CONVENTIONAL FACILITIESSTATUS Jess Albino – Associate Project Director for Civil Construction June 9, 2009
Agenda • Status of Conventional Construction • Turner Contract • CF Remaining Work • Turner Contract Closeout • Office Space Procurement
LCLS CF Work Remaining • Construct Experimental Hutches in Far Experimental Hall • Structural Steel in fabrication – installation begins in June. • Build-out contract in award stage – NTP in July. • Office Space Alternatives Project • Baseline Change approved – construct new building • Design/Build, Guaranteed Maximum Price contract • Contractor selected – NTP in June
WBS 1.9 Completed and Remaining Proc/Fab/Assy 11,285,208 Dsn/Engr 909,466 Admin/Mgmt 1,302,273
Turner Contract Closeout • Notice of Substantial Completion 11/17/2008 • Notice of Completion ~4/24/2009 • Remaining Activities • Redline mark-ups sent to Jacobs for Record Drawings • 23 of 26 trade subcontracts require closeout binders • Retention amounts to be released upon closeout • Complete Lessons Learned
CF CMGC Stewardship – Lessons Learned • October ’06 thru April ’07 Ramp Up to Full Production : Procedural Violations • Stand Down of Construction Activities : All Hands Meeting • Review of Work Planning Process for field work – JSA process inadequate • PMT changes • Deficiency Notices • May ’07 thru November ’07 Full Production : DARTs • Multi-day Stand Down of Construction Activities : Corrective Action Plan • Paperwork ineffectively utilized by CM/GC and trade contractors • PMT changes • Deficiency Notices & Fines • Communication with Corporate TCCo • Safety Stewardship Committee Established • Full time on-site medic (+30hr OSHA) • UTRs added • December ’07 thru April ’08 : Some progress, then… • Two DARTs associated with one sub • PM removed • Work stopped • May ’08 thru December ’08 : No DARTs • Effective work planning & execution sought • Plan for joint observation developed • Attendance at daily morning work planning meetings • JSA review with workers throughout the day • Identification / monitoring of specific trades or tasks for safe work practices