1 / 12

Muon Acceleration Program Technology Development

This program focuses on the development of technology for muon acceleration, including RF cavities, magnets, and targetry. The goal is to advance the field and optimize the efficiency of muon acceleration.

neilson
Download Presentation

Muon Acceleration Program Technology Development

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. It is not a Project! Muon Acceleration ProgramTechnology Development A. Bross NFMCC CM January 15, 2010 A. Bross NFMCC CM January 15, 2009

  2. MAP - Technology Development A. Bross NFMCC CM January 15, 2009

  3. Technology DevelopmentLevel 2 Task A. Bross NFMCC CM January 15, 2009

  4. Normal Conducting RF • Y’All know the Drill: • Three Approaches • Reduce/eliminate field emission in Vacuum RF • Material Studies • Process cavities utilizing SCRF techniques • RF cavities filled with HP gas • Utilize Paschen effect to stop breakdown • Magnetic Insulation in Vacuum RF • Eliminate magnetic focusing • Not Yet Tested • This is an area where there is already great pressure to down-select • “Resistance is Futile” • But we must, at least initially A. Bross NFMCC CM January 15, 2009

  5. RF Milestones A. Bross NFMCC CM January 15, 2009

  6. Super Conducting RF • You we hear about this in detail from Don next • But: • Need lots of 201 MHz • But, use 500 MHz as test vehicle • Application of ALD A. Bross NFMCC CM January 15, 2009

  7. Magnets • Other than the Very-Large-Magnetic volume needed for the NF TASD concept, all magnet work for MC/MCDFS • HTS solenoid R&D to assess the parameters that are likely to be achieved • HCC magnet R&D to assess the feasibility of this type of cooling channel and possibly to build a demonstration magnet for an HCC test section (see Section 6.2.2) • Note: Success with the HCC could make it cooling choice for NF also. • Open mid-plane dipole magnet R&D to assess the viability of this magnet type for the collider ring • Very fast ramping normal-conducting magnets for the later stages of acceleration • This may turn out to be an indispensible cost-saving technology • Other magnet studies to inform choices, parameters and cost estimates for the target-station solenoid and accelerator magnets. A. Bross NFMCC CM January 15, 2009

  8. Milestones A. Bross NFMCC CM January 15, 2009

  9. Targetry • Targetry is not currently explicitly in the text of the MAP proposal under Technology Development, but under the ISD-NF • With the input from the MERIT experiment, the U.S. contribution to the IDS-NF in this area will be on more advanced simulations to set definitive benchmarks for the NF/MC target system • Make the next iteration on the facility design (following the ORNL/TM-2001/124 technical report) and to develop engineering details of component parts of the system such as the target solenoid • But from Kirk’s (Harold’s) talk yesterday, we see that there is room for optimization • Splash mitigation in the mercury beam dump. • Possible drain of mercury out upstream end of magnets. • Downstream beam window. • Water-cooled tungsten-carbide shield of superconducting magnets. • HTS fabrication of the superconducting magnets. • Improved nozzle for delivery of Hg jet • -------- A. Bross NFMCC CM January 15, 2009

  10. Overall Goals A. Bross NFMCC CM January 15, 2009

  11. Global Manpower Effort - FTE This is a sum over all types: Scientists, Engineers, Postdocs and Technicians A. Bross NFMCC CM January 15, 2009

  12. Overall Effort & Likely available Resources • With current guidance we are not likely going to be able to do even all the tasks we currently have on our “A” list • Getting convergence on the overall Program Plan will take some work over the next weeks. A. Bross NFMCC CM January 15, 2009

More Related