1 / 18

Booster L12/Noker-L13/Absorber Update

Booster L12/Noker-L13/Absorber Update. PIP Update Talk August 15, 2012 Salah Chaurize. Current Status L12 Noker Systems. Tunnel Prep work 85% Complete

marcy
Download Presentation

Booster L12/Noker-L13/Absorber Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BoosterL12/Noker-L13/Absorber Update PIP Update Talk August 15, 2012 Salah Chaurize

  2. Current StatusL12 Noker Systems • Tunnel Prep work 85% Complete • Two of three Noker kicker magnets have been rotated using new magnet angle brackets and end plates. Third magnet will be rotated this week. • Maintenance work in progress on kicker load resistors. • Charging resistor module need component fabrication. • L12 Noker power supply systems controls migration completed and tested. • Working on timing/trigger module installation for NokerThyratron firing. • New Thyratron cabinet construction in progress.

  3. Noker and MKS04 Racks Before After

  4. East Gallery Thyratron Cabinets

  5. Load Resistors And Charging Resistor Box

  6. Rotated Magnet support plates.

  7. Current StatusL13 Absorber Systems • Tunnel prep work 90% Complete • Floor and wall marking to be laid out to show foot print of K and L Blocks and wall shielding support section locations. • Small concrete blocks have been painted by AD Techs. • Machined Beam tube and liner components in hand at Meson Assembly Building. Preassemble of components in progress. • V. Sidorov is refining design details for aisle side beam kick configuration. • V. Sidorov is overseeing preassembly efforts by PPD Techs. So far parts are going together as planned. Liner parts are heavy precision milled components.

  8. Vacuum Liner

  9. Vacuum Liner

  10. Moving block support plates.

  11. Moving block assembly parts

  12. Preassembly process at MAB

  13. Preassembly process at MAB

  14. Preassembly process at MAB

  15. Preassembly process at MAB

  16. Booster Long 13

  17. Illustration of Wall shielding and blocks in tunnel

More Related