Solar Probe Plus FIELDS Monthly Management Telecom Sep 17, 2012

Solar Probe Plus FIELDS Monthly Management Telecom Sep 17, 2012. MONTHLY MGMT AGENDA. Monthly Report Review Schedule Review Financial Report Review EVM Inputs and Variance Explanations. FIELDS Overview. Observations Measure electric and magnetic fields and waves

neola
Download Presentation

Solar Probe Plus FIELDS Monthly Management Telecom Sep 17, 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Solar Probe Plus FIELDS • Monthly Management Telecom • Sep 17, 2012

  2. MONTHLY MGMT AGENDA • Monthly Report Review • Schedule Review • Financial Report Review • EVM Inputs and Variance Explanations

  3. FIELDS Overview Observations • Measure electric and magnetic fields and waves • Measure poynting flux, absolute plasma density and electron temperature, S/C floating potential and density fluctuations, and radio emissions Measurements • Magnetic field vectors DC-50kHz • Electric field vectors DC-1MHz • Plasma waves 5Hz to 1MHz • Quasi-thermal Noise 10 kHz to 2.5MHz • Radio emissions 1MHz to 16MHz UCB E-Field Antenna GSFC Fluxgate Magnetometer (MAG) LPC2E Search-Coil Magnetometer (SCM) • Project Status Update • Phase B contract signed 7/24/12 • Funding • Definitized Contract Value: $13.7 M • Definitized Funding Value: $ 3.6 M • End Date: 3/14/2013 • Current EAC: $13.7 M • Milestones (Phase B) • FIELDS Specification Dev (L2) Oct, 2012 • MEP Specification Dev (L3)Jan, 2013 • ICU & AEB Detailed Dsn Sep 2013 • HFR/TNR Detailed Dsn Oct 2013 • FPGA Reviews Oct 2013 • IPDR Nov 2013

  4. FIELDS Overview Main Electronics Package includes: • Thermal Noise Receiver / High Frequency Receiver (TNR/HFR) - LESIA • Time Domain Sampler (TDS) - UMinn • Digital Fields Board (DFB) - LASP • Antenna Electronics Board (AEB) – UCB • MAG Electronics (MAG) – GSFC • Instrument Control Unit (ICU) – UCB • Low Noise Power Supply (LNPS) - UMinn E-Field Antennas 2.3 m Tip-to-Hinge Preamps located at Hinge Main Electronics Package (MEP) MagBoom MAG (Inboard) MAG (Outboard) SCM

  5. FIELDs Organization

  6. FIELDs Technical Status • Antenna Technology Development • Basic Concept Complete • Materials Tests in progress @GRC • Niobium C-103 • Tantalum-Tungsten Ta-W • Thermal Modeling • Expected 10/15/12 • Will need Preamp details soon • Thermal Test Model • Design in progress • Fabrication expect by end of year • PROMES tests in Winter 2013 • Deployment Brake • Prototype #1 Complete • Prototype #2 in fab

  7. FIELDS Technical Status • Main Electronics Package Development • Basic Interface Concept with Spacecraft Complete • Internal Electrical Concept Complete • Working on Box Mechanical Specifications • Basic Concept Uses Board Slices (similar to MAVEN) • Board Size Must be Common Among all Boards • FIELDS boards have THEMIS, MAVEN and STEREO heritage • Mass Estimate Used THEMIS-sized Boards (6”x9”) • AEB (THEMIS) no issue • ICU (MAVEN) adding memory but will fit in 6x9” format. • DFB (THEMIS) has to add circuitry and needs smaller A/D’s to fit. The smaller A/Ds need radiation testing (in the works at LASP). • MAG (MAVEN) is requesting a separate slice for heater circuits and more filtering than on MAVEN. Would prefer MAVEN footprint. • Digital Spectrometer would be a single slice, replacing HFR-TNR. There is a group working on these specifications.

  8. FIELDS Schedule • Electric Field Antennae Schedule • Materials • Materials testing at GRC has shown mass increases in the samples • Concern that oxidation will change optical properties, we have repeated tests with “O2 getters” These did not solve the problem. • Added a second candidate material Ta-W to test • Thermal Test Model (at PROMES) • Thermal modeling showed initial concept of TTM would not fully demonstrate the design. Revised TMM design in progress, fabrication by year end. • Next PROMES opportunity is Winter 2013 (not Sept 2012)

  9. FIELDS Schedule • Main Electronics Package Schedule • Very high-level schedule of MEP effort currently in master schedule • Details to be linked in as the detailed specification is finished (i.e. Will the board size, shape, connectors change, etc?) • ICU design will have priority as other board designers will need “ICU simulators” for their test apparatus. • ICU test will require S/C simulator (GSEOS) as in RBSP. • FIELDs ICD will be needed for S/C simulator. • (LNPS, TDS, and DFB have nearly the same schedules at this point.)

  10. FIELDS Schedule • MAG Schedule • Supported MAG-SCM tests • Final report just delivered last week • GSFC has demonstrated 256 samples/sec operation • Designed non-magnetic TV chamber for sensor life tests • Considering materials changes in sensor

  11. FIELDS Schedule • SCM Schedule • Supported MAG-SCM compatibility tests • Built / Tested dual gain model with acceptable results for SPP • Developed SCM specification

  12. FIELDS Risk Summary F14 - Phase B Schedule Risk has been retired. This risk turned into reality as the APL-to-UCB contract took until the end of the funded period and UCB watched all its subcontracts fall out of contract. According to our Sponsored Projects Office, No-Cost-Extensions were offered to all subcontractors. We expect to get back on schedule in the coming period. F3 - Foreign Funding (commitment): Continuing as our top risk, we are expecting to hear more next month from our French colleagues about possible technical working arrangements for a joint project.

  13. FIELDS Cost

  14. Subcontracts All Subcontracts are currently on No-Cost Extensions APL-UCB contract modifications have historically occurred too late for UCB to keep subcontractors continuously funded.

  15. FIELDS Issues & Concerns • Technical • HFR/TNR funding issues. Replacement with UCB-Digital Receiver • Continuing EMC program (needed for final specification) • Vector Electric Field Fidelity (with S/C Electrostatics) • Cost • No Issues • Schedule • Fall 2012 Manpower issues. RBSP launch, CINEMA launch, FOXSI launch and MAVEN delivery has depleted engineering and management resources.