170 likes | 304 Views
CLIC RF structure development meeting Structure cost study (introduction). G. Riddone, 18.08.2010 . Content. Introduction and method Learning curves Manufacturing flow Parameters affecting the cost Some comparative numbers Cost study in industries. Introduction. Accelerating structures
E N D
CLIC RF structure development meetingStructure cost study (introduction) G. Riddone, 18.08.2010
Content Introduction and method Learning curves Manufacturing flow Parameters affecting the cost Some comparative numbers Cost study in industries
Introduction Accelerating structures • Two cases are considered: • Accelerating superstructures in quadrants • Accelerating superstructures in disks • For both cases: • Sealed structures • Diffusion bonding at ~1000 ˚C under hydrogen • 3 production lines PETS • Octants and mini tank concept • 3 production lines
Method Definition of the manufacturing flow Identification of the main steps Prototype cost based on current design Usually cost of the first third/fourfh unit Calculation of cumulative cost Application of learning curves Calculation of average unit cost
Learning curve - Theory • T.P. Wright, Factors affecting the cost of airplanes, Journ. Aero. Sci. (1936) • Unit cost c(n) of nth unit produced with a = « learning percentage », i.e. remaining cost fraction when production isdoubled • Cumulative cost of first nth units with C(n)/n = average unit cost of first nth units produced • n = number per production line ≠ total number in project We have to define c(1) and a
Learning percentage Typical learning percentage values (NASA Learning Curve Calculator)
Assumptions: 1 as = 30 disks Bonding of superstructures (2 as) Accelerating structures DISKS (142812) 1. Raw material a:1 2. Machining 4284360 disks (including HOM, manifolds), QC and cleaning Sequence a: 0.93 3. Assembly and brazing 285624 couplers 8 couplers /cycle [35703 cycles] a: 0.85 Alignment and bonding 71406 disk stacks 4 ss/cycle [17852 cycles] a: 0.85 5. Final bonding and assembly (HOM, manifolds), incl. RF check - 71406ss a: 0.85 4 ss/cycle [17852 cycles] a: 0.9 6. Baking 71406ss 4 ss/cycle [17852 cycles]
Assumptions: 1 as = 4 quadrants Bonding of superstructures (2 as) Accelerating structures QUADRANTS (142812) 1. Raw material a:1 Sequence 2. Machining 285624 quadrants (including HOM, manifolds), QC and cleaning a: 0.93 4. Alignment and bonding 71406 structures 4 ss/cycle [17852 cycles] a: 0.85 5. Final bonding and assembly (HOM, manifolds), incl. RF check - 71406ss a: 0.85 4 ss/cycle [17852 cycles] a: 0.9 6. Baking 71406ss 4 ss/cycle [17852 cycles]
Assumptions: 1 PETS: 8 bars, 1 coupler Mini-tank concept PETS (71406) 1. Raw material a:1 2. Machining 571248 bars (including HOM), QC and cleaning Sequence a: 0.92 3. Machining 71406minitanks, QC and cleaning a: 0.92 4. Machining 71406 couplers, QC and cleaning a: 0.92 5. Brazing 71406 couplers a: 0.85 8 couplers/cycle [8926 cycles] 6. Final bonding and assembly (HOM, minitanks), incl. RF check - 71406 a: 0.85 a: 0.9 7. Baking 71406 8 ss/cycle [8926 cycles]
Some parameters affecting the total cost Choice of learning factor (+++) Saturation value: value above which learning stops, no average cost reduction (negligible) Number of production lines (+)
Learning factor CLIC
Saturation Examples [a= 0.9]: Sat 0.8 learning process stops after 80 % of the production Cumulative cost increase 0.31 % Sat 0.5 learning process stops after 50 % of the production Cumulative cost increase 2.7 % For CLIC RF structure quantities
Influence of production lines Examples [a = 0.9]: Cost increase of 18% from 1to 3 production lines (no saturation)
Two beam module cost The highest contribution! BREAKDOWN RF system: 65 % Alignment system: 10 % Supporting system: 6 % Magnet system: 5 % Beam instrumentation: 5% Magnet powering system: 3% Vacuum system: 2.5 % Other systems: 3.5 %
Industrialization and mass production study • Launched industrialization and mass production studies in 3 industries/institutes: • VDL • KERN • VTT/HIP • CLIC structures, with HOM damping material, vacuum material,…. • Cost study will include both capital and running cost (CERN cost study only running cost) • Study currently under way. • Analysis of the preliminary results confirm tendency of CERN cost study