Engineering & Construction Management Department. August Report , 2012. EPIA Taxiway L Reconstruction. General Project Description : R econstruct Taxiway L in its entirety (8,200 LF) as well as the taxiway radius geometries to be in accordance with FAA standards. Taxiway L.
E N D
Engineering & Construction Management Department AugustReport, 2012 EPIA Taxiway L Reconstruction General Project Description: Reconstruct Taxiway L in its entirety (8,200 LF) as well as the taxiway radius geometries to be in accordance with FAA standards. Taxiway L PROJECT SCHEDULE Design Status: The design is complete. Pending Issues: None at this time Overall Project Budget (includes approved project development, design and construction costs): $15,434,000.00 Funding Source(s): Passenger Facility Charge Project Contact Project Manager: Victoria Ruiz 541-4357 Design Consultant: Parkhill, Smith & Cooper Page 1 of 1