Solar Probe Plus FIELDS Team Meeting Peter R. Harvey Dec 1, 2012
FIELDS REWORK FIELDS Schedule Rework Project 2010 was Crashing on Fields.mpp Linked to Wrong Sub-schedules Linked to random Tasks in Sub-schedules Unrecognizable Tasks e.g. “Update thermal model” Listing All Docs as due “2/1/2012” Need Real Dates and Real interactions with APL Milestones Needed Work • Mixture of SPP & random FIELDS tasks • Allowing Project 2010 to change instrument review dates Sub-schedules were insufficiently detailed Some still adjusting to changes in Mission schedule Want to be able to use PERT format Need to resource load Excerpt from Oct 5 schedule. Grey lines linked to other schedules in odd places.
SCHEDULE ORG FIELDS Schedule Organization Each schedule is maintained by a team member who provides direct and timely communication with the team. Revises the schedule as needed.
SCHEDULE ORG FIELDS Schedule Organization Progress and changes are reported to UCB by a member of that team with intimate knowledge of the application area.
EXAMPLE FIELDS Schedule Example (Orange In, Blue Out)
Phase B Schedule iPDR 11/19 ETU I&T NB: iCDR is 1/19/2015, 2 months after ETU I&T is completed.
WHAT’s NEXT? Schedule Ahead • MAVEN has delivered. Should be able to pick up the pace on FIELDS • Dec 5 Schedule to APL will get Feedback on our Milestones • December Schedule telecoms (mid-month one-on-one) • Additional Milestones (if APL requests) • Add Peer Reviews • Add Software/ FPGA Reviews if applicable • Add Slack before all Milestones • Revised Preamp Delivery Dates • Revised GSE Delivery Dates (mini-emulator) • Discuss GSE needs. Are teams planning to use the UCB-delivered GSE?