract • Revised staffing plan for CF CM team • Role of interface managers for CFD, ASD and XFD has been key in minimizing costly changes to date

  23. NSLS-II Facilities FY11 Goals • Maintain effective safety culture at all construction sites • Ring Building • Maintain effective working relationship with GC • Maintain construction on schedule and budget – achieve BO dates • LOB Construction • Maintain construction on schedule and budget • Foster cooperative coexistence between Ring & LOB contractors • Successful commissioning & transition to operations • Integrate O&M in start-up & commissioning process • Verify technical performance goals are achieved (particularly vibration & temp ctrl.) • Oversee occupancy/ASD installation phase operational requirements • Support strategic planning for PSD goals • Complete B725 study and initiate facilities project planning

  24. Issues • Continued focus on contractor safety performance is necessary to prevent significant injury or incident • Need to maintain close oversight of contractor schedule and maintain constructive relationship with Ring & LOB contractors • Completed partnering session with Ring Bldg Contractor • Contractors working well together at this time • Process of resolving and implementing contract changes has been labor intensive • Recent PCR issued to address this helping significantly • Process of transitioning to operation of buildings as they are turned over to ASD/XFD underway

  25. Conclusion • All goals for CY 10 have been met, there has been substantial progress and LOBs are now accelerated 1year • CF is on schedule and on budget and CF Team is in place • CF risks are well understood and mitigation plan in place • 98% of CF construction costs are under fixed price contract • Plans for FY11 and beyond are well understood • CF well on track for early completion