Engineering & Construction Management Department. March Report , 2011. Neighborhood Traffic Program Phase II. General Project Description: Conversion of Monroe and Van Buren to two-way streets and design of traffic calming measures for Trowbridge between US 54 and Howze. PROJECT SCHEDULE.
E N D
Engineering & Construction Management Department March Report, 2011 Neighborhood Traffic Program Phase II General Project Description: Conversion of Monroe and Van Buren to two-way streets and design of traffic calming measures for Trowbridge between US 54 and Howze PROJECT SCHEDULE Design Status: Review of Pre-final Design Plans Pending Issues: No approved funds for construction Overall Project Budget (includes approved project development and design only) $500,000 Funding Source(s): CIP Project Contact Project Manager: Margaret Schroeder 541-4200 Design Consultant: Quantum Engineering Page 1 of 1