2013 Meson Hall Clean-up and Manpower Requirements (Oct 17, 2012) L.Lee

2013 Meson Hall Clean-up and Manpower Requirements (Oct 17, 2012) L.Lee. **Storage Space is still the important issue (i.e. for magnets, stands, equipment in: M13, M11, above 1A/1B). Vijay / Mark. ARIEL & Shutdown Plan (2012-2016) - DRAFT. Sept. 5, 2012. 2012. 2013. 2015. 2016. 2014.

nen
Download Presentation

2013 Meson Hall Clean-up and Manpower Requirements (Oct 17, 2012) L.Lee

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2013 Meson Hall Clean-up and Manpower Requirements (Oct 17, 2012) L.Lee **Storage Space is still the important issue (i.e. for magnets, stands, equipment in: M13, M11, above 1A/1B)

  2. Vijay / Mark ARIEL & Shutdown Plan (2012-2016) - DRAFT Sept. 5, 2012 2012 2013 2015 2016 2014 Major Tasks A J O J A J O J A J O J A J O J A J O Legend: 100Kw e-Beam E-Hall Available Tunnel & Bldg Avail LC (50Kw) e-Beam ARIEL & E-Linac Milestones Shutdown Jobs Construction Non Shutdown Jobs Install & Connect ELBT & EINJ-2 in E-Hall ARIEL & E-Linac Cryogenic Plant (delivery & operational) Test & Commission High Power RF System (Klystron & HVPS) Install EHBT from ACM to Target Hall Install & Connect EACA, Test & Comm Beam in E-Hall (50kW & 100kW) Complete IRIS Complete EMMA Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods Complete M20 Front end & M9A Front end work 2012 / 2013 Cleanup (incl M11 Expt area, above 1A/1B shielding blocks) Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services Install Kicker Ceramic beam Tube & Services Install Septum & Dipole (with services, where possible) 2014 Shutdowns Mod Vault Quads (rem. Steerers), 1BVB2, and BL1A/1B Reconfigure Vault-to-1A Shld, and beamline Shld to run 1A Remove & Store M13 Front end, Hot Blocks & Crumbling Blocks Core through M13 Block Install Kicker, UCN Beam line, Services & Controls 2015 Install Base Layer of UCN Shielding to Run BL/1A Install UCN Shielding Install UCN Spallation Target & R/Handling System, & UCN Source 2016 Complete Shielding & Commissioning Tests Dsgn Procure & Inst Procure & Inst Upgrades Hel liquefier system (and UCN upgrade)

  3. Vijay / Mark ARIEL & Shutdown Plan (2012-2016) - DRAFT Sept. 5, 2012 2012 2013 2015 2016 2014 Major Tasks A J O J A J O J A J O J A J O J A J O Legend: 100Kw e-Beam E-Hall Available Tunnel & Bldg Avail LC (50Kw) e-Beam ARIEL & E-Linac Milestones Shutdown Jobs Construction Non Shutdown Jobs Install & Connect ELBT & EINJ-2 in E-Hall ARIEL & E-Linac Cryogenic Plant (delivery & operational) Test & Commission High Power RF System (Klystron & HVPS) Install EHBT from ACM to Target Hall Install & Connect EACA, Test & Comm Beam in E-Hall (50kW & 100kW) Complete IRIS Complete EMMA Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods 1 Complete M20 Front end & M9A Front end work 2012 / 2013 Cleanup (incl M11 Expt area, above 1A/1B shielding blocks) 2 Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services 3 Install Kicker Ceramic beam Tube & Services Install Septum & Dipole (with services, where possible) 2014 Shutdowns Mod Vault Quads (rem. Steerers), 1BVB2, and BL1A/1B Reconfigure Vault-to-1A Shld, and beamline Shld to run 1A Remove & Store M13 Front end, Hot Blocks & Crumbling Blocks Core through M13 Block Install Kicker, UCN Beam line, Services & Controls 2015 Install Base Layer of UCN Shielding to Run BL/1A Install UCN Shielding Install UCN Spallation Target & R/Handling System, & UCN Source 2016 Complete Shielding & Commissioning Tests Dsgn Procure & Inst Procure & Inst Upgrades Hel liquefier system (and UCN upgrade)

