An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DuPage ETSB Emergency Dispatch Interoperability Radio Project Presented to ETSB Radio Steering Committee January 27, 2011

  2. Overview • Starting New Project Phase – Beginning Implementation Phase of Project; (Majority of) work has been defined, budgets established, and schedules set • Complexity Requires Oversight, Coordination – Multiple, interconnected sub-projects • Finite Timeframe – Timeframe is constrained by regulation, seasons, ETSB objectives • Actions Necessary – Remaining planning and decision making must be made promptly

  3. Major Work Elements

  4. Radio Network Infrastructure (STARCOM21) • SCOPE: • STARCOM21 system enhancements to provide 95% Coverage, 12dB In-Building Penetration, 2% Grade-of-Service • DuPage cell comprises eight sites (including Wheaton OEM & Streamwood) • Work performed by Motorola and the STARCOM21 team – No direct ETSB involvement • TIMELINE: Underway – October 2011 • COST: “Impact Fee”, $5.4 MM • PRIORITIES, RISKS & OTHER CONSIDERATIONS: • Coverage testing during periods of full foliage • Wheaton OEM and Streamwood sites are essential, but have not yet been contracted

  5. Wheaton OEM & Streamwood Sites • SCOPE: Development of two existing RF sites for addition to STARCOM21 network • TIMELINE: Underway – August 2011 • COST: Budgetary Numbers Not Yet Finalized • PRIORITIES, RISKS & OTHER CONSIDERATIONS: • ETSB to share cost of development of Streamwood with NWCD • ETSB to coordinate site use negotiations between Motorola and DuPage County • DuPage County requirements have not been resolved • Sites are essential to meeting coverage and penetration requirements • Lengthy construction durations

  6. Subscriber Units • SCOPE: Multiple orders, shipments, distributions, training • TIMELINE: Underway – March 2012 • COST: $21.8 MM • PRIORITIES, RISKS & OTHER CONSIDERATIONS: • Talk-group template development is a priority • Subscriber deployment strategy includes multiple shipments of subscriber units completed EOY 2011

  7. ETSB Network Reconfiguration • SCOPE: Effort includes an assessment of the existing SONET data network, the determination of the requirements for future use by ETSB, integration with STARCOM21, and other county entities. • State-of-the-art technologies will be considered. • TIMELINE: Stalled • COST: TBD • PRIORITIES, RISKS & OTHER CONSIDERATIONS: • Services and service provider are being re-evaluated. • PSAP connections to STARCOM21 master site constrained by STARCOM21 system requirements

  8. PSAP Consolidation • SCOPE: TBD • TIMELINE: TBD • COST: TBD • PRIORITIES, RISKS & OTHER CONSIDERATIONS: • Known Consolidations • Westmont/Downers Grove   May 1 • Woodridge, Lisle, Darien, Darien/Woodridge FPD to DU-COMM  May 1 • Need to finalize balance of PSAP site locations

  9. Consoles & Recorders • SCOPE: New consoles, control stations and recorders at multiple PSAPs • TIMELINE: Underway – December 2011 • COST: $6.2 MM • PRIORITIES, RISKS & OTHER CONSIDERATIONS: • Some uncertainty regarding final PSAP count and configuration • Staging and cutover will be especially challenging for DU-COMM due to scale of operation and space constraints • Space preparation is the responsibility of the PSAP agency • Requires decisions on Talk Groups and Conventional Resources

  10. Countywide Fire Paging Solution • SCOPE: • Narrow-banding of existing VHF paging & toning system • Patch to STARCOM21 system • TIMELINE: Goal is to coincide with overall project • COST: $1.5 MM • PRIORITIES, RISKS & OTHER CONSIDERATIONS: • Reimbursement program – Eligible agencies are responsible for implementing their solutions • Hardware and software patching solutions – Need to select which solution to implement • Funding available now, affected agencies should begin implementation immediately upon execution of IGA

  11. Proposed Radio Steering Committee Assignments • Talk-group template development – Requesting initial Recommendations w/in 30 Days • Conventional resource prioritization and STARCOM21 port allocation • Policies (as identified) • Fire paging implementation • Training