HOOSIER HEARTLAND HIGHWAY

HOOSIER HEARTLAND HIGHWAY. Public Information Meeting – August 27, 2009 STATE ROAD 25, SEGMENT 2 From 0.42 mile east of Tippecanoe/Carroll County line to 0.20 mile east of CR400W Length of 8.46 miles with 9 Bridges INDOT DESIGN CONSULTANT: Bernardin Lochmueller & Associates, Inc.

mira-vang
Download Presentation

HOOSIER HEARTLAND HIGHWAY

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HOOSIERHEARTLANDHIGHWAY Public Information Meeting – August 27, 2009 STATE ROAD 25, SEGMENT 2 From 0.42 mile east of Tippecanoe/Carroll County line to 0.20 mile east of CR400W Length of 8.46 miles with 9 Bridges INDOT DESIGN CONSULTANT: Bernardin Lochmueller & Associates, Inc. Jeff Whitaker, P.E.

  2. Section 2: Central Segment • Current Design Status • Road & Bridge Design - 50% Complete • R/W Engineering – 50% Complete

  3. Section 2: Central Segment • Work Schedule • Hydraulic Review & Grade Review (Completed 2007) • Context Sensitive Solution Design (Completed August 28, 2008) • Preliminary Field Check of Road & Bridge (February 23, 2009) • Public Information Meeting (August 27, 2009) • Design Approval (September 2009)

  4. Section 2: Central Segment • Right-of-Way Schedule • R/W Engineering & Acquisition (2008-2011) • 90 Parcels of Property • 26 Relocation • R/W Appraising (Oct/Nov 2009-April 2010) • Property Information

  5. Section 2: Central Segment • Construction Schedule • Phase 2A - (November 2010- 2012) • Phase 2B – (March 2011-2013) • Phase 2C – (December 2011-2013) • Phase 2D – (October 2011-2013)

  6. Section 2: Central Segment • Alignment Issues: • Alignment was shifted on SR 25 and Connector Roads to avoid Environmental Sensitive Areas • Alignment shifted on SR 218 because of an at-grade Railroad Crossing • Alignment shifted on Connector Road between the New SR 218 and Existing SR 218 • Robinson Branch Bridge Added: • Because of Environmental Stream Impacts & Wetland Seeps • Upstream Bridge Creek Bridge Added: • Because of hydraulics & cost savings

  7. Section 2: Central Segment Main Street Access • Local Officials Requested – Main Street Access Revised • Improve Entrance into Delphi • Signature Bridge for the Monon Trail

  8. Section 2: Central Segment Context Sensitive Solutions - Deer Creek Valley Rural Historic District • Committee Stakeholders • Total of 4 Meetings, Last Meeting August 28, 2008 • Context Sensitive Design Solutions • Texturing & Coloring of the Retaining Walls & Bridge Piers • Shape of Bridge Piers • Type of Bridge Railing • Type of Landscaping • Type of Lighting at Main Street

  9. HOOSIERHEARTLANDHIGHWAY Thank You For Coming Questions Contact: Aimee Kindred, Public Involvement Director Office: (317)234-4938 Mobile: (317)517-2166 Fax: (317)233-4929 Email: Akindred@indot.in.gov