14 DNI PRED PLANIRANO ZAUSTAVITVIJO (REMONT), ELEKTRARNA DELUJE ŽE 500 DNI NA POLNI MOČI …

14 DNI PRED PLANIRANO ZAUSTAVITVIJO (REMONT), ELEKTRARNA DELUJE ŽE 500 DNI NA POLNI MOČI …. 1.10.2010 SMO DOSEGLI NOV REKORD - 515 DNI OBRATOVANJA BREZ PREKINITVE ALI VEČJE REDUKCIJE MOČI IN HKRATI ZAČELI REMONT

monifa
Download Presentation

14 DNI PRED PLANIRANO ZAUSTAVITVIJO (REMONT), ELEKTRARNA DELUJE ŽE 500 DNI NA POLNI MOČI …

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 14 DNI PRED PLANIRANO ZAUSTAVITVIJO (REMONT), ELEKTRARNA DELUJE ŽE 500 DNI NA POLNI MOČI …

  2. 1.10.2010 SMO DOSEGLI NOV REKORD - 515 DNI OBRATOVANJA BREZ PREKINITVE ALI VEČJE REDUKCIJE MOČI IN HKRATI ZAČELI REMONT REMONT – planirana zaustavitev (cca. 30 dni) in popravilo elektrarne (vsakih 18 mesecev) Reaktorska zgradba To sem jaz

  3. Notranjost reaktorske zgradbe, višina 65 metrov. V njej je reaktor z gorivnimi elementi, uparljalnik, tlačnik, ventilacijske enote, … Ventilacija Uparjalnik 1

  4. V začetni fazi remonta se celotno gorivo odstrani iz reaktorja in ga shrani v poseben bazen. V zadnji fazi remonta se gorivo spet vrača v reaktor. Polovico goriva se vstavi novega, druga polovica je staro gorivo. Nadalje slike prikazujejo vračanje goriva. Reaktorski bazen se napolni z vodo, nato pa gorivne elemente pripeljemo s strojem za menjavo goriva v reaktorsko posodo... Stroj za menjavo goriva Reaktorski bazen z vodo Reaktorska posoda (reaktor)

  5. 19.10.2010 Polnjenje reaktorske sredice z gorivnimi elementi, polovica goriva je novega Staro gorivo (temne barve) Novo gorivo (svetle barve) Vstavljanje gorivnega elementa v reaktorsko sredico Prostor za ostalo gorivo Skupaj je v reaktorju 121 gorivnih elementov

  6. Nivo vode Gorivni elementi (uran)

  7. 20.10.2010 - ¾ reaktorskega goriva (elementov) je že v sredici Novo gorivo (svetlo) Staro gorivo (temno)

  8. Kontrolne palice, s katerimi nadzorujemo toploto v reaktorju

  9. Ko je reaktor poln goriva, se voda iz reaktorskega bazena izčrpa, na reaktorsko posodo pa namesti pokrov z mehanizmom za kontrolne palice mehanizem kontrolnih palic pokrov

  10. Na koncu delavci pokrov privijačijo z vijaki, tako da “ekonom” lonec dihta …

  11. Pogled iz “reaktorja” na Krško celulozo- seveda možno le v remontu, ko je “okno” odprto

  12. Za menoj stoji motor vseh motorjev – motor ki poganja črpalko za kroženje vode skozi reaktor, 6300 kV, 5.2 MW. Motor porabi za svoje delovanje toliko energije, kot jo v povprečju proizvede ena savska elektrarna. Na elektrarni sta dva takšna motorja

  13. Turbinska zgradba. Tu je generator, ki pretvori mehansko energijo turbine v električno in tako po daljnovodu pride do računalnika, da lahko gledaš ta email. turbina generator

  14. Največja aktivnost v letošnjem remontu je zamenjava statorja glavnega generatorja Novi generator v “zraku” – 450 ton

  15. SEDAJ SMO PRI KONCU REMONTA IN UPAJMO, DA BOMO ELEKTRARNO USPEŠNO ZAGNALI IN JO USTAVILI ŠELE ČEZ 500 dni, KO BO NOVA PLANIRANA ZAUSTAVITEV (REMONT). LP iz Krškega