1 / 6

Human Services Department Video Conference Augmentation Project

Human Services Department Video Conference Augmentation Project. Project Closeout Presentation, August 27, 2014. Presenters: William Russell, HSD IT Project Manager Mario Gonzalez, HSD ITD Project Management Bureau Chief

Download Presentation

Human Services Department Video Conference Augmentation Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Human Services DepartmentVideo Conference Augmentation Project Project Closeout Presentation, August 27, 2014 Presenters: William Russell, HSD IT Project Manager Mario Gonzalez, HSD ITD Project Management Bureau Chief Steven Chavez, HSD ISD Bureau Chief, Program Administrative Services

  2. Project Overview • The purpose of this project was to augment and expand the current HSD video conference network by 22 more offices. • The benefit will be automation of the current manual scheduling function, reduced travel cost and travel time to attend meetings, and improved communication between field staff. • The expanded equipment was successfully installed, tested and is now in production.

  3. Project Delays / Lessons Learned • The project took far too long to complete. • Delays commonly tie back to state resource availability and scheduling commitments. • Internal resource forecasts need improvements and should receive proper review up front. • Staff turnover through the end of 2013 encompassed the entire technical team including the bureau chief.

  4. Project Timeline

  5. Appropriation & Certification History Note: All certified funds were used for hardware procurement