The ‘Measure L’ Construction Program. Presented By : Bill Winslow Program Manager, Bernards. Presented to the Citizens’ Oversight Committee November 29, 2011. Presented by Bill Winslow Program Manager, Bernards. Summary. November 29, 2011. COC Presentation.
E N D
The ‘Measure L’ Construction Program • Presented By: • Bill Winslow • Program Manager, Bernards Presented to the Citizens’ Oversight Committee November 29, 2011 Presented by Bill Winslow Program Manager, Bernards
Summary November 29, 2011 COC Presentation • Completed Projects 2002-2011 • Chino Campus • Fontana Campus • Rancho Cucamonga Campus • Schedule • Financials • Questions • An estimated 350,000 square feet of new facilities and a multitude of completed site improvement projects have made a significant contribution towards improving the physical learning environment.
Completed Projects 2002-2011 (Partial Listing) November 29, 2011 COC Presentation • Renovate/Paint Auto Tech Lab • Infrastructure/Campus Theme • Environmental Impact Report • Renovate Athletics Office • Scoreboards • Snack Bar • Track & Field Timer • Stadium Flag Pole • Rad Tech Retrofit • San Antonio Comm. Hosp./CNA • Master Plan (Chino) • Vocational Education – Phase I • Wargin Hall – Phase I • Visitor’s Restroom/ADA Access • Science Complex Site work • Theater Fire Alarm • Bookstore Loading Dock • North Parking Lot Irrigation • North Parking Lot Landscaping • ATL Landscaping • Nature Preserve Fence • Central Plant Phase IA • Central Plant Phase IB • College Drive • Softball Field • Ralph M. Lewis Center (Fontana) • Wilson/College Dr.ive Intersection • Marie Kane Center for Student • Services/ Administration • Theatre – Phase I • North Parking Lot • Science Complex • Don Berz Excellence Building • College Drive Landscaping • Maintenance Yard Drainage • Agricultural Demonstration Area • Skills Road Extension • Fire Lane/Science Site Lighting • New Marquee • Physical, Health, and Life Science • Health and Life Science Re-Roof • Main Instructional Building (Chino) • New Elevator Tower • Parking Lot 12 • Health Sciences Bldg. (Chino) • Community Center Bldg. (Chino) • Library Lawn • Landscaping (Fontana) • Physical Science Complex Roof • Replacement • Language Arts/Social Science • Energy Project • Parking Lot Upgrades (Fontana) • Chino Health Science Parking Lot • Data and Telecom Cabling • Sports Center • Visual and Performing Arts Complex • Visual and Performing Arts Complex • Landscape Addition • Math Success Center & Physical • Science Renovations • Physical Education Facility • Gymnasium Renovation • Aviary Landscape • Central Plant Build Out – Phase 1C – • Hot Water Upgrades • Student Services/Administration East • Doors • Fire Alarm Upgrades
District Campuses November 29, 2011 COC Presentation
Chino Campus November 29, 2011 COC Presentation • Library/Learning Resource Center Future Location Projects in Planning
Fontana Campus November 29, 2011 COC Presentation Aerial View September 2011
Fontana Campus November 29, 2011 COC Presentation Projects Completed in 2011 • Academic Building • New 30,400 sq. ft. building includes: laboratories, lecture rooms, dance/yoga room, art studio, library, and bookstore
Fontana Campus November 29, 2011 COC Presentation Projects Completed in 2011 • Academic Building
Rancho Cucamonga Campus November 29, 2011 COC Presentation Aerial View September 2011
Rancho Cucamonga Campus November 29, 2011 COC Presentation • Greenhouse • Estimated Completion: December 2011 Projects Under Construction • Installation of a prefabricated greenhouse structure at the Science Complex
Rancho Cucamonga Campus November 29, 2011 COC Presentation • Business Education Renovation Projects Completed in 2011 • Interior and exterior renovation of the existing Business Education building includes energy and accessibility upgrades
Rancho Cucamonga Campus November 29, 2011 COC Presentation • Michael Alexander Campus Center Projects Completed in 2011 New 16,454 sq. ft. two-story building includes: staff and student dining rooms, coffee bar, kitchen and server, health services, student government, Extended Opportunity Programs & Services, and career services
Rancho Cucamonga Campus November 29, 2011 COC Presentation • Michael Alexander Campus Center Projects Completed in 2011
Rancho Cucamonga Campus November 29, 2011 COC Presentation • Projects in Pre-Bid • Central Plant Build Out – Phase 1C – TES Tank • Installation of thermal energy storage tank and six new boilers at Central Plant • Health Science Pathway • Addition of a concrete pathway from Health Sciences to the Michael Alexander Campus Center • North Parking Lot Drainage • Addition of drainage systems at Parking Lot 4 • Projects in Design • Physical Education Athletics – Parking Lot and Flagpole • Parking lot resurfacing and striping with new flagpole • Community Trail Landscaping • Landscaping and irrigation
Rancho Cucamonga Campus November 29, 2011 COC Presentation • Projects in Planning • Language/Liberal Arts and Letters • Library Remodel/Expansion • Wargin Hall Remodel • Vocational and Student Service Support Remodel
Construction Cost Summary November 29, 2011 COC Presentation Completed Projects 2009-2011
Summary of Funds November 29, 2011 COC Presentation Program Funds (Includes Rancho Cucamonga, Fontana, and Chino Campuses) Measure L Bond Funds (Includes Rancho Cucamonga, Fontana, and Chino Campuses)
Remaining Funds November 29, 2011 COC Presentation Program Funds (Includes Rancho Cucamonga, Fontana, and Chino Campuses) Measure L Bond Funds (Includes Rancho Cucamonga, Fontana, and Chino Campuses)