Short Term and Mid Term Load Forecast

Short Term and Mid Term Load Forecast. John Dumas Supervisor, Operations Planning ERCOT January 24, 2007. ERCOT Load Forecasts. ERCOT uses three primary types of load forecast. Long Term Mid Term Short Term This presentation will cover only short term and mid term load forecast.

Download Presentation

Short Term and Mid Term Load Forecast

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Short Term and Mid Term Load Forecast John Dumas Supervisor, Operations Planning ERCOT January 24, 2007

  2. ERCOT Load Forecasts • ERCOT uses three primary types of load forecast. • Long Term • Mid Term • Short Term • This presentation will cover only short term and mid term load forecast.

  3. Short Term Load Forecast • Period covered: • Every 5 minute period for the next hour. • The STLF program runs every 5 minutes. • Used for: • Determining Balancing Energy deployments 25 minutes prior to the start of the interval. • Developed by AREVA

  4. STLF Error

  5. Mid Term Load Forecast • Period covered: • Each hour period for the next 7 days. • The MTLF program runs every hour. • Used for: • Day Ahead reliability studies. • Decisions on Unit Commitment • OOMC • Replacement Reserve • Developed by: • AREVA • PRT

  6. MTLF Error

  7. Causes of MTLF Error • Error in Weather Forecast • Temperature • Humidity • Wind Chill • No good way to account for probability of rain • Load Response • May be based on energy cost (MCP) or 4CP anticipation • ERCOT has limited knowledge of this behavior

  8. January 15, 2007 MTLF Day Ahead 16:00 MAPE: 5.84

  9. January 15, 2007

  10. January 15, 2007

  11. January 15, 2007

  12. January 16, 2007 MTLF Day Ahead 16:00 MAPE: 6.0

  13. January 16, 2007

  14. January 16, 2007

  15. January 16, 2007

  16. January 17, 2007 MTLF Day Ahead 16:00 MAPE: 2.63

  17. January 17, 2007

  18. January 17, 2007

  19. January 17, 2007