QIP status 1 • 07-04-26: Major incident in Barcelona. Rollback needed. Reason was wrong IP range configuration in a server table. Test showed ok but was performed on cashed information. Users didn’t have a usable network for 3-4 office hours. New date planned: May 9th, additional follow up will be performed. • Detailed plan for Karlskoga created. Work started. • Detailed planning meeting for YL postponed due to Ellis Moore’s absense. Göran Tegbrant will come back with new date proposal. • Following time plan, except for small rescheduling due to printer password issues, printers out-of-order, LITC need to prioritize other tasks etc etc … • No migrations during w18 due to financial report tasks at NB sites