  4. ARIEL & Shutdown Plan (2012-2016) - DRAFT Oct. 17, 2012 2012 2013 2015 2016 2014 Major Tasks A J O J A J O J A J O J A J O J A J O Legend: 100Kw e-Beam E-Hall Available Tunnel & Bldg Avail LC (50Kw) e-Beam ARIEL & E-Linac Milestones Shutdown Jobs Construction Non Shutdown Jobs Install & Connect ELBT & EINJ-2 in E-Hall ARIEL & E-Linac Cryogenic Plant (delivery & operational) Test & Commission High Power RF System (Klystron & HVPS) Install EHBT from ACM to Target Hall Install & Connect EACA, Test & Comm Beam in E-Hall (50kW & 100kW) Complete IRIS Complete EMMA Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods 1 Complete M20 Front end & M9A Front end work 2012 / 2013 Cleanup (incl M11 Expt area, above 1A/1B shielding blocks) 2 Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services 3 Install Kicker Ceramic beam Tube & Services July-2013: M11,M13 floor area cleared Install Septum & Dipole (with services, where possible) 2014 Shutdowns Mod Vault Quads (rem. Steerers), 1BVB2, and BL1A/1B Reconfigure Vault-to-1A Shld, and beamline Shld to run 1A Remove & Store M13 Front end, Hot Blocks & Crumbling Blocks Core through M13 Block Install Kicker, UCN Beam line, Services & Controls 2015 Install Base Layer of UCN Shielding to Run BL/1A Install UCN Shielding Install UCN Spallation Target & R/Handling System, & UCN Source 2016 Complete Shielding & Commissioning Tests Dsgn Procure & Inst Procure & Inst Upgrades Hel liquefier system (and UCN upgrade)

  5. Comments: **Cleanup (main issue): Identifying Storage Space of Critical Importance - Find/Build new storage space on-site (?) - Store off-site (?) 1. Assess/Vault mods: Cleanup issues; Vault mods (July-Dec/2012) M11 Assess Cleanup issues (M11 platform, services, cables) M13 Assess Cleanup issues (Storage/Disposal of magnets, services, cables) 1A/1B Determine “ownership” of equipment on 1A/1B shielding blocks (email notice, with link to pictures of equipment) (Jan-Mar/2013) Vault Rewire Vault Quads for Steering Capability during 2013 Shutdown (Shutdown Work Request submitted) Allows for testing in 2013, with “Existing” & “New” steering available Setup shunts on 1VQ4 and 1VQ5, Run shunt cables (#12, P.S.’s to Quads) Work Estimate: 2 weeks; 1 BL, 1 Contractor (Electrician)

  6. Comments: 2. Cleanup: M11 experiment area and above 1A/1B shielding blocks M11 Platform Reroute services & cables; Clear & Remove platform Work Estimate4 weeks; 1 crane operator, 2 riggers, 1 BL Cleanup M11 expt area and above 1A/1B shielding blocks Clear M11 area for temporary storage (activated blocks) or staging area (for 2014 S/D) Clear area above 1A/1B for 2014 S/D (Excavate shielding in MH SouthWest corner) Work Estimate2.8 months (11 weeks); 1 crane operator, 2 riggers, 1 BL Flexible Does not impact UCN 2014 S/D

  7. Comments: 2. Cleanup: M11 experiment area and above 1A/1B shielding blocks (Jan-Sep/2013) Jan.2-Mar.29 M11 Platform Reroute services & cables; Clear & Remove platform Work Estimate4 weeks; 1 crane operator, 2 riggers, 1 BL Apr.2-Aug.30 Cleanup M11 expt area and above 1A/1B shielding blocks Work Estimate2.8 months (5m at 55%); 1 crane operator, 2 riggers, 1 BL (Jan-Sep/2013) Jan.2-Feb.28 M11 Platform Work Estimate4 weeks; 1 crane operator, 2 riggers, 1 BL Mar.1-Aug.30 Cleanup M11 expt area and above 1A/1B shielding blocks Work Estimate12 weeks; 1 crane operator, 2 riggers, 1 BL [ 6 weeks for M11 work, 6 weeks for 1A/1B work ] *Assuming storage space issue solved (Previous draft plan – July-2012) Flexible Does not impact UCN 2014 S/D (New draft plan)

