Engineering Operations

Engineering Operations. FY09 Operations: To date, NSTX has completed 10.48 run weeks, with 1698 plasma attempts resulting in 1611 completions. Scheduled to complete the run by Aug 14th at a target 16 run weeks. Last NSTX maintenance period of the run is drawing to a close

nessa
Download Presentation

Engineering Operations

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Engineering Operations • FY09 Operations: • To date, NSTX has completed 10.48 run weeks, with 1698 plasma attempts resulting in 1611 completions. • Scheduled to complete the run by Aug 14th at a target 16 run weeks. • Last NSTX maintenance period of the run is drawing to a close • - Replaced the NB Calorimeter Bellows • - Refilled both LITER probes • - Re-shimmed and tightened error field coil brackets • - Installed lithium droppers (shakers) at Bays I & C • HHFW Antenna and NB Ion Source conditioning will continue for the remainder of this week. Plasma Ops to resume on July 6th. • Error Field Coil testing this week will include the commissioning of PFAB coil protection in the SPA controls.

  2. Engineering Operations • FY09 Outage/ FY10 Ops Planning: • Plan on an abbreviated outage to install and commission the Liquid Lithium Divertor system and the new BES diagnostic, as well as whatever progress can be made on the MSE/LIF diagnostic. • Seven weeks of in-vessel work is planned (Oct 9th - Nov 24th). • 3 weeks of post run & ~ 4 weeks of post outage calibrations planned. • In-vessel tiles will be cleaned (sanded) before Oct 9th • LLD & BES tasks scheduled 2 shifts/day during opening • - Pump-down scheduled for Jan 6th • - ISTP scheduled to start on Feb 24th • - Planning on 17 run weeks in FY10 • Significant Elevated Water Tower riser repairs, and a PSE&G replacement of 138kV lines are needed before the start of the FY10 run.