Role . Yongzhi , Z huang Key coder Jianlei , Zhang Documentation work Keeping meeting notes Testing Wei, Zeng Project manager assign work to each member, keep project processing in time Seconder coder. Time Plan. Background Research – 2 week Initial Design - 1 week
E N D
Role • Yongzhi, Zhuang • Key coder • Jianlei, Zhang • Documentation work Keeping meeting notes • Testing • Wei, Zeng • Project manager assign work to each member, keep project processing in time • Seconder coder
Time Plan • Background Research – 2 week • Initial Design - 1 week • Implementation – 5 weeks • Minimum requirements • Packets handle • Connection setup • Data uplink forwarding • Data downlink forwarding • Optional Functions • Congestion Control • Checksum • Testing and Evaluation – 2 weeks • Dissertation Writing – 2 weeks
Resource Manage • Version Control System Google Code + SVN http://code.google.com/p/mptcp-proxy/ • Documentation Evernote: using a shared account to manage meeting notes, design drafts, relative materials.
Risk Management • Schedule flaws Lack of through understanding the work involved, under estimate the time need to complete certain function. Group members may have some unexpected issues in this summer. • Technical Issues Because of the current internet structure and protocol, we may meet some unsolvable problem. • Design mistake and Bug We may spend a a lot time in going wrong direction, and solving bug. • Control Risk Define minimum requirements, keep the whole processing as fast as the plan.