1 / 41

Case for Cambodia

Case for Cambodia. Team 6. Aaron Goodman. Lisa Andela. Eric Immerfall. Elizabeth Smit. Jordan Johnston. Presentation Outline. Design Norms Master Plan Layout Designs Budget Implementation Challenges Lessons Learned Questions. Design Norms. Cultural Appropriateness:

havyn
Download Presentation

Case for Cambodia

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Case for Cambodia Team 6 Aaron Goodman Lisa Andela Eric Immerfall Elizabeth Smit Jordan Johnston

  2. Presentation Outline • Design Norms • Master Plan Layout • Designs • Budget • Implementation • Challenges • Lessons Learned • Questions

  3. Design Norms • Cultural Appropriateness: • Through the design, materials, and construction methods of the common Cambodian. • Transparency: • Communication about the simplicity and reliability of the design. • Integrity: • Design will facilitate relationships between people and their land. Design Norms - Layout - Designs - Budget - Implementation - Challenges - Questions

  4. Master Plan Layout • Common Building • Sanitary Facilities • Bridge • Fish Ponds • Drip Irrigation • Well • Solar Pump Design Norms - Layout - Designs - Budget - Implementation - Challenges - Questions

  5. Common Building • Purpose: • Meeting space • Housing for ~30 people • Eating/cooking space • Design Requirements • Built in the Cambodian • architectural style • Use local easily obtained materials • Low cost • Long design life Examples of similar existing structures Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  6. Layout • 1stFloor- • Classroom, • Kitchen, • 3 full bathrooms • open space • 2nd Floor- • 11 dorm rooms • Tile roof • Steel Frame • Concrete block • Wood/Stucco Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  7. Roof Design • Clay Tiles • Local tiles used • Size no smaller than 0.369m long • Steel Framing • Steel angles 3”x3” spaced at 0.369m O.C. • Support Beams • W8x10 • Spaced at 3m O.C • Support Truss • WT4x5 used as outer shape • L30305 is used as bracing Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  8. Second Floor Design • 2nd Floor Columns • W8x24 in center at end of building • W10x12 at each corner of building • Steel beam design • W8x10- Floor framing over 3m spans (also along stairway) • W10x12- Girder spanning 4 or 5 m • W12x19- Girder spanning 6m to allow large open space Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  9. First Floor Design • First Floor Includes: • Kitchen • Enclosed in concrete block (along with classroom and restrooms • Classroom • Large space for classes, meetings, worship, etc. • Potential for computer lab • Restroom facilities • Each include toilet, sink, and shower • Storage room • Battery bank storage • Stairway • Wrap design • Foundations • Wall foundations and column footings • Short perimeter wall • Keeps rain out Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  10. Sanitary Facility Method Selection • Provide Increased Sanitation • Alternatives • Waste Removal • Current Method is Ineffective • New Method: • Safe • Effective • Efficient • Proven • Provide a Better Future Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  11. Sanitary Facility System Plan • Three Bathrooms • Sink, Toilet, and Shower in Each • Water Demand: 1692 Liters per Day • Septic System for Waste Removal • 2 Septic Tanks in Series • 1st Tank: 1500 gallons with Baffle • 2nd Tank: 1500 gallons • Drain Field • Approximately 950 sq ft in size Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  12. Sanitary Facility Water Demand Assumptions • Maximum population in dorms = 30 people • 15 Showers per day at 1.5 gallons per minute • 3 Toilet uses per person per day at 2 gallons per flush • 90 Bathroom uses per day at 0.3 gallons per hand wash • 15 gallons used per day for Kitchen sink use • Total Daily Water Demand = 1692 Liters per Day Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  13. Sanitary Facility Bathroom Layout Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  14. Sanitary Facility Bathroom Specifications • A standard toilet, sink, and shower head will be used • Standard piping with two outflows from three bathrooms • Outflow will connect with the kitchen waste en route to the septic tanks • Standard spacing for the shower at 0.8 meters wide and 1.4 meters long • Toilet and Sink will fit any standard model Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  15. Sanitary Facility Septic System Design Specs • 2 Septic Tanks in Series • Extra Storage • Sludge Movement Prevention • Schedule 40 Piping • Minimum Slope is 0.25 in per 1 foot • 950 sq foot drainage field • Level • Perforated 4” Piping • Baffle System Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  16. Sanitary Facility Waste Removal (Plane View) Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  17. Sanitary Facility Waste Removal (Bird’s Eye) Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  18. Sanitary Facility Drainage Field • Depth Varies on Soil Type • Level of Drain Field • 6 inches of supporting bed of stone washed gravel • 4 inch thin walled perforated piping • 2 inches of covering stone washed gravel bed • Back filled to whatever distance required • Sloped Cover Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  19. Sanitary Facility Drain Field (Plane View) Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  20. Sanitary Facility Drain Field (Bird’s Eye) Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  21. Bridge Design – Stream Modeling • Modeled stream in HEC-RAS and HY – 8 • 3 Different Models were made in HEC-RAS • The first model made was the stream as it is now Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  22. Bride Design – Stream Modeling Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  23. Bridge Design - Culverts • The second model was made with the dam being assumed as part of the ground and with the sides of the stream being excavated to provide room for the structure • From there culverts were inserted to find out how many were needed to convey the worst case flow. Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  24. Bridge Design - Culverts Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  25. Bridge Design - Culverts • The third model was made to with the dam being assumed as part of the ground but this time the culverts were put at a downward slope. Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  26. Bridge Design – Dam Section • The Dam that was chosen is an Earthen Dam. • The Dam was decided to be 1m tall and 10.5m wide with a length of 10m at the base Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  27. Bridge Design - • There are four different protection measures that must be implemented • Side Bank • Underflow • Bridge/Dam Frontal • Seepage Rock Toe Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  28. Bridge Design - Roadway • The Roadway over the bridge can be one of two designs • Concrete (proposed) • Gravel (alternative) Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  29. Bridge Design – Final Design Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  30. Bridge Design - Installation • Excavation should start at the beginning of the dry season • Materials should be brought in during excavation • Dam must be built carefully Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  31. Renewable Energy Source • Sizing of the components based on 6kWh demand • System Autonomy 3 days • Average solar irradiation 4.96 kWh/m²/d • Require 12 Sharp 175 w Panels • Battery Bank 12 x 2 volt batteries in series • Require Total Capacity of 1500 Ah • Inverter sized with all appliances running • Continuous output power should be approximately 1600 W at 25°C http://cambodia.picosol.nl Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  32. Renewable Energy Source – System Configuration Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  33. Renewable Energy Source – Solar Pumps • Two types of solar pump systems • Main pump-Lorentz PS600 HR/C • Meets daily flow demands and provides 30 m lift • Fish Pond Pumping System-Lorentz PS600 BADU • Low head levels with high volume capacity www.lorentz.de/ PS600 BADU PS 600 HR/C Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  34. Renewable Energy Source – Design Costs • Price Per kWh: $1.07 Annuity Based on a 6% growth rate and end of year payments Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  35. Water Distribution & Irrigation Well, Pump, & Tank Rice Plots New Piping • Water Needs from Well: • Existing Common Building: 564L/day • New Common Building: 1629L/day • Soursop Tree: ~8L/day • Water distribution system modeled in EPANET to confirm that 3000L tank will supply water demands • Using Lorentz PS600 to refill tank throughout the day Fishponds & Garden Existing Piping Rows of Soursop Trees Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  36. IDEal Drip Irrigation Systems • IDEal Drip Kits • International Development Enterprises • A local non-profit • Offer all sized drip irrigation kits (20m2-1000m2) • Pump: • Lorentz PS600BADU to pump water from fishponds to tank http://www.ideorg.org/OurTechnologies/IDEal_Drip_Technical_Manual.pdf • Drip Irrigation System Layout for • Garden • Research plots Design Norms - Layout - Designs- Budget - Implementation - Challenges - Questions

