Transmission & Distribution: Indian Scenario - An Overview

Transmission & Distribution: Indian Scenario - An Overview. S.C. Misra Director(Projects) Power Grid Corpn. of India Ltd. Power System in India. Electricity is a concurrent subject - both State and Central Govt. responsible for development & management of this sector

paul2
Download Presentation

Transmission & Distribution: Indian Scenario - An Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Transmission & Distribution: Indian Scenario - An Overview S.C. Misra Director(Projects) Power Grid Corpn. of India Ltd.

  2. Power System in India • Electricity is a concurrent subject- • both State and Central Govt. responsible for development & management of this sector • State Electricity Boards (SEBs) responsible for wheeling of power from state generating units and state level IPP’S • POWERGRID – the Central transmission utility wheels power of central generating utilities and interstate mega IPP’s • Power distribution responsibility is generally with SEB’s / Private distribution utilities • 3 levels for Grid management system adopted namely State, Regional & National (under progress)

  3. Hierarchy of Indian Power System

  4. Power Scenario - Present • Installed capacity - 107,000 MWCoal – 71% Hydro – 25% Nuclear & others – 4% • Peak demand Peak power - 82,000 MW Energy (average) - 1430 MU/day • Availability Peak power - 71,260 MW Energy (average) - 1325 MU/day • Shortage Peak power - 10,300 MW (12.6%) Energy - 107 MU/day (7.5%)

  5. Transmission - Present • Figs. are in ckt. km • State Central Total (POWERGRID) • HVDC 1,504 4,420 5,924 • 800 KV 400 550 950 • 400 kV 13,000 39,000 52,000 • 220/132 kV 2,06,000 9000 2,15,000 • Transmission loss: 3 - 4% considered reasonable as per international standards. • Application of State-of-the-art technologies - HVDC bipole, • HVDC back-to-back, SVC, Series Compensation, FACTS etc. • Application of improved O&M technologies– Hotline maintenance, Emergency Restoration System, Thermovision scanning etc.

  6. Demand - Supply Scenario – by 2012 • Projected Peak Demand - 157,000 MW (as per 16th EPS) • Capacity addition envisaged– • In 10th Plan - 45,000 MW • In 11th Plan - 55,000 MW

  7. Regional to National level Planning • Uneven disposition of energy resources • Major Hydro resources in Arunachal Pradesh, H.P and J&K • Coal reserves mostly in Bihar/Orissa/West Bengal • Unbalanced growth of different regions • Surplus situation in Eastern Region, while deficit in others • Difficulties in day-to-day operation • Optimisation of generation capacity addition • Utilising time diversity • Spinning reserve optimisation, mutual support • Poor Hydro-thermal mix • Poor ratio – 25:75, Eastern Region – 12:88

  8. Future Transmission – Strategy Change in approach • Bulk power transmission over long distances • Transmission Planning & development at National level • Establishment of sufficient no. of inter-regional links inter-connecting different regions

  9. Major Considerations • Conservation of Right-of-Way • Avoidance of Forest • Flexibility to accommodate uncertainty in generation addition • Minimisation of Transmission cost

  10. Technology Integration • Large investment is required • Scarcity in Right-of-Way • Hence, there is a need to optimally utilise the existing transmission infrastructure by enhancing transmission capacity

  11. Technology for optimal utilisation • Series compensation /FACTS like TCSC • Line can be loaded upto its Thermal capacity. • Higher final Conductor Temperature – 850/ 950C • Uprate loadability to about 30-50% more than existing 750C . • Increase in capital cost 1-2% • Multi-conductor bundle (tripple/quad.) • Bulk power transfer over moderate distance. • Uprating of line by using Alternate Conductor System • High temp. endurance (200 deg C)conductor like INVAR, ACSS, Gap etc.

  12. Upgradation to Higher voltage • Upgrading the existing lower voltage line to next higher voltage increases power transfer capacity with less investmentand practical option. • POWERGRID has developed design and done actual case studies for upgradation of • 66 kV D/c to 132 kV D/c • 132 kV D/c to 400 kV S/c • 220kV D/c to 400 kV S/c • Upgradation of Kishtwar - Kishenpur 220 kV D/c to 400 kV S/c line is being carried out by POWERGRID to increase power transfer capability by 1.8 times

  13. Technology for future expansion • Utilisation of existing capacity will not be sufficient to meet the long term transmission requirement • Adoption of following technologies would also be required: • Next higher transmission voltage – 800kV • Hybrid EHVAC and HVDC system • Compact lines

  14. Next Higher voltage • 765 kV already introduced as next higher voltage • largetransfer capacity, low losses, lower cost/MW/km • Suitable for evacuation from Mega projects • Reasons: Large unit size, scope for immediate future generation expansion, less R-O-W & compensation, availability of strong 400 kV underlying network. • Needs careful attention on Insulation Design, Reactive Power Management and Operational aspects • More than 75% reactive compensation. • Chances of resonant-overvoltages. • Voltage controlled switched shunt reactors. • Maintain large source strength.

