Upgrade of Atlas TAS S. EVRARD July 19th 2009
Agenda New shieldings New RP calculations Protection against overpressure Motorization (TAS alignment) Survey issues Cooling Schedule AOB
Protection against overpressure By O. Beltramello
Cooling • Demineralized water • Routing agreed by integration (J-P Corso) • UJ 14 RB14 • UJ16 RB16 • Stainless steel pipes 2 x DN15 4 X DN12 • Flexibles EPDM/Kevlar rad-hard 4m long • Adjustable circuit pressure • Target : installation in August
Drawing LHCTAS0044
Pics RB14 RB16