Broadway Avenue Improvement Project Update

Broadway Avenue Improvement Project Update. Forest Lake EDA Meeting June 27, 2011. CR 2 and I-35 Bridge/Interchange First Ave NW ( Backage Road) CR 2/Broadway Avenue Roadway Utilities Hardwood Creek Pedestrian Bridge Impact of Possible State Shutdown (July 1) Communication Update.

nadine
Download Presentation

Broadway Avenue Improvement Project Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Broadway Avenue Improvement Project Update Forest Lake EDA Meeting June 27, 2011

  2. CR 2 and I-35 Bridge/Interchange First Ave NW (Backage Road) CR 2/Broadway Avenue Roadway Utilities Hardwood Creek Pedestrian Bridge Impact of Possible State Shutdown (July 1) Communication Update Broadway Avenue Improvement Project Update

  3. Bridge Removal CR 2 and I-35 Bridge/Interchange Week of May 9 Bridge Removal between 9PM-6AM 4 nights

  4. Interchange Construction CR 2 and I-35 Bridge/Interchange Construction on temporary ramp Surcharge construction

  5. Bridge Construction CR 2 and I-35 Bridge/Interchange Pouring concrete on east abutment stem wall A look at the east abutment Prior to backfilling

  6. Bridge Construction CR 2 and I-35 Bridge/Interchange Excavation for the center pier (In I-35 median)

  7. First Ave NW (Backage Road) Open to Traffic– Friday, July 1

  8. Broadway Ave Roadwork To begin after the Backage Road (First Ave NW) is open to traffic.

  9. Utilities Watermain work Directional boring utility work

  10. Hardwood Creek Pedestrian Bridge May 6, 2011

  11. Hardwood Creek Pedestrian Bridge Painting the walls Pouring the bridge deck

  12. Hardwood Creek Pedestrian Bridge Hardwood Creek Bridge Open Temporarily The Pedestrian Bridge will be open from July 1-July 4. The Bridge will close again beginning July 5. The Pedestrian Bridge will be open at the end of July. Chain-link fencing is temporary.

  13. Impact of Possible State Shutdown Washington County Engineer Wayne Sandberg to give a more detailed presentation at City Council meeting tonight – 7PM.

  14. Communication Update • Broadway Bulletin - 31 Businesses participating • - 15 distribution sites • Go Local Discount Card - 18 Businesses participating • - Expires 12/31/11 • Where’s the Concrete Truck? • Arts in the Park

  15. Communication Update • Facebook: - 35 people follow the page • - posts have gotten up to 250 Impressions • Twitter: - 113 Followers • YouTube: - Construction Videos • - “A View of Broadway” Videos • Website: - 1384 unique visitors (June) • - 2228 total visits (June)

  16. Broadway Avenue Improvement Project Update Any Questions?