2008 LTU and Beam Dump Installation Tim Montagne J Langton. Agenda. 2008 LTU and Beam Dump Installation Subsystem Responsibilities Installation Objectives LTU Installation Schedule Beam Dump Installation Schedule LTU and Beam Dump System Test Schedule LTU Installation Documentation
E N D
Agenda • 2008 LTU and Beam Dump Installation • Subsystem Responsibilities • Installation Objectives • LTU Installation Schedule • Beam Dump Installation Schedule • LTU and Beam Dump System Test Schedule • LTU Installation Documentation • Beam Dump Installation Documentation • Safety
Subsystem Responsibilities • Mike Saleski - Safety Systems • J. Chan - Linac Project Management • K. Ratcliffe - Installation Manager • T. Montagne - LTU Integration Engineering • J Langton – Beam Dump Integration Engineering • P. Rodriguez - Cable Installation • R. Fuller - Controls Checkout
Installation Objectives • Install and align beamline structural supports • Install and align magnets • Install and align diagnostics • Install and verify vacuum system • Install and verify: • Magnet cooling water supply and return • Vacuum pump power and vacuum gauge signal • AC power • Magnet DC power • Diagnostics controls • Pneumatics • Purge Gas • Install and verify safety systems • Radiation Shielding • BCS system • MPS system • PPS system
LTU Installation Schedule - BTH West • BTH west co-occupancy starting 12/2/07 • Alignment network and monumentation 12/20/07-1/08/08 • Stand hole pattern layout 1/09/08 -1/11/08 • Core drill mount holes 1/14/08 -1/28/08 • Stand installation 1/29/08 -2/19/08 • Install racks & cable plant 9/04/07-11/28/07 • Install components 2/20/08-4/01/08
LTU Installation Schedule - BTH • BTH co-occupancy starting 12/05/07 • Alignment network and monumentation 1/09/08-1/23/08 • Stand hole pattern layout 1/24/08 -1/29/08 • Core drill mount holes 1/30/08 -2/12/08 • Stand installation 2/06/08 -3/19/08 • Install racks & cable plant 12/05/07-3/10/08 • Install components 3/20/08-6/12/08
Beam Dump Installation Schedule • Beam dump co-occupancy starting 12/05/07 • Alignment network and monumentation 12/05/07-2/01/08 • Stand hole pattern layout 12/05/07 - 2/01/08 • Core drill mount holes 12/05/07 - 2/01/08 • Stand installation 2/04/08 - 2/15/08 • Install racks & cable plant 2/19/08 - 3/17/08 • Install components 4/21/08 - 6/18/08
LTU and Beam Dump System Test Schedule • LTU system test complete 10/01/08 • Beam dump system test complete 9/18/08
Beam Dump Installation Documentation • Beam dump installation documentation is complete pending release.
Safety • The listed documents are required prior to installation and operation • Safety Overview Approval • Work authorization approval from LCLS and AD • Penetration permit • Earthquake approval • Building inspection approval • Electric safety approval • Radiation Physics approval • Non-ionizing approval