150 likes | 355 Views
Joint Implementation and industrial energy efficiency Alchevsk Steel Mill Modernization. Grzegorz Peszko Senior Environmental Economist Sustainable Development Department, Europe and Central Asia The World Bank. Steel sector background.
E N D
Joint Implementation and industrial energy efficiencyAlchevsk Steel Mill Modernization Grzegorz Peszko Senior Environmental Economist Sustainable Development Department, Europe and Central Asia The World Bank
Steel sector background • Ukraine’s steel sector very competitive due to rich and cheap iron ore and coke. • Steel products account for 36% of Ukrainian exports and 25% of industrial production. • Ukraine 7th largest steel producer in the world and 3rd largest exporter after Japan and Russia. • Export = 74% of output in 2004. • Historically high steel prices encourage modernization investments in the sector world wide.
Project owner: OJSC ‘Alchevsk Iron and Steel Works’ AIWS • Key employer in Alchevsk city (24 thousand employees from 118 thousand inhabitants). • Typical post-soviet vintage of technologies and depreciation: high energy intensity and poor general environmental performance relative to comparable facilities in OECD countries. • Main shareholder: Industrial Union of Donbas, one of the largest industrial groups in Ukraine • IUD acquired steel plants in Hungary and Poland that facilitate access to EU export market
Project context JI project is a part of the wider modernization program of the whole iron/steel production process which started in 2004 Objectives of modernization • More efficient technologies • improved environmental performance • Improved process efficiency • increased capacity • upgrade the quality and range of steel products
Generic steel mill production process Alchevsk JI project focus
Baseline Scenario Project Scenario Project boundaries
Technical scope • Elimination of existing old Open Hearth Furnace and Blooming Mill • Installation of two LD Converters • Installation of a twin ladle furnace (300 t / 50 MVA) • Installation of a Vacuum Tank Degassing Plant • Installation of 2 Continuous 2-strand Slab Casters • Reconstruction and installation of new oxygen blocks All this with 2 times increased steel output!
Emissions reductions • Emission Reduction Units (ERUs) = 934 thousand tons CO2 eq./year (4.67 million tons over a five years ) • Sources of emission reduction: • reduced use of natural gas in open heart furnaces in comparison with converters, • reduced use of blast furnace gas in blooming mill with saved gas utilized in an existing on site combined heat and power plant to replace natural gas and grid electricity, • reduced use of raw materials, energy and steel in converters and continuous casting.
Investment analysis: Financing • Total project cost $944 million • Financing: 30% equity, 70% loans • Evolution of the debt structure reflects a growing confidence of financial institutions in AISW and its shareholder IUD: • 2003: Euro 140M trade finance package for new equipment by the Swiss trading company, • 2003: Euro 350 million 3-years finance facility was syndicated by Societe Generale – some for CAPEX, • 2004: long term US$100 million direct loan and $250 million syndicated lending facility for CAPEX • 2006: US$ 200 million raised from the consortium of Ukrainian commercial banks
Role of carbon finance • Sale of ERUs US$14 million per year, between 2008 and 2012 (US$70 million total). • ERU = roughly 7.4% of investment cost (undiscounted), but less than 1% of total operational revenue • Only 1 million ton (about 20% of total) will be sold to the Netherlands European Carbon Facility through the World Bank. • NECF absorbs project development and determination risks; hence its price NECF lower than expected average sale price. Other buyers anticipated to pay more for lower risk once the project is successfully determined and ERPA signed.
Financial analysis • Relatively high financial rates of return (FIRR) both for baseline and project scenarios • FIRR for baseline (29.5%) higher than for project, with or without carbon revenues • NPV of the project is larger than in the baseline • Volatility of slab prices have significant impact on financial performance of the project (sensitivity analysis). • Carbon finance has small impact on FIRR, but its significance would increase if slab prices fell (risk cusion).
Baseline is technically feasible, with less risks and higher financial return • Implementation of the project is financially attractive to AISW, but rehabilitation of currently used older technologies (OHFs and ingot casters) is even more financially attractive and less risky • Open heart furnaces (OHFs) represent obsolete technology by international standards, but are still a typical business practice in Ukraine and Russia • So large-scale project has not been implemented in the steel sector of Ukraine before. • Construction risks and operational risks high and well managed by project company
Barriers that would prevent project implementation • Financing has been the main barrier for the project. With a total investment of US$943.7 million, the project ranks among the largest investments made by private investors in Ukraine, • Domestic bank credit small and short term • Foreign finance of Ukrainian corporate entity on such a scale still uncommon • Carbon finance revenue provide additional early cash flow less dependent on commercial risks; • Additional comfort for lenders through due diligence by the carbon investors and the World Bank. • Improved environmental performance also important factor to undertake project (civil society and access to EU market)
Value added of carbon finance • JI was crucial in making this project financeable • AISW would not implement the project without considering carbon finance
Contact Grzegorz Peszko Senior Environmental Economist, ECSSD Europe and Central Asia Region The World Bank 1818 H Street N.W., Mail H5-503 Washington, DC 20433 USA gpeszko@worldbank.org Phone: (1-202) 473-4767