  8. Comments: 3. Dismantle: M13 expt area (PIENU,Q6,Q7) and Infrastructure/Services Cleanup M13 Floor Area PIENU BG/Calib and remove detectors (PIENU personnel) Remove PIENU and clear M13 floor area - (Includes M11-Q6 & Q7, PACman, Quad-Triplet) Work Estimate6 weeks; 1 crane operator, 2 riggers, 1 BL Remove M13 Infrastructure Remove PIENU-M13 cables, cable trays, services Work Estimate 8 weeks; 1 crane operator, 1 rigger, 2 BL, 2 EL Removal of M13 B/L (Q1–B2) requires shutdown (in 2015)

  9. Comments: 3. Dismantle: M13 expt area (PIENU,Q6,Q7) and Infrastructure/Services (Sep-Dec/2013) Finish Sep.15 PIENU BG/Calib and remove detectors (PIENU personnel) Sep.16-Dec.20 Remove PIENU and clear M13 floor area (Includes M11-Q6 & Q7, PACman, Quad-Triplet) Work Estimate6 weeks (3m at 50%); 1 crane operator, 2 riggers, 1 BL (May-Dec/2014) May.1-Aug.1 Remove PIENU-M13 infrastructure & services Work Estimate 8 weeks; 1 crane operator, 1 rigger, 2 BL, 2 EL (Apr-July/2013) Finish Mar.29 PIENU BG/Calib and remove detectors (PIENU personnel) Apr.1-Jun.30 Remove PIENU and clear M13 floor area Work Estimate6 weeks; 1 crane operator, 2 riggers, 1 BL (July-Oct/2013) Jul.1-Sep.30 Remove PIENU-M13 infrastructure & services Work Estimate 8 weeks; 1 crane operator, 1 rigger, 2 BL, 2 EL (Previous draft plan – July-2012) (New draft plan)

  10. ARIEL & Shutdown Plan (2012-2016) - DRAFT Oct. 17, 2012 2012 2013 2015 2016 2014 Major Tasks A J O J A J O J A J O J A J O J A J O Legend: 100Kw e-Beam E-Hall Available Tunnel & Bldg Avail LC (50Kw) e-Beam ARIEL & E-Linac Milestones Shutdown Jobs Construction Non Shutdown Jobs Install & Connect ELBT & EINJ-2 in E-Hall ARIEL & E-Linac Cryogenic Plant (delivery & operational) Test & Commission High Power RF System (Klystron & HVPS) Install EHBT from ACM to Target Hall Install & Connect EACA, Test & Comm Beam in E-Hall (50kW & 100kW) Complete IRIS Complete EMMA Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods 1 Complete M20 Front end & M9A Front end work 2012 / 2013 Cleanup (incl M11 Expt area, above 1A/1B shielding blocks) 2 Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services 3 Install Kicker Ceramic beam Tube & Services July-2013: M11,M13 floor area cleared Install Septum & Dipole (with services, where possible) 2014 Shutdowns Mod Vault Quads (rem. Steerers), 1BVB2, and BL1A/1B Reconfigure Vault-to-1A Shld, and beamline Shld to run 1A Remove & Store M13 Front end, Hot Blocks & Crumbling Blocks Core through M13 Block Install Kicker, UCN Beam line, Services & Controls 2015 Install Base Layer of UCN Shielding to Run BL/1A Install UCN Shielding Install UCN Spallation Target & R/Handling System, & UCN Source 2016 Complete Shielding & Commissioning Tests Dsgn Procure & Inst Procure & Inst Upgrades Hel liquefier system (and UCN upgrade)

  11. ARIEL & Shutdown Plan (2012-2016) - DRAFT Oct. 17, 2012 2012 2013 2015 2016 2014 Major Tasks A J O J A J O J A J O J A J O J A J O Legend: 100Kw e-Beam E-Hall Available Tunnel & Bldg Avail LC (50Kw) e-Beam ARIEL & E-Linac Milestones Shutdown Jobs Construction Non Shutdown Jobs Install & Connect ELBT & EINJ-2 in E-Hall ARIEL & E-Linac Cryogenic Plant (delivery & operational) Test & Commission High Power RF System (Klystron & HVPS) Install EHBT from ACM to Target Hall Install & Connect EACA, Test & Comm Beam in E-Hall (50kW & 100kW) Complete IRIS Complete EMMA Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods 1 Complete M20 Front end & M9A Front end work 2012 / 2013 Cleanup (incl M11 Expt area, above 1A/1B shielding blocks) 2 Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services 3 Install Kicker Ceramic beam Tube & Services Install Septum & Dipole (with services, where possible) 2014 Shutdowns Mod Vault Quads (rem. Steerers), 1BVB2, and BL1A/1B Reconfigure Vault-to-1A Shld, and beamline Shld to run 1A Remove & Store M13 Front end, Hot Blocks & Crumbling Blocks Core through M13 Block Install Kicker, UCN Beam line, Services & Controls 2015 Install Base Layer of UCN Shielding to Run BL/1A Install UCN Shielding Install UCN Spallation Target & R/Handling System, & UCN Source 2016 Complete Shielding & Commissioning Tests Dsgn Procure & Inst Procure & Inst Upgrades Hel liquefier system (and UCN upgrade)

