1 / 21

Case for Cambodia

Case for Cambodia. Team 6. Aaron Goodman. Lisa Andela. Eric Immerfall. Elizabeth Smit. Jordan Johnston. Presentation Outline. Master Plan Layout Design Norms Designs Budget Challenges Lessons Learned Questions. Master Plan Layout. Common Building Sanitary Facilities. Bridge.

nova
Download Presentation

Case for Cambodia

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Case for Cambodia Team 6 Aaron Goodman Lisa Andela Eric Immerfall Elizabeth Smit Jordan Johnston

  2. Presentation Outline Master Plan Layout Design Norms Designs Budget Challenges Lessons Learned Questions

  3. Master Plan Layout • Common Building • Sanitary Facilities • Bridge • Fish Ponds • Drip Irrigation • Well • Solar Pump Design Norms - Layout - Designs - Budget - Implementation - Challenges - Questions

  4. Design Norms • Cultural Appropriateness: • Through the design, materials, and construction methods of the common Cambodian. • Transparency: • Communication about the simplicity and reliability of the design. • Integrity: • Design will facilitate relationships between people and their land. Design Norms - Layout - Designs - Budget - Implementation - Challenges - Questions

  5. Building Layout • 1stFloor- • Classroom, • Kitchen, • 3 full bathrooms • open space Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions • 2nd Floor- • 11 dorm rooms • Tile roof • Steel Roof Framing • Concrete • Wood/Stucco

  6. Roof Design Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions • Clay Tiles • Local tiles used • Size no smaller than 0.369m long • Steel Framing • Steel angles 3”x3” spaced at 0.369m O.C. • Support Beams • W8x10 • Spaced at 3m O.C • Support Truss • WT4x5 used as outer shape • L30305 is used as bracing

  7. Structure Design Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions • 2nd Floor Columns • W8x24 in center at end of building • W10x12 at each corner of building • Concrete Design • Second floor slab, beams, columns, floor, foundations • Designed as modular system • 3 different modules • 3x3m, 3x4m, 3x6m • Reinforcement steel designed

  8. First Floor Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions • First Floor Includes: • Kitchen • Enclosed in concrete block (along with classroom and restrooms • Classroom • Large space for classes, meetings, worship, etc. • Potential for computer lab • Restroom facilities • Each include toilet, sink, and shower • Storage room • Battery bank storage • Stairway • Wrap design • Foundations • Wall foundations and column footings • Short perimeter wall • Keeps rain out

  9. Renewable Energy Source • Sizing of the components based on 6kWh demand • System Autonomy 3 days • Average solar irradiation 4.96 kWh/m²/d • Require 12 Sharp 175 w Panels • Battery Bank 12 x 2 volt batteries in series • Require Total Capacity of 1500 Ah • Inverter sized with all appliances running • Continuous output power should be approximately 1600 W at 25°C http://cambodia.picosol.nl Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  10. Renewable Energy Source – System Configuration Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  11. Water Distribution & Irrigation • Water Needs from Well: • Existing common building: 564L/day • New common building: 1692L/day • Soursop Tree: ~8L/day • System Components • Irrigation for vegetable garden (IDEal Drip Kits) • Solar pumps to meet demands PS600 BADU www.lorentz.de www.lorentz.de PS 600 HR/C http://www.ideorg.org Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  12. Sanitary Facility – Bathroom Layout System Plan • Three Bathrooms • Sink, Toilet, and Shower in Each • Water Demand: 1692 Liters per Day • Septic System for Waste Removal • 2 Septic Tanks in Series • 1st Tank: 5678 Liters with Baffle • 2nd Tank: 5678 Liters • Drain Field • Approximately 950 sq ft in size Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  13. Sanitary Facility Septic System Design Specs • 2 Septic Tanks in Series • Extra Storage • Sludge Movement Prevention • Schedule 40 Piping • Minimum Slope is 0.635 cm per 30.48 cm • 88 sq meter drainage field • Level • Perforated 10 cm Piping • Baffle System Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  14. Sanitary Facility- Septic System Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  15. Sanitary Facility – Septic System Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  16. Bridge Design - Culverts Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions The first model made was the stream as it is now The second model was made with the dam being assumed as part of the ground and with the sides of the stream being excavated to provide room for the structure From there culverts were inserted to find out how many were needed to convey the worst case flow.

  17. Bridge Design – Final Design Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  18. Budget Design Norms - Layout - Designs -Budget- Implementation - Challenges - Questions • Projected costs were based on • Cost of materials • Cambodian price if known, otherwise price in the US • Does not include cost of labor

  19. Challenges in Design • Assumptions about site data • Finding local vendors and prices for system components • Different design codes and styles between countries • Culturally appropriate design choices Design Norms - Layout - Designs - Budget - Implementation -Challenges- Questions

  20. Lessons Learned Keep units straight -metric Document everything Things change- be able to adapt We don’t know everything-make assumptions Getting started is half the battle- where to start Learned a lot about different aspects of site development Communication is key between group members Design Norms - Layout - Designs - Budget - Implementation -Challenges- Questions

  21. THANK YOU Design Norms - Layout - Designs - Budget - Implementation - Challenges -Questions • Special Thanks To: • Prof DeRooy-Team Advisor • Prof Dornbos-Biology Prof • Rachel Koopman-Interim Data Coordinator • Interim Group • Roger Lamer-Industrial Consultant • Navy Chann-Chhay & Li Chhay-Client • Founders of Eden School of Agriculture • CEAC

More Related