I-35E/Maryland Ave. Bridge Replacement Design-Build Project S.P. 6280-353 Industry Kickoff Meeting September 27, 2011. Curt Kallio, Design-Build Program Manager David Herzog, Project Manager. Roles and Responsibilities. Disclaimer.
E N D
I-35E/Maryland Ave.Bridge ReplacementDesign-Build ProjectS.P. 6280-353Industry Kickoff MeetingSeptember 27, 2011
Curt Kallio, Design-Build Program Manager David Herzog, Project Manager Roles and Responsibilities
Disclaimer What is discussed today is informational only, meant to assist interested teams in the pursuit of this project. The ultimate contract requirements will be included in the Request for Proposals (RFP). There may be changes between now and the time the RFP is issued and proposal due date.
Design-Build Best Value • Two-Step Procurement Process • RFQ (Request for Qualifications) • RFP (Request for Proposals) • RFQ • Draft posted on September 19, 2011 • Short-List Up to 5 Teams • Addendums and clarifications posted to ftp site • Email notification to those who responded to LOI
Design-Build Best Value • RFP • Issued only to the short-listed teams • Technical Proposal • Alternative Technical Concepts • One-on-One Meetings • Stipends • Price/DBE Proposal • Best-Value = Proposal Price/Technical Score
RFQ Update – Prequalification Changes • The Design Engineer – Roadways shall be employed by a firm on MnDOT’s pre-qualified list to perform Work Type 2.12, Highway Design Level 2 • The Design Engineer – Structures shall be employed by a firm on MnDOT’s pre-qualified list to perform Work Type 3.12, Bridge Design - Level 2 • Removed Bridge Design SPMT Engineer from pre-quals. (Remains a Level - A Personnel in 3.3.1)
Procurement Timeline(Subject to Change) ACTIVITY DATE Issue RFQ September 28, 2011 Short List of Submitters November 4, 2011 Issue RFP November 18, 2011 Technical Proposals due January 18, 2012 Price Proposals due February 1, 2012 Anticipated Contract March 2012
General Project Information • No Co-Housing Requirement • Key Participants to be on project or available as described in RFP • DBE - Goal to be determined • Oversight Contract
Why Design-Build? • Project acceleration • Industry Innovation • Speciality skills required (SPMT’s)
What are SPMT’s?(Self-Propelled Modular Transporters) • Combination of multi-axle platforms • Computer-operated • Pivots 360 degrees • Lifts, carries, sets large/heavy loads • Moves at walking speed
Why SPMT? • Reduce Traffic Disruption • Improve Work Zone Safety • Improve Quality and Constructability • Increase Contractor and Owner Options • Federally funds on the project stipulate that Accelerated Bridge Construction (ABC) used, specifically SPMT’s
Design-Build Webpage http://www.dot.state.mn.us/designbuild
Project InformationI-35E/Maryland Ave.David HerzogMnDOT Metro DistrictProject Manager
Roadway • Bridge • Drainage • MOT • Geotechnical • Permits • Utilities • Deep storm sewer • Relocate watermain Project Details
Project Partners • MnDOT • City of St. Paul • Ramsey County • Federal Highway Administration • Design-Build Proposers • HNTB – RFP Development • DNR – Pedestrian underpass
Project Goals • Quality • Encourage innovative design & construction practices • Design and construct a quality project with quality personnel • Schedule and Budget • Project completion by December 2012 • Stakeholder Satisfaction • Implement effective use of SMPT during construction • Minimize traffic disruptions • Minimize impacts to residents and businesses • Safety • Employment Opportunities
Questions ? • Curt Kallio • Design-Build Program Manager • David Herzog • Project Manager