  12. 2013 Meson Hall Cleanup Plan (Durations, not Actual Work – i.e. typically 50% FTE’s or less) Legend: Shutdown Jobs 2013 Non Shutdown Jobs A F M M J A N D J S O J Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods 1 Complete M20 Front end & M9A Front end work 2012 / 2013 Shutdowns Cleanup (incl M11 Expt area, above 1A/1B shielding blocks) 2 Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services 3

  13. 2013 Meson Hall Cleanup Plan ( Durations [dashed] & Actual Work [solid, 100% FTE’s] ) Legend: Legend: Shutdown Jobs Shutdown Jobs 2013 (Reference scenario) Non Shutdown Jobs Non Shutdown Jobs A F M M J A N D J S O J Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods 1 Complete M20 Front end & M9A Front end work 2012 / 2013 Shutdowns Cleanup (incl M11 Expt area, above 1A/1B shielding blocks) 2 Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services 3 July-2013: M11, M13 floor area cleared 2013 (Alternate scenario 1) A F M M J A N D J S O J Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods 1 Complete M20 Front end & M9A Front end work 2012 / 2013 Shutdowns Cleanup (incl M11 Expt area, above 1A/1B shielding blocks) 2 Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services 3 Jun-2013: M11, M13 floor area cleared Tasks appear to divide up into 6-8 week “blocks” **Ideally, would like crew (1 crane op, 2 riggers, 1 BL) for 6 weeks at a time

  14. 2013 Meson Hall Cleanup Plan ( Durations [dashed] & Actual Work [solid, 100% FTE’s] ) Legend: Legend: Shutdown Jobs Shutdown Jobs 2013 (Alternate scenario 2) Non Shutdown Jobs Non Shutdown Jobs A F M M A N D J S J O J Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods 1 Complete M20 Front end & M9A Front end work 2012 / 2013 Shutdowns Cleanup (incl M11 Expt area, above 1A/1B shielding blocks) 2 Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services 3 2013 (Alternate scenario 3) A F M M J A N D J S O J Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods 1 Complete M20 Front end & M9A Front end work 2012 / 2013 Shutdowns Cleanup (incl M11 Expt area, above 1A/1B shielding blocks) 2 Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services 3 Tasks appear to divide up into 6-8 week “blocks” **Ideally, would like crew (1 crane op, 2 riggers, 1 BL) for 6 weeks at a time

  15. 2013 Meson Hall Cleanup Plan ( Durations [dashed] & Actual Work [solid, 100% FTE’s] ) 2013 (Alternate scenario 2) A F M M A N D J S J O J Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods 1 Complete M20 Front end & M9A Front end work 2012 / 2013 Shutdowns Cleanup (incl M11 Expt area, above 1A/1B shielding blocks) 2 Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services 3 He Liquefier Sys: Clean out & Reconfig Mezzan. (crew:0.5 man-mth) He Liquefier Sys: Equip arrival, install (BL:1 man-mth) He Liquefier Sys: Equip arrival, inst. services (BL:0.75 man-mth) 2013 (Alternate scenario 3) A F M M J A N D J S O J Assess: Cleanup of M11, M13, above 1A/1B; BL1B & Vault mods 1 Complete M20 Front end & M9A Front end work 2012 / 2013 Shutdowns Cleanup (incl M11 Expt area, above 1A/1B shielding blocks) 2 Dismantle M13 Expt area (PIENU,Q6,Q7) & Infrastructure/Services 3 He Liquefier Sys: Clean out & Reconfig Mezzan. (crew:0.5 man-mth) He Liquefier Sys: Equip arrival, install (BL:1 man-mth) He Liquefier Sys: Equip arrival, inst. services (BL:0.75 man-mth)

