1 / 13

Learning from incidents

Learning from incidents. Glasgow Caledonian University. 10 December 2013. Neal Stone Director of Policy & Communications British Safety Council. Three ODA award winners 2010 and lessons learnt . PROJECTS Company A: International Broadcast Centre/ Main Press Centre

norris
Download Presentation

Learning from incidents

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Learning from incidents Glasgow Caledonian University 10 December 2013 Neal Stone Director of Policy & Communications British Safety Council

  2. Three ODA award winners 2010 and lessons learnt PROJECTS Company A: International Broadcast Centre/ Main Press Centre Company B: Sewerage system Company C: New utilities

  3. Whilst erecting the steel Beams and Columns aslinger fitted the piling clamp to a 10 meter length column. The piling clamp is a propriety lifting attachment and is regularly used to lift the columns. The slinger failed to ensure the pin had secured properly through the hole in the web. As the cranes head was directly above the lifting point the piling clamp would grip until the angle of the column altered enough for the piling clamp to slide free. This then left the piling clamp suspended on the chain and the column falling to the ground. Fortunately, an exclusion zone was in place and nobody was injured. Company A: International Broadcast Centre/ Main Press Centre The Background Company A: International Broadcast Centre/ Main Press Centre

  4. The piling clamp Company A: International Broadcast Centre/ Main Press Centre The Real Picture Poorly positioned clamp Dawson clamp Company A: International Broadcast Centre/ Main Press Centre

  5. Company A: International Broadcast Centre/ Main Press Centre Lessons learnt • Slingers need to ensure that they double check that all lifting equipment is attached correctly before signalling the crane driver to begin lifting. • The design of the piling clamp means that you rely on the operator to ensure the clamp engages in the hole using the spring release. Dawson clamps should be used instead of piling clamps to lift the columns because there is less of a risk of an operational error due to the fact the operator must physically install the pin through the hole before signalling the crane driver to begin lifting. • The resulting investigation and near miss report was shared across the Park. Company A: International Broadcast Centre/ Main Press Centre

  6. On 1 April 2009, an employee suffered multiple fractures and a cracked heel to the left foot when a concrete shaft segment (approx. 700 kg) toppled and fell onto his foot. In recent years as developments of concrete shaft segment has progressed, the segments have become thinner and taller, making them less stable when stored upright in their correct position. The standard industry practice was to tie the segments in a stack which was adequate when the segments were not being used. The problem arose when a segment was required to be removed from the end of the stack for use in the construction. When the ties were released, the end segment became unstable. Company B: Sewerage system The Background Company B: Sewerage system

  7. Toppled concrete Company B: Sewerage system The Real Picture Segment into frame Multiple shaft segments into frame Company B: Sewerage system

  8. Company B: Sewerage system Lessons learnt • Key Learning Opportunities • Sectional ownership reviewed providing slinger signallers storage responsibilities • All existing segment storage sites checked to ensure safe storage i.e. provision of segment restraints. • New 'L' bracket and segment buffers designed as permanent preventative solution. • 4 Stage safe segment storage working practice document to be introduced and implemented as a mandatory requirement. • New Measures • Segment buffers available • New guidance sheets available on safe use of segment buffers. • Ownership is being rolled out to all supervisors/site agents. • System used across the business Company B: Sewerage system

  9. Company C: New utilitiesThe Background • Company C was required to install over 50 salmor pits for the 11kv (LVU) installation works. To install them the ground has to be excavated to the correct depth and wide enough to accept the pit. • During the initial installation works, the teams reported that the standard industry practice for access and egress was plainly not best practice. i.e. two ladders tied and criss-crossed, one on the inside and one on the outside of the pit. The operative had to access the actual excavation via a ladder, then climb another ladder on the outside of the pit, then cross over and descend into the pit via another ladder on the inside of the pit. • The reason the access arrangements were like this was that the excavation when constructed was supported by battering the sides to an angle of 45°. Therefore the edge of the excavation was always approximately 1 - 1.5 metres away from the edge of the salmor pit. Company C: New utilities

  10. Best practice winners 2010 Company C: New utilities The Real Picture Access platform The pit Company C: New utilities

  11. Company C: New utilitiesLessons learnt • Something that would span the gap between the excavation and the salmor pit was required. It would have to be a least 2 metres in length, have handrails, wide enough to access a ladder safely to enter the pit, light weight (two man lift maximum) and robust with stop ends. A quick prototype was developed and the solution was found to be ideal for the task in hand. • The access platform eliminated two ladders. Handrails provided security when accessing the pit over the excavation. The risk of falling into the pit during access was eliminated. The standards of the ladder accessing the pit were secured to the platform providing more security for the person. The platform could not slip even if the platform had to be placed at angles to access the pit. Company C: New utilities

  12. Company C: New utilitiesLessons learnt “What was particularly pleasing about this innovation was that it did not require a committee to decide to do it; but from a ground/workface demand the team felt empowered to go and make it happen.” Project Director (Company C) Company C: New utilities

  13. Thank you Neal Stone Director of Policy & Communications British Safety Council

More Related