1. 2012 Planned Facilities Reconstruction Project
2. Planned Facilities Reconstruction Health & Life Safety
Energy Conservation & Management
Security Upgrades
Reconstruction
Sitework
3. Why Do We Need A Capital Project? State Education Department Requirements
Manual Of Planning Standards
NYS Building Codes
Fire Inspections (Annual)
Visual Inspections (Annual)
Building Condition Survey (5 Year)
5 Year Capital Plan
NYCRR Part 155 Regulations of Commissioner
The School District is Required to Maintain the Buildings and Grounds to Certain Standards to Provide a Healthy & Safe Learning Environment
5. All District Buildings Public Address/Clock System
-Systems are currently serviced by different vendors
-MHS is currently functioning on two separate schedules
Stone Joint Replacement
Parking Lot Repair
6. Middle/High School & Fenner Elementary
7. Temple Elementary
8. Middle/High School Terrazzo Reconstruction (1935)
Asbestos Floor Tile Removal (1967)
Ceramic Tile Replacement (1967)
Stair Tread Replacement
Exhaust Fan Replacement (1967)
Upgrade Security Entrance Access
9. Fenner Elementary Replace Roof (1989)
Replace Interior Gym Doors
Replace Interior Door Hardware (1989)
Replace Boiler & Water Heater
Upgrade HVAC Controls
Upgrade Security System
Repair Sidewalks
10. Temple Elementary Upgrade Security System
Replace Exhaust Fans
Repair Sidewalk
11. Bus Garage Add Heat Detection
Upgrade Fire Alarm System
Masonry Repair
12. Project Budget MIDDLE/ HIGH SCHOOL $1,513,000
FENNER ELEMENTARY $ 907,000
TEMPLE ELEMENTARY $ 221,000
BUS GARAGE $ 59,000
Total Budget $2,700,000