90 likes | 197 Views
AB/ATB equipment Hardware commissioning. Oliver Aberle On behalf of the ATB Group and the Collimation Project. Beam dumps (TDE). Collimators TCP, TCS, TCLI, TCLP, TCT, TCHS. Dumps (TED) and stoppers (TBSE). Injection protection (TDI, TCDI, TCDD). Schedule for installation.
E N D
AB/ATB equipmentHardware commissioning Oliver Aberle On behalf of the ATB Group and the Collimation Project Beam dumps (TDE) Collimators TCP, TCS, TCLI, TCLP, TCT, TCHS Dumps (TED) and stoppers (TBSE) Injection protection (TDI, TCDI, TCDD) Review of Hardware commissioning
Schedule for installation • Beam obstacles Review of Hardware commissioning
Production schedule • Collimators • Preliminary data, subject to discussions with company Review of Hardware commissioning
LHC collimators • Collimators with different angles • Vacuum interconnect modules Review of Hardware commissioning
Collimator project • Responsibilities in AB, AT and TS Review of Hardware commissioning
Hardware commissioning requirements • Prerequisites for Hardware Commissioning: • Installation completed • Water and Electricity • Control Network available • Vacuum and bake out done • Access to the tunnel Review of Hardware commissioning
Phase I • Preparation on Surface 2006 - 2007 • Equipment assembled on surface • UHV Test of the system • Commissioning of the full system on surface (Motorisation, monitoring, cooling, vacuum) • Relative alignment by metrology of the moving components, calibration of motors and encoders • Align with reference to the planned position in the tunnel • Underground work summer 2006 - 2007 • Installation of the support units and alignment with mock-up • Check the cabling (motors, controls, interlocks) (done by cabling service) • Connect to the cooling circuit • Vacuum chamber connection • Verification of the alignment Review of Hardware commissioning
Hardware commissioning requirements Review of Hardware commissioning
Conclusions • This is a first discussion on the collimator commissioning • Some iterations are needed (Lab tests, final set up) • The design of some collimator types is not yet finished (special design for two-in-one type) • One contract with industry for all collimator types • Two full working prototype have been installed, commissioned and operated in the SPS, summer 2004 • Plug-in system will ease the installation and commissioning • specific check list for each component under production(end 2005) Review of Hardware commissioning