1 / 5

EMMA DELIVERY UPDATE Neil Bliss

EMMA DELIVERY UPDATE Neil Bliss. Production Quadrupoles. 2 nd rotating coil bench alignment scheduled for July 22 – 24 Some issues to be resolved in the design of the bench to ensure we have the best accuracy from the magnet centre to the fiducials

mili
Download Presentation

EMMA DELIVERY UPDATE Neil Bliss

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EMMA DELIVERY UPDATE Neil Bliss

  2. Production Quadrupoles • 2nd rotating coil bench alignment scheduled for July 22 – 24 • Some issues to be resolved in the design of the bench to ensure we have the best accuracy from the magnet centre to the fiducials • Delivery of 12 - 20 magnets per week from August QD Rotating coil bench magnet location QF

  3. Production Cavities Machining • Machining - complete • EB welding - complete • Brazing – in progress • Re measure Frequency & Q • Dimensional checks • Chemical etching • Clean • Assemble and pump down • Measure F & Q • Leak Check • Bakeout • RGA & vacuum measurement • Delivery of batches from Sep 5 E B welding

  4. Procurement Exercise Update • Contract placed on Scaditronix on 29 May for the injection line magnets.13 quads and 4 dipoles. Steel ordered. Preliminary design review held on 2 July a final design review due next week. Delivery - end of October • Injection line vacuum chambers, including the bpm and OTR assemblies. Tender return July 25. Delivery – Mid September – end of October • Girder design in progressaiming at staged deliveries – mid October - November • Contract placed on VG Scienta on 19 June for the ring standard vacuum chambers. Delivery towards end of October - early November • Contract placed on Testbourne for the BPM pickups for the injection line and ring that will weld into the vacuum chambers – delivery end of September • OJEC advert placed on 20 June for the kickers, kicker power supplies and septums, 52 day process bids by mid August, delivery by April 09 • OJEC tender bids for RF system still under evaluation. Delivery required for end of February 09

  5. GANTT Chart

More Related