Masco Builder Cabinet Group. Financial & Operational Business Review Letter , 2009. Leadership Agenda – bt ². Duncanville Using post-production kaizen events to improve customer satisfaction Financial close is challenged due to Oracle issues – resolution in progress Los Lunas
E N D
Masco Builder Cabinet Group Financial & Operational Business Review Letter , 2009
Leadership Agenda – bt² • Duncanville • Using post-production kaizen events to improve customer satisfaction • Financial close is challenged due to Oracle issues – resolution in progress • Los Lunas • Delay to 8/17 to ensure no customer impacts • Tests using production orders revealing issues in shop floor paperwork (sequencing) • Day in the Life (UAT), Stress, and Regression Testing planned for 7/13 – 7/31 • Future Releases • QBAC changes defined for component plants (Cedar Hill and Duncanville Mill) • Working to complete Duncanville Assembly design changes • Component plant design review complete