  37. Budget • Projected costs were based on • Cost of materials • Cambodian price if known, otherwise price in the US • Does not include cost of labor Design Norms - Layout - Designs -Budget- Implementation - Challenges - Questions

  38. Implementation Design Norms - Layout - Designs - Budget -Implementation - Challenges - Questions

  39. Challenges in Design • Obstacles Have Overcome • Assumptions about site data • Finding local vendors and prices for system components • Different design codes and styles between countries • Culturally appropriate design choices Design Norms - Layout - Designs - Budget - Implementation -Challenges- Questions

  40. Lessons Learned • Keep units straight -metric • Document everything • Things change- be able to adapt • We don’t know everything-make assumptions • Getting started is half the battle- where to start • Learned a lot about different aspects of site development • Communication is key between group members Design Norms - Layout - Designs - Budget - Implementation -Challenges- Questions

  41. Questions? Further questions…email us!….caseforcambodia@gmail.com • Special Thanks To: • Prof DeRooy-Team Advisor • Prof Dornbos-Biology Prof • Rachel Koopman-Interim Data Coordinator • Interim Group • Roger Lamer-Industrial Consultant • Navy Chann-Chhay & Li Chhay-Client • Founders of Eden School of Agriculture • CEAC Design Norms - Layout - Designs - Budget - Implementation - Challenges -Questions

More Related