An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WEF SDC 2011 Expansion of Acton WWTP University of Guelph Team: Alexandra Chan Adam Erb Cynthia Mason Julia Veerman October 16, 2011

  2. Outline • Introduction • Population Analysis • Process Selection • Phase 1 Design • Modeling • Noise & Odour Control • Construction • Phase 2 Design • Economic Evaluation • Conclusions and Recommendations

  3. Review of Existing Facility

  4. Problem Statement • Current WWTP operating near peak capacity • Need to increase capacity to accommodate projected growth in two phases • Meet projected effluent criteria

  5. Design Basis

  6. Population Analysis • Predicted linear growth • Assumed water saving devices at 10% • Infiltration/Inflow at 204 L/c/d

  7. Process Selection • Constraints • Accommodate design flows • Meet effluent discharge limits • Use available land • Be compatible with existing facility • Criteria • Cost effectiveness • Integration with existing facility • Environmental impact and footprint minimization

  8. Phase 1 Design

  9. Process Flow

  10. Primary Clarifier

  11. Primary Clarifier • Add two rectangular clarifiers • New volume 256 m3 • ADF SOR of 27.5 m3/m2/day • Maximum day flow • 62.5% TSS removal • 40.3% BOD removal • Chain & scraper sludge collector and scum removal system

  12. Secondary Treatment

  13. Aeration System • Two conventional plug flow activated‐sludge system with nitrification • Accommodate 1275 m3/d required • Target MLSS = 4000 mg/L • SRT = 12 days • Fine bubble aeration • Positive displacement blower • Designed for max day flow + additional feedback flow

  14. Secondary Clarifier • Two additional secondary clarifiers • Limiting solid flux concept • MLSS = 6620 mg/L • Overflow = 31 m3/m2d • Chain & scraper sludge collector and scum removal system • Max day flow design

  15. Tertiary Treatment

  16. Chemical Addition • 85 mg/L liquid alum with 45% purity – 824 kg/d • Addition point in activated sludge tank

  17. Filtration • Dual media deep bed filtration • Existing filters work well to meet limits • Widely accepted in WWT • Easily retrofit • Leopold™ Type S™ Underdrain • Air scour + surface wash backwash • Max day flow design with one filter out of commission • SLR of 7.2 m3/m2/h http://www.wateronline.com/product.mvc/Universal-Type-S-Underdrain-0002

  18. UV Disinfection • UV selected as best disinfection method • Trojan UV3000Plus™ system • LP/HI lamp • Automatic and continuous dose pacing • Automated mechanical/chemical cleaning • Automatic level controller • Sized for peak flow

  19. Solids Handling

  20. Bio-Solids Digester • Sequential dual-stage digester series • Add new series in parallel • Methane gas collected for heating • Thermophillic Stage 1 • SRT 2 days • Recirculation pump mixing • Mesophillic Stage 2 • SRT 8 days

  21. Sludge Drying • Belt press drying after digester • Polymer addition • Increases solids concentration from ~3% to ~25% • Cost-effective in disposal • Reduces footprint

  22. Mass Balance

  23. System Controls and Instrumentation • Control strategy • Increased control and monitoring • Small relative capital cost • Significant efficiency improvements • Biological treatment • Aeration accounts for up to 50% energy consumption • Matched oxygen demand profile • Intelligent feedback control for aeration, RAS, WAS

  24. System Controls and Instrumentation • Clarifiers • Monitoring • Sludge pumping control mechanisms • Digesters • Control for feeding rates, recirculation, heating, withdrawal • Tertiary Treatment • Flow splitting • SCADA • Interfacing with SCADA for remote monitoring

  25. Hydraulic Profile

  26. Phase 1 – Model Inputs • Projected peak influent concentrations and flows • Proposed plant sizing • Clarifier modeling based on Lessard and Beck dynamic model • Activated sludge modeling completed using the IAWQ1 model

  27. Phase 1 – Model Results • BOD and NH3 water quality requirements met • Model Shortcomings: • Chemical phosphorous treatment or tertiary filtration not accounted for

  28. Odour and Noise Control • Currently no odour or noise issues • Reduce odour and noise • Buffer zone • Housing potential equipment

  29. Construction • Completion in 24 months • Best management practices: • Construct in phases • Protect waterways • Provide training • Conduct inspections

  30. Phase 2 Conceptual Design

  31. Phase 2 Conceptual Design • Modify Plant B aeration basin configuration to plug flow + BNR • Investigate: • Membrane technology • Phosphorus extraction

  32. Phase 1 – Capital Cost Total Capital Cost Estimate = $24M

  33. Phase 1 – O&M Cost Annual O&M Cost Estimate = $1.2M

  34. Phase 2 – Capital Cost Total Capital Cost Estimate = $12M

  35. Conclusions • Expansion design to increase the Acton WWTP capacity • Preliminary Phase 1 design • Additional clarifier, disinfection, and anaerobic digestion trains • CAS + nitrification • Deep bed dual media filter • Belt press • Conceptual Phase 2 design

  36. Recommendations • Implement sewer system improvement plan • Conduct more simulations • Obtain more cost-specific information from manufacturers • Conduct pilot tests

  37. Acknowledgements Dr. Hongde Zhou, P.Eng., University of Guelph – Faculty Advisor David Arsenault, P.Eng., CH2M Hill – Consulting Advisor Rafiq Qutub, P.Eng., WEAO – SDC Sub-Committee Chair Lauren Zuravnsky, P.E., WEF – Design Competition Sub-Committee Chair