Status start-up planning

Status start-up planning. 10/02 – 28/03 —> Access system tests for individual zones with help form CCC + Linac2 HW commissioning start . —> 1 person 2 shifts start 07:00 end 20:00 with overlap, no weekends 10/03 – 14/03—> 1st global access system tests with help from CCC

norris
Download Presentation

Status start-up planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status start-up planning • 10/02 – 28/03—> Access system tests for individual zones with help form CCC + Linac2 HW commissioning start. • —> 1 person 2 shifts start 07:00 end 20:00 with overlap, no weekends • 10/03 – 14/03—> 1st global access system tests with help from CCC • 2 persons 2 shifts start 07:00 end 20:00 with overlap, no weekends • 27/03 —> Decondamnation power supplies • 31/03 – 02/05—> PSB and Ps HW test period. 4 weeks for Multipoles + 1 week for the rest • —> 2 persons 2 shifts start 07:00 end 20:00 with overlap, no weekends • 05/05 – 21/05—> Start cold check-out PSB • —> Morning: 3 persons ,Afternoon: 3 persons, Nights: 2 persons • 21/05 onwards —> beam from LINAC2 in PS zone, continuation of PSB cold check out • —> full shifts (3 persons ,Afternoon: 3 persons, Nights: 3 persons). • 30/05—> Booster setup with beam. • 19/06 Beam to PS. • 10/08 Beam to Isolde.

  2. Status start-up planning • What is new in the PSB? • New Fesa Class for the power supplies (218). • All the TG8 have been replaced by CTRV. 400 timings to commission. • We keep old Repetitor and the TSM are removed. • New OASIS crate, scope and multiplexer. Xxx signals to commission • new BSM and new Tomoscope based on OASIS. • New Fesa class to control cavities, • New Amplifyer for Transverse Feedback + new Fesa class. • New RF beam control. • New Booster dump. • BTM has been completely disassembled and reassembled. Polarity test? • BIC extraction to replace the old interlock system for B.HZ10 and BHZ301. • Instrumentation: • New Injection Pick-up, BCT • New Fesa Class inj Pick-up, Inj BCT, Ring BCT, New Interlock comparator • BLM • Orbit, tune measurement. • INCA modifications. • …..

  3. Status start-up planning • Hardware Test (5 weeks only for specialists) • Commissioning Multipoles • New FGC3 • Polarity measurements. • Commissioning WIC (Warm magnet Interlock Controllers). • Control Dry Run with EPC only control The power supplies will be off. • Control Dry Run with others services (RF, ABP, BI,…) not yet defined.

  4. Status start-up planning • Cold Check-out • We have from 5th May to 30th May (3½weeks)to commission: • 218 Power supplies • 389 Timings • RF • Kickers • Oasis Signals 700 Signals. • MPS • BIC • SIS • Instrumentations • … • Procedures and planning aremandatory.

  5. Status start-up planning • Booster setup with beam to confirm with specialist • From 30th May to 19th June, we have 3 weeks to send beam to the PS. • During the ascension week-end we will try to inject low intensity in the booster ( ring 3) with the new pick-ups. BI specialist should have commissioned the pick-up the week before (21/05). • From 2nd June, RF specialists will work on the NEW RF beam control. • Once the beam is accelerated, we can do the setting-up of the extraction. BTM has been completely disassembled and reassembled • Prepare the beam for the PS. ( to discuss with them). • High intensities (Isolde)