  16. Summary: (Reference Scenario) 1. Vault mods: Cleanup issues; BL1B & Vault mods Jan.2-Mar.29 Rewire Vault Quads for Steering Capability Work Estimate2 weeks; 1 BL, 1 Contractor (Electrician) 2. Cleanup: M11 experiment area and above 1A/1B shielding blocks Jan.2-Feb.28 M11 Platform Work Estimate4 weeks; 1 crane operator, 2 riggers, 1 BL Mar.1-Aug.30 Cleanup M11 expt area and above 1A/1B shielding blocks Work Estimate12 weeks; 1 crane operator, 2 riggers, 1 BL 3. Dismantle: M13 expt area (PIENU,Q6,Q7) and Infrastructure/Services Finish Mar.29 PIENU BG/Calib and remove detectors (PIENU personnel) Apr.1-Jun.30 Remove PIENU and clear M13 floor area Work Estimate6 weeks; 1 crane operator, 2 riggers, 1 BL Jul.1-Sep.30 Remove PIENU-M13 infrastructure & services Work Estimate 8 weeks; 1 crane operator, 1 rigger, 2 BL, 2 EL Person-Week Sums Shutdown & Meson-Hall Cleanup 2013[ Time Estimate in Person-Weeks] 2013 ShutdownM11 Platform (2013 )2013 non-Shutdown BL [2] PG [12] PG [70] Contr [2] BL [4] BL [34] EL [16]

  17. Summary (cont’d): Some flexibility in scheduling of Tasks and Subtasks - For efficiency reasons (D.P.), best to have “full-time” crew for 6 weeks at a time **Cleanup (main issue): Identifying Storage Space of Critical Importance - Find/Build new storage space on-site (?) (any possible storage solutions left on-site?) - Store off-site (?) Determine “ownership” of equipment above 1A/1B - email notice (link to pictures of equipment)

  18. ADDITIONAL SLIDES

  19. Any possible storage solutions left on-site? MH ISAC II ISAC I Cycl Gg RH Construction ARIEL Constr. He Fac PH Hh M.S. MOB A Ff D.O./Stores Plant Grp.

  20. Comments: 4. UCN Installation 1 (Jan-May/2014): BL1U, Vault and Upstream Section After: 1UM6 1UB2 KICKER BEAMTUBE 1VM4 1BVB2 1VVA4 TPUMP 1U Septum 1AUM5 1UBB2

  21. Comments: 4. UCN Installation 1 (Jan-May/2014): BL1U, Vault and Upstream Section

  22. Comments: 4. UCN Installation 1 (Jan-May/2014): BL1U, Vault and Upstream Section Late Dec/2013 Remove large shielding blocks outside (3 days) Start Jan.2/2014 Week 1 RPG survey & prepare for S/D work Week 2 Remove Warm blocks (layers A-D); Disconn.services; Remove 1A vault comp.’s Week 3 Cleanup/Layout BL1U; Specify location for coring of Immovable-block (and tx.) Week 4 - 5 1BVB2 mods (and 1B mods) Week 5 - 7 Install stands for kicker,septum,1UB2; Install & Align kicker-beamtube Week 8 Install & Align septum magnet Week 9 Install & Align 1UB2 magnet and 1UM6 Week 10 Reinstall 1A vault comp.’s; Install Notch-monitor; Install 1AUM5/1UBB2 Week 7 - 9 Install rough-in services (Electrical, Water, Air) Week 10 - 11 Finish Electrical (AC & DC), Water, Air services Week 11 Finish all vacuum connections Week 12 Leak check & ready to pull vacuum Week 13 Pull vacuum & check-out vacuum controls Week 14 General check-out and ready to cover Week 15 - 16 Restore vault & 1A shielding and prepare for beam Resources: 3 Beamlines techs (2 BL + Alignment), 13 weeks [39 person-weeks] 1 Crane Operator + 2 Riggers, 7 weeks [21 person-weeks] Vacuum Group [6 person-weeks] Services: Outside Contractors, 5 weeks [6 person-weeks] Close Up Main Work Open Up Mostly Contractors (?)

