QIP status 1. 07-04-11: Decision taken together with NB (Göran Tegbrant) to postpone migration of production sites (Yorba Linda and Karlskoga) till after Las Vegas sales event, i.e, completion date will be mid of June.
E N D
QIP status 1 • 07-04-11: Decision taken together with NB (Göran Tegbrant) to postpone migration of production sites (Yorba Linda and Karlskoga) till after Las Vegas sales event, i.e, completion date will be mid of June. • Specific meeting will be held to perform detailed planning of Karlskoga and YL, April 20th and 25th. • Following time plan, except for small rescheduling due to printer password issues, printers out-of-order, LITC need to prioritize other tasks etc etc …