  15. HVDC Transmission • Long distance point-to-point bulk power transmission • Asynchronous HVDC links are already under operation • Talcher-II Transmission System • Generation in ER, beneficiaries in SR situated about 1500 kms. away • Would acts as separator between SR and the rest of synchronously connected grid. • Power transfer capacity of the order of 3000MW over long distance is already under operation with higher voltage like  600kV in the world

  16. Compact Lines • Guyed V tower, Chainette tower etc. can be adopted so that space occupied by the tower base can be reduced. • Compactness in the line by • Optimisation of clearances • Use of insulated cross-arms • Phase spacers. • Compactness would increase SIL by 15-20% of traditional line • POWERGRID already designed 400kV compact line

  17. PLAN FOR NATIONAL GRID - A PHASED DEVELOPMENT Phase – 1 – Already completed in 2002 • Interconnection of Regional Grids through HVDC Back-to-Back links having cumulative capacity of 5000 MW Phase – 2 – Partly completed – by 2006-07 • Hybrid system comprising of high capacity HVDC and HVAC lines (both 765 kV and 400 kV) • 2000MW, 1400kms long HVDC bipole between Eastern and Southern regions – completed • 400kV synchronous interconnections between Eastern and Western regions resulting into synchronous operation of power system having 50,000MW capacity - completed • Most of transmission lines would be part of associated transmission system of large sized generation project. • Cumulative inter-regional capacity would be 23,000 MW Phase – 3 – to be completed by 2012 • Ring of 765 kV transmission lines inter-connecting ER, WR and NR • Cumulative capacity would be 30,000 MW

  18. Growth of Energy exchange between ER & Other Regions • All India energy exchange in 2002-03 : 12000 MU

  19. Benefits of inter-regional energy exchange • For transfer of surplus power from ER to other regions, inter-regional links being developed progressively • In 1996-97, total inter-regional transfer capacity was 1200MW, which is now 8000MW • Inter-regional energy exchange increased to 12000MU in 2002-03 out of which 9000MU from ER • Export of energy from ER leads to • Saving in fixed cost for ER constituents by about Rs. 1350 Cr. • Average 2000MW power exported from ER. Hence, investment of about Rs. 8000 Cr. deferred against addition of equivalent generation capacity by deficit regions.

  20. Benefits of National Grid • Reduction in capacity addition requirement by about 13750 MW--- hence saving on investment of Rs. 55,000 crore. (due to peak time diversity and saving in spinning reserve) • Saving in operational cost – Rs. 1200 Cr per annum • Transmission highway would enable setting up of large pit head stations having lower cost of energy Savings on account of this -Rs. 9000 crores per annum. • In addition, Nation’s investment towards fuel transportation infrastructure could be avoided. • Better overall hydro-thermal mix • Very low for ER and WR ( ER – 15 : 85, WR - 17 : 83 ) – affecting grid operation • With National Grid, it would become 33 : 67 on all India basis.

  21. Phase – II & III

  22. Growth of Cumulative capacity of Inter-regional links

  23. Present State of Distribution • Distribution is the Weakest link in the entire power chain • Distribution is characterised by inefficiency – • High losses – both technical and non-technical • Inadequate metering • Interruption on power supply • Unplanned growth – weak network • Poor quality • Tardy record in billing and revenue collection – weak financial health of utilities

  24. Distribution Reforms • APDRP initiated by GoI to improve the distribution system in the country with following objectives : a) Make the distribution circles commercially viable by reducing the aggregate Technical and Commercial loss (ATC) b) Improvement in quality of power supply c) Customer satisfaction • Govt. of India budgeted an outlay of about Rs. 40,000 Crores for next 5 years. • Govt of India appointed POWERGRID & NTPC as lead Advisor cum Consultant (AcC)

  25. POWERGRID’s Role in APDRP • POWERGRID assigned 81 nos. of circles in 18 States all over the country • For these circles schemes for improvement in distribution system approved by MOP at total cost of about Rs 5000 Crores. Schemes covers – • 100% metering at consumers & system level • Energy Audit and Accounting • Upgradation/strengthening of sub-transmission and distribution network including revamping of S/s and DTs • In addition schemes of about Rs.850 crores being executed by POWERGRID in various States on bilateral agreement basis. • POWERGRID is also carrying out Rural Electrification works in about 2600 villages in Bihar

  26. Thank You Thank You