  23. Preparations for 2014 Shutdown:(Design, Procurement, Assembly of Subsystems) Items/Subsystems Eng. DWGs Procurement Assy./Testing (needed Jan-2014) (incl Modeling) Vault-BL1A Shielding Saf./ UCN DO UCN n/a Septum Mods UCN UCN MS / UCN BL / UCN Septum Vacuum Box UCN UCN MS / UCN BL / UCN Septum Stand UCN UCN MS / UCN BL / UCN 1UAM5/1UBB2 Diag. DO MS /Diag./ ET ET / Diag. 1BVB2 Stand Mod. Eng.Div. DO MS BL Dipole Vacuum Box UCN UCN MS BL 1AM4(ToF)/1AM4.5 Diag. UCN Diag. / UCN Diag./ UCN Kicker Beamtube UCN UCN UCN BL Kicker Stand UCN UCN MS / UCNBL SEM for BL1B Diag. D.O. Diag. Diag. (M.Trinczek)

  24. Preparations for 2014 Shutdown:[ Time Estimate in Person-Weeks ] Items/Subsystems Eng. DWGs Procurement Assy./Testing (needed Jan-2014) (incl Modeling) Vault-BL1A Shielding Saf.[3]/UCN[4] DO [7] UCN [3] n/a Septum Mods UCN [8] UCN [4] MS [2] / UCN [1] BL [10] / UCN [2] Septum Vacuum Box UCN [3.5] UCN [6] MS [6] / UCN [1] BL [6] / UCN [3] Septum Stand UCN [3.5] UCN [6] MS [5] / UCN [1] BL [4] / UCN [2] 1UAM5/1UBB2 Diag. [8] DO [7] MS[6]/Diag.[2]/ET[4] ET [3] / Diag. [7] 1BVB2 Stand Mod. Eng.Div. [1.5]DO[3]MS[2]BL[2] Dipole Vacuum Box UCN [1] UCN [6] MS [8] BL [1] 1AM4(ToF)/1AM4.5 Diag. [3] UCN [6] Diag. [2] / UCN [5] Diag. [2] / UCN [6] Kicker Beamtube UCN [3.5] UCN [5.5] UCN [3.5] BL [2.5] Kicker Stand UCN [3.5] UCN [6.5] MS [5] / UCN [2.5] BL [4] SEM for BL1B Diag. [2] D.O. [2] Diag. [3] Diag. [3] (M.Trinczek) UCN Designer (need to hire)

  25. Person-Week Sums: Summary [ Time Estimate in Person-Weeks ] Shutdown & Meson-Hall Cleanup 2013 & 2014 2013 S/DM11 Platform (2013 )2013 non-S/D BL [4] PG [12] PG [70] BL [4] BL [34] EL [16] 2014 S/D PG [21] BL [39] Vac [6] Con.[6] Preparations for 2014 S/D (2012,2013) Safety [3] Eng.Div [1.5] DO [19] MS [34] BL [29.5] Diag. [32] ET [7] UCN.Eng [46] UCN.Des [34] UCN.Stu [17]

  26. Preparations for 2014 Shutdown:[ Time Estimate in Person-Weeks ] (Deferral Options - Prioritized) Items/Subsystems Eng. DWGs Procurement Assy./Testing (needed Jan-2014) (incl Modeling) Vault-BL1A Shielding Saf.[3]/UCN[4] DO [7] UCN [3] n/a Septum Mods UCN [8] UCN [4] MS [2] / UCN [1] BL [10] / UCN [2] Septum Vacuum Box UCN [3.5] UCN [6] MS [6] / UCN [1] BL [6] / UCN [3] Septum Stand UCN [3.5] UCN [6] MS [5] / UCN [1] BL [4] / UCN [2] 1UAM5/1UBB2 Diag. [8] DO [7] MS[6]/Diag.[2]/ET[4] ET [3] / Diag. [7] 1BVB2 Stand Mod. Eng.Div. [1.5]DO[3]MS[2]BL[2] Dipole Vacuum Box UCN [1] UCN [6] MS [8] BL [1] 1AM4(ToF)/1AM4.5 Diag. [3] UCN [6] Diag. [2] / UCN [5] Diag. [2] / UCN [6] Kicker Beamtube UCN [3.5] UCN [5.5] UCN [3.5] BL [2.5] Kicker Stand UCN [3.5] UCN [6.5] MS [5] / UCN [2.5] BL [4] SEM for BL1B Diag. [2] D.O. [2] Diag. [3] Diag. [3] (M.Trinczek)